This pre-solicitation notice describes a federal construction contract opportunity to renovate approximately 11,000 square feet of space on the 7th floor of Building 111 at the Clement J. Zablocki VA Medical Center in Milwaukee, Wisconsin. The project scope includes demolishing existing interior spaces, renovating areas for a relocated GI Procedure Clinic, and updating mechanical, electrical, plumbing, medical gas, fire protection, and pneumatic tube systems. The contract value is estimated between $2 million and $5 million. The North American Industry Classification System code for this procurement is 236220 with a size standard of $39.5 million. The solicitation is scheduled to be posted to beta.SAM.gov on or about October 15, 2020 with a bid opening of November 16, 2020. This opportunity is set aside for Service-Disabled Veteran-Owned Small Businesses.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Renovate 7AN for Endoscopy Lab Project # 695-19-107
For the
Department of Veterans Affairs Clement. J. Zablocki Veterans Medical Center
Milwaukee, WI. 53295
PROJECT MANUAL
100% Construction Documents Submission
Volume 1 of 2
08/21/2020
GUIDON DESIGN INC.
RING AND DUCHATEAU, LLP
PROJECT CONTACTS:
OWNER: CLEMENT J. ZABLOCKI VA MEDICAL CENTER
Attn: Jim Beier 5000 W. National Avenue Milwaukee, Wisconsin 53295 Phone: 414.384.2000 x 47297 Email: james.beier@va.gov
ARCHITECT: GUIDON DESIGN INC.
Attn: David Vallandingham 1221 N. Pennsylvania Street Indianapolis, Indiana 46202 Phone: 317.800.6388 x 130 Email: dvallandingham@guidondesign.com
M/E/P ENGINEER: RING & DUCHATEAU, LLP
Attn: Michael McGann 17400 W. Capitol Drive Brookfield, WI 53045 Phone: 414.778.7451 Email: mmcgann@ringdu.com
ISSUE DATE: August 21, 2020
Milwaukee VAMC 08-01-19
695-19-107 Renovate 7AN for Endoscopy Lab 100% Construction Documents
Milwaukee, WI 53295 August 21, 2020
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS VOLUME 1
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 03-20
01 01 10 SN Special Notes
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 03-20
01 33 23 Shop Drawings, Product Data, and Samples 05-17
01 35 26 Safety Requirements 07-20
01 74 19 Construction Waste Management 09-13
01 81 13 Sustainable Construction Requirements 10-17
01 91 00 General Commissioning Requirements 10-15
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
02 82 11 Traditional Asbestos Abatement 04-19
02 82 13.13 Glovebag Asbestos Abatement 09-15
02 82 13.19 Asbestos Floor Tile and Mastic Abatement 09-15
DIVISION 03 – CONCRETE
03 30 53 Cast-in-Place Concrete 07-19
DIVISION 05 – METALS
05 50 00 Metal Fabrications 08-18
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17
06 20 00 Finish Carpentry 08-16
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 13 Thermal Insulation 10-17
07 84 00 Firestopping 02-16
07 92 00 Joint Sealants 10-17
07 95 13 Expansion Joint Cover Assemblies 02-16
DIVISION 08 - OPENINGS
Milwaukee VAMC 08-01-19
00 01 10-2
08 11 13 Hollow Metal Doors and Frames 08-16
08 14 00 Interior Wood Doors 02-16
08 31 13 Access Doors and Frames 02-16
08 71 00 Door Hardware 04-20
08 71 13.11 Low Energy Power Assist Door Operators 08-16
08 80 00 Glazing 10-15
08 90 00 Louvers and Vents 05-15
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 02-15
09 06 00 Schedule for Finishes 04-15
