RFP Document 9 - UNIFORMAT II - Level 3 Detail Reference Guide.xlsx

XLSX spreadsheet 53 KB Posted

Attached to
Construction Manager as Constructor (CMc) Requirement for a New Land Port of Entry (LPOE), Coburn Gore, Maine
Solicitation number
47PB0025R0044
Issued by

About this file

The provided file is a UNIFORMAT II Level 3 Detail Reference Guide, an Excel spreadsheet that presents a comprehensive Work Breakdown Structure (WBS) for construction cost estimation. The document systematically categorizes building construction elements into seven primary categories (A-G) with multiple levels of granular detail, including Substructure, Shell, Interiors, Services, Equipment & Furnishings, Special Construction, and Sitework. Each category is further subdivided into specific components with associated measurement units (UOM) such as square feet (SF), cubic yards (CY), number of items (EA), and other relevant metrics.

The breakdown provides a standardized method for quantifying and organizing construction cost elements, with detailed definitions for each sub-category. For example, under the Substructure (A) section, it defines elements like standard foundations, special foundations, and slab on grade, specifying measurement methodologies. Similarly, other sections like Services (D) break down complex systems into granular components such as conveying systems, plumbing, HVAC, fire protection, and electrical systems, enabling precise cost estimation and project scoping. The guide also includes an Indirect Costs (Z) section that covers design contingencies, general conditions, escalation, and other administrative cost considerations.

View the file

Other files

File Type Posted
Coburn Gore 47PB0025R0044 QA V4 2026 03 02.pdf PDF
47PB0025R0044 Amendment 0005 SF30 2026 03 02.pdf PDF
Attach 29v1 Coburn Gore LPOE FFE Proposal Worksheet 2026 02 26 .xlsx XLSX spreadsheet
RFP Document 4 V1- Agreement CMc REVISED 2026 02 26.pdf PDF
RFP Document 2 V2 - Contract Price Form 47PB0025R0044 2026 02 26.pdf PDF
47PB0025R0044 Amendment 0004 SF30 .pdf PDF
47PB0025R0044_0003 Amendment SF30 .pdf PDF
Attach 28 Coburn Gore Parcel Acquisition 2026 01 13.pdf PDF
Attach 25 Divison 1 Template Sections 2025 07 02.docx DOCX document
RFP Document 2 - Contract Price Form 47PB0025R0044 2026 01 22.pdf PDF
Attach 11 Wage Determination ME20260007 2026 01 02.pdf PDF
Coburn Gore 47PB0025R0044 QA V3 2026 01 22.pdf PDF
47PB0025R0044 1442 dated 2026 01 22.pdf PDF
Attach 26 Coburn Gore Division 01 - Table of Contents 2025 07 02.docx DOCX document
Attch 24 Coburn Gore 47PB0025R0044 QA V2 2025 12 10.pdf PDF
Attch 11 - Wage Determination ME20250007 2025 12 05.pdf PDF
Amendment 0002 to 47PB0025R0044 Final 2025 12 10 .pdf PDF
Attch 24ii- Coburn Gore -Funding Responsibility Tool 2025 12 10.xlsx XLSX spreadsheet
Attch 24iii. Coburn Gore Final Geothermal Study 2025 09 06.pdf PDF
Attch 24i. DS Quick Reference Guide- 2023 LPOE DS Overview 2023 12 06.pdf PDF
Amendment 0001 to 47PB0025R0044 Final 102725.pdf PDF
47PB0025R0044 QA Document 102725.pdf PDF
Pre-Proposal Meeting Final.pdf PDF
Coburn Gore Attendance Sheet 102225.pdf PDF
RFP Document 5 - Reps and Certs CMc MAY 2025.pdf PDF
3. Coburn Gore AE SOW_FINAL 2024 08 06.pdf PDF
5. Colby Coburn Gore Three-Phase Final Report 2022 12 22.pdf PDF
6. P-120 Public Buildings Service Cost and Schedule Management Policy Requirements, October 2022.pdf PDF
7. Coburn Gore LPOE 15Aug25- LPOE POR at final concept.pdf PDF
RFP Document 1 - SF1442-22.pdf PDF
RFP Document 10 - Bid Bond SF24.pdf PDF
RFP Document 14 - Proprietary Information Agreement - Sample Template.docx DOCX document
11. GSA Commissioning Guide September 2020.pdf PDF
16. Coburn Gore LPOE_Spec TOC_Final Concept_Combined 08-11-25.pdf PDF
RFP Document 2 - Contract Price Form 47PB0025R0044.pdf PDF
RFP Document 3 - Solicitation CMc MAY 2025.pdf PDF
RFP Document 4 - Agreement CMc MAY 2025.pdf PDF
RFP Document 6 - Past Performance Questionnaire.docx DOCX document
RFP Document 8 - CASB DS-1.pdf PDF
RFP Document 11 - Wage Determination ME20250007.pdf PDF
1. Coburn Gore LPOE CMc SOW Final 2025 03 27.pdf PDF
2. Coburn Gore Three phase SOW Final 2025 04 04 (1).pdf PDF
17. Coburn Gore Housing_Preliminary Concepts 13June25.pdf PDF
RFP Document 7 - SB Sub Plan - Individual Model - May 2025 - 508 Compliant.docx DOCX document
RFP Document 12 - CBP Non-Disclosure Agreement Form.pdf PDF
RFP Document 13 - CBP Short Term Contractors- Visitor Form_BLANK - Short Term Contractors Template.pdf PDF
4. Coburn Gore LPOE - CMa w CxP SOW 2023 10 12.pdf PDF
10. PBS Core Building Standards Memorandum 2025 02 24.pdf PDF
14. Coburn Gore LPOE - Design Narrative_Final Concept REV 08-11-25.pdf PDF
15. Coburn Gore LPOE_Final Concept Submission_Combined_REV 08-11-25.pdf PDF
Show all 50