09 22 16 Non-Structural Metal Framing 06-18
09 29 00 Gypsum Board 04-20
09 51 00 Acoustical Ceilings 12-18
09 65 13 Resilient Base and Accessories 02-16
09 65 16 Resilient Sheet Flooring 05-18
09 65 19 Resilient Tile Flooring 05-18
09 91 00 Painting 01-16
DIVISION 10 – SPECIALTIES
10 11 13 Chalkboards and Markerboards 10-15
10 14 00 Signage 10-15
10 21 23 Cubicle Curtain Tracks 05-15
10 26 00 Wall and Door Protection 10-15
10 28 00 Toilet, Bath, and Laundry Accessories 02-16
10 44 13 Fire Extinguisher Cabinets 08-18
DIVISION 11 – EQUIPMENT
11 73 00 Ceiling Mounted Patient Lift System 08-20
DIVISION 12 – FURNISHINGS
12 24 00 Window Shades 08-17
12 32 00 Manufactured Wood Casework 09-15
12 36 00 Countertops 12-18
12 59 00 Systems Furniture
DIVISION 14– CONVEYING EQUIPEMENT
14 92 00 Pneumatic Tube System
Milwaukee VAMC 05-01-20
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GENERAL
GI000 COVER SHEET
GI101 LIFE SAFETY PLAN
GC101 INFECTION CONTROL/PHASING PLAN
HA101 HAZARDOUS MATERIAL REMOVAL PLAN
ARCHITECTURAL
AE001 ARCHITECTURAL SYMBOLS AND ABBREVIATIONS
AE002 WALL TYPES
AD101 SEVENTH FLOOR DEMOLITION PLAN
AD102 SIXTH FLOOR REFLECTED CEILING PLAN (DEMO/NEW WORK)
AE101 SEVENTH FLOOR ARCHITECTURAL PLAN
AE102 SEVENTH FLOOR DIMENSION PLAN
AE111 SEVENTH FLOOR REFLECTED CEILING PLAN
AE501 BUILDING DETAILS
AE502 LEAD SHIELDING DETAILS
AE601 DOOR AND WINDOW SCHEDULE
AI101 SEVENTH FLOOR FINISH AND WALL PROTECTION PLAN
AI201 INTERIOR ELEVATIONS AND ENLARGED PLANS
AI202 INTERIOR ELEVATIONS AND ENLARGED PLANS
AI203 INTERIOR ELEVATIONS AND ENLARGED PLANS
AI204 INTERIOR ELEVATIONS AND ENLARGED PLANS
AI205 INTERIOR ELEVATIONS AND ENLARGED PLANS
AI501 INTERIOR FINISH AND CASEWORK DETAILS
AI601 FINISH SCHEDULES
AI901 SIGNAGE PLAN
AI902 SIGNAGE TYPE
QH101 SEVENTH FLOOR FIXED EQUIPMENT FLOOR PLAN
IF101 SEVENTH FLOOR FURNITURE PLAN
IF102 SEVENTH FLOOR FURNITURE PLAN ELEVATIONS
FIRE PROTECTION
FP001 FIRE SUPPRESSION SYMBOLS, ABBREVIATIONS AND SHEET INDEX
FPD107 SEVENTH FLOOR DEMOLITION FIRE SUPPRESSION PLAN
FP107 SEVENTH FLOOR FIRE SUPPRESSION PLAN
PLUMBING
PS001 PLUMBING SYMBOLS, ABBREVIATIONS AND SHEET INDEX
PD106 SIXTH FLOOR DEMOLITION FLOOR PLAN
PD107 SEVENTH FLOOR DEMOLITION PLAN
DD107 SEVENTH FLOOR DEMOLITION MEDICAL GAS PLAN
PL106 SIXTH FLOOR PLUMBING PLAN
PL107 SEVENTH FLOOR PLUMBING PLAN
DG107 SEVENTH FLOOR MEDICAL GAS PLAN
PL300 MASH PLUMBING PLAN
00 01 15 - 2
PL400 PLUMBING ISOMETRICS
PL500 PLUMBING DETAILS AND SCHEDULES
MECHANICAL
MI000 MECHANICAL SYMBOLS, ABBREVIATIONS, SHEET INDEX
MD101 MECHANICAL DEMOLITION FLOOR PLAN - 7TH FLOOR
MD102 MECHANICAL DEMOLITION FLOOR PLAN - 6TH FLOOR
MH101 MECHANICAL DUCTWORK FLOOR PLAN - 7TH FLOOR
MH102 MECHANICAL DUCTWORK FLOOR PLAN - 8TH FLOOR
MP101 MECHANICAL PIPING FLOOR PLAN - 7TH FLOOR
MM400 ENLARGED PLANS AND SECTIONS
MM500 MECHANICAL DETAILS
MM501 MECHANICAL DETAILS
MM502 MECHANICAL DETAILS
MM600 MECHANICAL SCHEDULES
MM601 MECHANICAL SCHEDULES
MM602 MECHANICAL SCHEDULES
MM603 MECHANICAL SCHEDULES
ELECTRICAL
EI000 SYMBOLS, ABBREVIATIONIS AND SHEET INDEX
ED101 SEVENTH FLOOR - DEMOLITION
EL101 SEVENTH FLOOR PLAN - LIGHTING
EP100 SECOND FLOOR PLAN
EP101 SEVENTH FLOOR PLAN - OVERALL
EP102 SEVENTH FLOOR PLAN - POWER
EP103 PARTIAL ROOF PLAN - POWER
EP300 ENLARGED PLANS
EP301 ENLARGED PLANS
EP400 ONE-LINE SYMBOLS
EP401 POWER RISERS
EP500 DETAILS LIGHTING
EP501 DETAILS LIGHTING
EP510 DETAILS POWER
EP600 LIGHTING SCHEDULES
EP601 SCHEDULE POWER
EP602 SCHEDULES POWER
ET000 SYMBOLS, ABBREVIATIONS AND SHEET INDEX
ET101D SEVENTH FLOOR - TECHNOLOGY DEMOLITION
ET101 SEVENTH FLOOR PLAN - TECHNOLOGY
ET102 SEVENTH FLOOR PLAN - SYSTEMS
ET500 DETAILS TECHNOLOGY
ET501 DETAILS TECHNOLOGY
ET600 SCHEDULES
REFERENCE
GUL101 FACILITY SIGNOFF
GUL102 GEN. INFO
GUL102.1 GEN. INFO
GUL103 ATTACHMENT
GUL104 PROJECT DETAILS
GUL104.1 PROJECT DETAILS
GUL104.2 PROJECT DETAILS
00 01 15 - 3
GUL104.3 PROJECT DETAILS
GUL104.4 PROJECT DETAILS
GUL105 GI ENODSCOPY - 7207
GUL106 SPECIAL EXAM RM - 7215
GUL107 FLUOROSCOPY - 7230
GUL109 PREP/RECOVERY - 7233
GUL110 GI ENDOSCOPY - 7236
GUL111 GI ENDOSCOPY 7244
GUL112 7TH FLOOR OVERALL
A-101 SIEMENS - ARTIS ZEE MULTI-PURPOSE SITE SPECIFIC DRAWING
A-102 SIEMENS - ARTIS ZEE MULTI-PURPOSE SITE SPECIFIC DRAWING
S-101 SIEMENS - ARTIS ZEE MULTI-PURPOSE SITE SPECIFIC DRAWING
E-101 SIEMENS - ARTIS ZEE MULTI-PURPOSE SITE SPECIFIC DRAWING
E-102 SIEMENS - ARTIS ZEE MULTI-PURPOSE SITE SPECIFIC DRAWING
E-501 SIEMENS - ARTIS ZEE MULTI-PURPOSE SITE SPECIFIC DRAWING
M-501 SIEMENS - ARTIS ZEE MULTI-PURPOSE SITE SPECIFIC DRAWING
SKYTRON-00 SKYTRON REFERENCE DRAWING
SKYTRON-00A SKYTRON REFERENCE DRAWING
SKYTRON-01A SKYTRON REFERENCE DRAWING
SKYTRON-02A SKYTRON REFERENCE DRAWING
SKYTRON-03A SKYTRON REFERENCE DRAWING
SKYTRON-A1 SKYTRON REFERENCE DRAWING
SKYTRON-A1.1 SKYTRON REFERENCE DRAWING
SKYTRON-A2 SKYTRON REFERENCE DRAWING
SKYTRON-A3 SKYTRON REFERENCE DRAWING
SKYTRON-A4 SKYTRON REFERENCE DRAWING
SKYTRON-B1 SKYTRON REFERENCE DRAWING
SKYTRON-B1.1 SKYTRON REFERENCE DRAWING
SKYTRON-B2A SKYTRON REFERENCE DRAWING
SKYTRON-B2B SKYTRON REFERENCE DRAWING
SKYTRON-B3 SKYTRON REFERENCE DRAWING
SKYTRON-B4A SKYTRON REFERENCE DRAWING
SKYTRON-B4B SKYTRON REFERENCE DRAWING
SKYTRON-B5A SKYTRON REFERENCE DRAWING
SKYTRON-B5B SKYTRON REFERENCE DRAWING
SKYTRON-C1 SKYTRON REFERENCE DRAWING
SKYTRON-C1.1 SKYTRON REFERENCE DRAWING
SKYTRON-S1A SKYTRON REFERENCE DRAWING
SKYTRON-S1B SKYTRON REFERENCE DRAWING
SKYTON-S SKYTRON REFERENCE DRAWING
PT-2.07A SWISSLOG - PNEUMATIC TUBE ROUTE
- - - END - - -
Milwaukee VAMC 03-01-20 i
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 DISPOSAL AND RETENTION
1.9 PROTECTION OF EXISTING STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS
1.10 RESTORATION
1.11 PHYSICAL DATA
1.12 PROFESSIONAL SURVEYING SERVICES
1.13 LAYOUT OF WORK
1.14 AS-BUILT AND MEP COORDINATION DRAWINGS
1.15 WARRANTY MANAGEMENT
1.16 USE OF ROADWAYS
1.17 CONTRACTOR'S FIELD OFFICE
1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.19 TEMPORARY USE OF EXISTING ELEVATORS
1.20 TEMPORARY USE OF NEW ELEVATORS
1.21 TEMPORARY TOILETS
1.22 AVAILABILITY AND USE OF UTILITY SERVICES
1.23 NEW TELEPHONE EQUIPMENT
1.24 TESTING AND COMMISSIONING
1.25 INSTRUCTIONS AND O&M MANUALS
1.26 GOVERNMENT-FURNISHED PROPERTY
ii
1.27 RELOCATED EQUIPMENT
1.28 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT
1.29 CONSTRUCTION SIGN
1.30 SAFETY SIGN
1.31 PHOTOGRAPHIC DOCUMENTATION
1.32 FINAL ELEVATION Digital Images
1.33 HISTORIC PRESERVATION
1.34 VA TRIRIGA CPMS
695-19-107 Renovate 7AN for GI/GU 100% Construction Documents
Milwaukee, WI 53295 August 7, 2020
01 00 00 - 1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to Specification 01 35 26 for Safety and Infection Control requirements.
1.2 GENERAL INTENTION
A. See attached Scope of Work.
B. Visits to the site by Bidders may be made only as described in the solicitation in accordance with FAR 52.236-27 Site Visit
(Construction).
C. Offices of Guidon Design Inc., as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. All employees of Contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access. Refer to Specification 01 01 10-SN for fingerprint, badging, construction door access and parking requirements.
1.3 STATEMENT OF BID ITEM(S) – IF BID SCHEDULE APPLIES, IT WILL BE PROVIDED
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and specifications (contract documents) may be obtained from the beta.SAM.gov website where the solicitation is posted. Hard copies will be the responsibility and expense of the Contractor(s).
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Submit the Site Security Plan meeting requirements as listed below and in accordance with Specification 01 33 23 SHOP DRAWINGS, PRODUCT DATA
AND SAMPLES within 60 calendar days of the Notice to Proceed meeting.
B. Security Procedures:
1. Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. A Special Agreement SAC form is required for every contract employee. See the SPECIAL NOTES specification for an example of this SAC form. This needs to be supplied to the COR for every contract employee on the jobsite. Even if the Contractor has an active badge, a SAC form is needed for the COR’s records.
01 00 00 - 2
3. Before starting work the Contractor shall give one week’s notice to the Contracting Officer so that security escort arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
4. No photography of VA premises is allowed without written permission of the Contracting Officer.
5. VA reserves the right to shut down the project site and order
Contractor’s employees off the premises in the event of a national emergency. The Contractor may return to the site only with the written approval of the Contracting Officer.
C. Document Control:
1. The Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
2. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
3. All paper waste or electronic media shall be shredded and destroyed in a manner acceptable to the VA.
4. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
D. Motor Vehicle Restrictions
1. Permits shall be issued for Contractor and its employees for parking in designated areas only. See the SPECIAL NOTES Specification.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary storage facilities and utilities may be requested, built or implemented by the Contractor, but only with the approval of the COR.
They shall be provided with labor and materials furnished by the
Contractor without expense to the Government. Any temporary storage or utilities shall be removed by the Contractor at its expense upon completion of the work. Ultimately, working space and space available for storing materials shall be as determined by the COR.
1. Do not store materials and equipment in other than assigned areas.
01 00 00 - 3
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities enough for not more than two workdays. Receipt of materials at Building 111 Loading Dock shall be scheduled prior to 8am or after 4pm to not interfere with regularly scheduled hospital deliveries. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roads, corridors, the existing loading dock and the service elevators as authorized by the COR. When materials are transported or delivered in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. Deliveries at the Loading Dock shall be coordinated with the COR. The Contractor shall not cross curbs, lawns or sidewalks, and shall protect existing conditions from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. The Contractor and all subcontractor employees are subject to rules of
Medical Center applicable to their conduct.
E. Execute work to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space. Refer to the Special
Notes Specification for more details.
F. Utilities Services: Maintain existing utility services in the Medical
Center. Provide temporary facilities (including heat), labor, materials, equipment, connections, and utilities to assure uninterrupted services when needed. Where necessary to cut existing pipes (sanitary drain, roof drain, condensate drain), electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be
01 00 00 - 4 accomplished with all affected circuits or equipment de-energized.
Refer to Specification 26 05 11, 27 05 11 and 28 05 00 for additional requirements.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 14 days in advance of proposed interruption.
Request shall state reason, date, exact time of, and approximate duration of such interruption. Requests shall also include Lock-out/Tag-out location/equipment identified. Refer to Specification
01 35 26 for additional requirements.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions (involving patient curtailment) of any system must be requested, in writing, at least 21 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
G. Phasing:
1. In accordance with the drawings, submit the Phasing Plan meeting requirements as listed below and in accordance with Specification 01
33 23 SHOP DRAWINGS, PRODUCT DATA AND SAMPLES within 60 calendar days of the Notice to Proceed meeting.
2. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the Contractor’s responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work defining the duration of the work with milestone subtasks. Refer to Specification 01 32 16.15 for schedule requirements.
3. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR
01 00 00 - 5 two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to COR and Contractor, generally as follows:
Phase I Pre-Construction Submittals (Periods 1/2/3 from SOW)
Phase II Mobilization; Demo in 7B and Common Corridor
Phase III 7AN IC/CN Barriers*, General Demo 7AN, Abatement
Phase IIIa Coordinated plumbing demo/relocations & HVAC piping demo
Phase IIIb Floor leveling 7AN
Phase IV 7AN New Construction
Phase IVb 7B and Common Corridor off-shift finishes
Phase V Finishes, Punchlist, Closeout, Acceptance, Commissioning
* Coordinate IC/CN barriers with existing 7AS Contract barriers
H. Building 111, 7AN is a vacated ward. Note that 7AS will be under construction at the time of contract award of the 7AN project. The 7AS
(Dialysis) and 7AN (Endoscopy) projects share construction barriers and most likely will share the infection control and construction barrier entrance. The space will be available to the Contractor immediately after issuance of the Notice to Proceed (for pre-construction survey and for the preparation of other pre-construction submittals). Upon approval of all required pre-construction submittals, 7AN will be turned over to Contractor for mobilization and work (Phase II).
1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that Medical
Center operations will not be hindered. Contractor shall be aware that while 7AN will be turned over entirely, there are parts of the building in which he shall permit access to Department of Veterans
Affairs personnel, visitors and patients (7B corridors, B-bank elevators, basement corridor to loading dock/dumpster). Coordinate protection means and alteration work in areas so that Medical Center operations will continue without impact to staff, visitors and patients during the construction period.
2. Contractor shall also note that coordination with neighboring 7AS/
Dialysis construction projects will be required.
I. When 7AN is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance, specifically:
1. Contractor shall maintain a minimum temperature of 40°F.
Construction during winter months may require temporary hydronic heating (equipment shall be supplied by the mechanical Contractor;
VA will supply heating hot water at no cost).
2. Contractor will be allowed to demo and remove fire suppression system in 7AN (sprinklers, detection and alarm equipment) prior to
01 00 00 - 6 general demolition. However, Contractor shall install and maintain a temporary heat detection and alarm system, tied into the Building
111 Fire Alarm system at Graphics (Building 113). It shall be tested monthly with reports to the COR.
J. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
K. Existing Conditions: Upon completion of demo/abatement activities, there may be existing MEP infrastructure in the ceiling to remain
(conduit or piping supporting the 8th floor or 7B for example). The
Contractor shall be responsible for supporting and anchoring this infrastructure (that will remain) to meet current code requirements.
L. Pre-Construction Submittal Requirements (to be complete prior to mobilization):
Preconstruction Submittal Spec Ref. Due
Construction Site Security Plan 01 00 00 60d after NTP
Construction Phasing Plan 01 00 00 60d after NTP
Existing Conditions Survey 01 00 00 60d after NTP
Contractor’s Impact Statement &
Checklist 01 01 10-SN 60d after NTP
Construction Schedule (Initial) 01 32 16.15 30d after NTP
Submittal Register 01 33 23 60d after NTP
Schedule of Values 01 33 23 60d after NTP
SF 1413s (Subcontractor List) 01 33 23 Pursuant to FAR
52.222-11
Surety Bonds & Certificates of
Insurance 01 33 23 Prior to NTP
Accident Prevention Plan 01 35 26 30d after NTP
Activity Hazard Analyses 01 35 26 60d after NTP; or 15d prior to Activity
SSHO and CP Memorandum 01 35 26 60d after NTP
OSHA Certificates and Applicable
Training Documents 01 35 26 60d after NTP
Infection Control Plan 01 35 26 60d after NTP
01 00 00 - 7
Fire Safety Plan 01 35 26 60d after NTP
Construction Waste Management
Plan 01 74 19 60d after NTP
Sustainable Construction
Spreadsheet 01 81 13 30d after Kickoff
1.7 ALTERATIONS
A. Submit the Existing Conditions Survey as listed below and in accordance with Specification 01 33 23 SHOP DRAWINGS, PRODUCT DATA AND SAMPLES within 60 calendar days of the Notice to Proceed meeting.
B. Survey: Before any work is started, the Contractor shall make a thorough survey of 7B and 7AN with the COR and furnish a written report. This report shall list:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur, and which have been agreed upon by Contractor and COR.
C. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government.
Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR
52.243-4 and VAAR 852.243-70).
D. Re-Survey: Thirty days before expected final inspection date, the
Contractor and COR together shall make a thorough re-survey of the areas of areas involved in the Existing Conditions Survey.
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workers in executing work of this contract.
01 00 00 - 8
E. Protection: Provide the following protective measures:
1. Wherever existing building envelope surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled, and equipment moved and/or relocated.
3. Protection of interior of existing structures always, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Refer to Specification 01 74 19 CONSTRUCTION WASTE MANAGEMENT for more information. Materials and equipment accruing from work removed and from demolition activities, shall be disposed of as follows:
1. Reserved items (existing to remain or existing to relocate) which are to remain property of the Government are identified in the drawings. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
1.9 PROTECTION OF EXISTING STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS
A. The Contractor shall preserve and protect all structures and equipment on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the
Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
C. Refer to Articles, "Alterations", "Restoration", and "Operations and
Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
01 00 00 - 9
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.243-70) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.11 PHYSICAL DATA – NOT USED
1.12 PROFESSIONAL SURVEYING SERVICES – NOT USED
1.13 LAYOUT OF WORK – NOT USED
1.14 AS-BUILT AND MEP COORDINATION DRAWINGS
A. The Contractor shall maintain two full size sets of as-built drawings
(“red-lines”) which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built “red-line” drawings shall be made available for the COR review, as often as requested.
C. Contractor shall email as-built “red-line” drawings in the electronic version (scanned PDF) to the COR monthly for progress payment purposes.
D. Contractor shall submit as-built “red-line” drawings in the electronic version (scanned PDF) to the COR at the completion of all new work and after acceptance of the project by the COR. The COR shall forward this
01 00 00 - 10 submittal to the Architect/Engineer for review/approval and so that formal CAD as-built drawings can be developed for the VA.
E. Contractors shall update (as work is completed) the VA electrical, medical gas, domestic plumbing and mechanical piping master schematic books. These books are in the FM office.
F. MEP Coordination Drawings:
1. Contractor shall prepare and provide (via submittal) MEP coordination submittal drawings showing the location of openings through slabs, the pipe sleeves/anchors and hangers inserts, as well as the location and elevation of utility lines, including, but not limited to, conveyor systems, pneumatic tubes, ducts, all existing utilities, and conduits and pipes two (2) inches and larger in diameter. These drawings are required for all areas being remodeled or new and ancillary areas required by such utility runs. Ancillary area drawings to include equal space on each side of main runs from main source to final location. These drawings, including plans, elevations, and sections as appropriate shall clearly show the manner in which the utilities fit into the available space and how they relate to each other and to existing building elements and controls for maintenance operations. Drawings shall be of appropriate scale to satisfy the previously stated purposes, but not smaller than 3/8-inch scale.
2. Drawings must be composite (with distinctive colors for the various trades) including but not limited to HVAC equipment, HVAC ductwork, mechanical piping, plumbing, fire protection, electrical (conduit and fixtures), medical gases, telecommunications, and pneumatic tube. The submitted drawings for a given area of the project shall show the work of all trades which will be involved in that particular area. A complete composite drawing set or complete sets of separate reproducible drawings and CAD files shall be received by the Government not less than 20 days prior to the scheduled start of the work in the area illustrated by the drawings, for the purpose of showing the Contractor's planned method of installation.
3. The objectives of such drawings are to promote carefully planned work sequence and proper trade coordination, in order to assure the expeditious solutions of problems and the installation of lines and equipment as contemplated by the contract documents while avoiding or minimizing additional costs to the Contractor and to the
Government. In coordinating the various installations and in planning the method of installation, if the Contractor finds a conflict in location or elevation of any of the utilities or structural items he shall bring this conflict to the attention of the COR immediately via the RFI process. In doing so, the
Contractor shall explain the proposed method of solving the problem
01 00 00 - 11 or shall request instructions as to how to proceed if adjustments beyond those of usual trades coordination are necessary.
4. Contractor shall include an initial MEP Coordination Drawing (and up to two revisions) as part of original contract. Utilities installation work will not proceed in any area prior to the submission and completion of the Government review of the coordinated drawings for that area, nor in any area in which conflicts are disclosed by the coordination drawings until the conflicts have been corrected to the satisfaction of the COR. It is the responsibility of the Contractor to submit the required drawings in a timely manner consistent with the requirements to complete the work covered by this contract within the prescribed contract time.
1.15 WARRANTY MANAGEMENT – NOT USED
1.16 USE OF ROADWAYS – NOT USED
1.17 CONTRACTOR’S FIELD OFFICE – NOT USED
1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of newly installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the
COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.
Installation of temporary electrical equipment or devices shall be in accordance with the current version of NFPA 70, National
Electrical Code. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned.
Vibrations must be eliminated.
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.
01 00 00 - 12
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.
6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.
B. Temporary use of any equipment or system will NOT start the warranty phase of the equipment or system and does not constitute VA acceptance or Beneficial Occupancy.
C. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
D. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
E. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the Contractor at the Contractor’s expense.
1.19 TEMPORARY USE OF EXISTING B-BANK FREIGHT/SERVICE ELEVATORS
A. Refer to Specification 01 01 10-SN SPECIAL NOTES for more information.
Use of existing B-bank freight and service elevators for handling building materials and Contractor's personnel will be permitted subject to following provisions:
1. Contractor shall note that use of the B-bank elevators (B-9, B-10, B-11 and B-12) is NOT exclusive. These elevators are shared with VA staff (food service), other Contractors, and also for patient transport.
2. Do NOT use an elevator if VA staff are utilizing for patient transport. Wait for a future, empty elevator.
3. B-bank elevators are 6ft wide, 7ft deep and just under 8ft tall.
They are rated at 5,500 lbs. Elevator B-12 has an additional ceiling “bump out” for longer materials (it is 6ft wide, 2ft deep and 2ft tall).
4. Contractor shall install temporary elevator protection as necessary and may leave it in place for the duration of the project if it does not impede usage by others (VA staff, food service carts, patient beds).
01 00 00 - 13
5. Personnel for operating elevators will not be provided by the
Department of Veterans Affairs.
6. If existing cab protections, jambs, floor or elevator systems are excessively worn or damaged during temporary use, they shall be removed and replaced at the Contractor’s expense.
7. All parts of main controller, starter, relay panel, selector, etc., worn or damaged during temporary use shall be removed and replaced with new parts at the Contractor’s expense.
1.20 TEMPORARY USE OF NEW ELEVATORS – NOT USED
1.21 TEMPORARY TOILETS – NOT USED
1.22 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies. The
Contractor shall carefully conserve utilities as they will be furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the COR, shall install and maintain all necessary temporary connections and distribution lines
(temporary lighting). Before final acceptance of the work by the
Government, the Contractor shall remove all the temporary connections, distribution lines, and associated equipment and repair restore the infrastructure as required.
C. Heat: Refer to Article 1.6 (I) for more information. Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials. Obtain heat by connecting to Medical
Center heating hot water distribution system which is available at no-cost to the Contractor.
D. Electricity (for Construction and Testing): Furnish all temporary electric services. Obtain electricity by connecting to the Medical
Center electrical distribution system. Electricity is available at no cost to the Contractor.
E. Water (for Construction and Testing): Furnish temporary water service.
Obtain water by connecting to the Medical Center water distribution system at the 7AS HAC Closet. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the Contractor.
1. Maintain connections, pipe, fittings and fixtures and conserve water. Failure to stop leakage or other wastes will be cause for
01 00 00 - 14 revocation (at COR discretion) of use of water from Medical Center's system.
1.23 NEW TELEPHONE EQUIPMENT – NOT USED
1.24 TESTING AND COMMISSIONING
A. Refer to Specification 01 91 00 and the individual testing and commissioning sections within Specifications 21 08 00, 22 08 00, 23 05
93, 23 08 00, 26 08 00, 27 08 00 and 28 08 00. The Contractor shall coordinate with the VA’s 3rd party Commissioning Agent to provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval by the Commissioning Agent. The Contractor shall document the results of the approved plan and submit for approval with the as built documentation.
B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested. Pre-functional checklist completion is the responsibility of the Contractor.
C. Conduct final tests required in various sections of specifications in presence of the COR and the Commissioning Agent. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
D. Mechanical, Electrical/Technical, Plumbing and Fire Protection systems shall be balanced, controlled, coordinated and commissioned. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed.
E. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably period during which operating and environmental conditions remain reasonably constant and are typical of the design conditions.
F. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.
1.25 TRAINING, INSTRUCTIONS AND O&M MANUALS
A. Training & Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions
01 00 00 - 15 for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed. This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied regarding complete and thorough coverage.
The Contractor shall submit a course outline with associated material to the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the contractual requirements. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COR, does not demonstrate enough qualifications in accordance with requirements for instructors above.
B. Contractor shall furnish Operating and Maintenance manuals (firstly, electronic PDF copies for review and approval, then one set hard copy when VA approves) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
C. O&M Manuals: Operating and Maintenance manuals shall be required for each separate piece of equipment. An equipment-specific O&M shall be included at project completion, via electronic submittal, even if the original submittal included a generic O&M or if the equipment was delivered with a hard copy O&M. Manuals shall be complete, detailed guides for the operation and maintenance of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations.
Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
D. Equipment List: Provide an Excel table equipment list to show all installed electrical and mechanical equipment to include model and serial numbers.
01 00 00 - 16
1.26 GOVERNMENT-FURNISHED PROPERTY – NOT USED
1.27 RELOCATED EQUIPMENT – NOT USED
1.28 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT – NOT USED
1.29 CONSTRUCTION SIGN – NOT USED
1.30 SAFETY SIGN – NOT USED
1.31 PHOTOGRAPHIC DOCUMENTATION
A. During the construction period through completion, provide photographic documentation of construction progress and at appropriate milestones.
B. Photographic documentation elements:
1. Each digital image shall be minimum size of 4 megapixels (MP).
2. Before construction, the construction area, adjacent utilities and adjacent structures surrounding the site shall be documented.
3. Construction progress both inside and outside shall be reasonably documented by photos throughout construction.
4. As-built condition of new utilities shall be documented prior to placing concrete and/or backfilling. This process shall include all underground utilities at the site.
5. As-built conditions of electrical systems shall be documented. As-built conditions of exterior grade elevations shall be documented specifically to capture the waterproofing work.
6. As-built finished conditions of the interior of the basement electrical room shall be documented at certificate of occupancy or equivalent.
7. Upload photos weekly with daily logs capturing the project at different stages of construction.
1.32 FINAL ELEVATION DIGITAL IMAGES – NOT USED
1.33 HISTORIC PRESERVATION
Where the Contractor or any of the Contractor's employees, prior to, or during the construction work, are advised of or discover any possible archeological, historical and/or cultural resources, the Contractor shall immediately notify the COR verbally, and then with a written follow up.
1.34 VA TRIRIGA CPMS – NOT USED
- - - E N D - - -
01 01 10SN - 1
SECTION 01 01 10 (SN)
SPECIAL NOTES
PART 1 - GENERAL
1.1 DESCRIPTION
This section specifies special requirements, processes, procedures, protocols, practices, prohibitions, protections, personnel matters, provisions for unique characteristics of the Milwaukee VAMC, and practical matters pertinent to construction.
1.2 RELATED WORK
A. Section 01 35 26 SAFETY REQUIREMENTS.
B. Section 01 00 00 GENERAL REQUIREMENTS.
C. Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS.
D. Section 01 74 19 CONSTRUCTION WASTE MANAGEMENT.
PART 2 - PRODUCTS (NOT USED)
PART 3 – EXECUTION
3.1 ANTE-ROOM CONSTRUCTION PRACTICES
A. Coordinate construction of the ante-room with NFPA 241 and the
Specification 01 35 26 SAFETY REQUIREMENTS.
B. Type “A” and “B” activities are those in which the fire/smoke hazard risks are MINIMAL. Type “C” and “D” activities are those in which the fire/smoke hazard risks are HIGH. The General
Contractor is obligated to consider the specified containment measures with the costs included within the various contract items of work. Refer to the Appendix for the Construction
Barrier and Fire Risk Assessment Matrix of Precautions for more information.
C. Type A (Minimal Fire Risk Activity/Construction): Provide authority to proceed with work in area, includes a ceiling permit as required, when working above ceilings.
D. Type B (Limited Fire Risk Activity/Construction):
1. Coordinate temporary construction partition installation with
Specification 01 35 26 SAFETY REQUIREMENTS.
2. Provide plastic from floor to ceiling above and seal joints and penetrations. All plastic will be labeled with the VA
ILSM TEMPORARY BARRIER orange tag once installed indicating the start of the three days. At openings, install z-wall overlapping plastic flap barriers or equivalent.
E. Type C (Moderate Fire Risk Activity/Construction): Coordinate temporary construction partition installation…