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNIFORMAT II Level 3 Detail

GSA OFFICE OF DESIGN AND CONSTRUCTION
UNIFORMAT II WBS COST ELEMENT ORGANIZATION
UNIFORMAT L1UNIFORMAT L2UNIFORMAT L3E UOMQuantity Definition
ASUBSTRUCTURESFFootprint area at grade
A10FOUNDATIONS
A1010STANDARD FOUNDATIONSSFFootprint area at grade
A1020SPECIAL FOUNDATIONSSFFootprint area at grade
A1030SLAB ON GRADESFFootprint area at grade
A20BASEMENT CONSTRUCTIONCYVolume of excavation
A2010BASEMENT EXCAVATIONCYArea of basement plan measured to outside of enclosing wall and average depth of finished grade to underside of slab on grade
A2020BASEMENT WALLSSFArea of wall
BSHELLSFSum area of supported floors and roof structure
B10SUPERSTRUCTURESFSum area of supported floors and roof structure
B1010FLOOR CONSTRUCTIONSFArea of supported floors
B1020ROOF CONSTRUCTIONSFArea of supported roof
B20EXTERIOR ENCLOSURESFArea of exterior walls
B2010EXTERIOR WALLSSFArea of exterior walls
B2020EXTERIOR WINDOWSSFArea of windows
B2030EXTERIOR DOORSEANumber of doors
B30ROOFINGSFGross area of roof
B3010ROOF COVERINGSSFGross area of roof
CINTERIORSSFGross floor area
C10INTERIOR CONSTRUCTIONSFGross floor area
C1010PARTITIONSSFArea of partitions
C1020INTERIOR DOORSLEFNumber of leaves
C1030FITTINGSSFGross floor area
C20STAIRSFLTNumber of flights
C2010STAIR CONSTRUCTIONFLTNumber of flights
C2020STAIR FINISHESSFArea of finished landings, treads, risers
C30INTERIOR FINISHESSFArea of finishing
C3010WALL FINISHESSFArea of finished walls
C3020FLOOR FINISHESSFArea of finished floors
C3030CEILING FINISHESSFArea of ceilings
DSERVICESEA
D10CONVEYINGSTYNumber of stories
D1010ELEVATORS AND LIFTSSTPNumber of stops
D1020ESCALATORS AND MOVING WALKSLFLength of stairs or walks
D1090OTHER CONVEYING SYSTEMSEA
D20PLUMBINGEANumber of fixtures
D2010PLUMBING FIXTURESEANumber of fixtures
D2020DOMESTIC WATER DISTRIBUTIONEANumber of fixtures
D2030SANITARY WASTEEANumber of fixtures
D2040RAIN WATER DRAINAGESFArea of roof
D2090OTHER PLUMBING SYSTEMSEANumber of special fixtures, etc.
D30HVACMBHTotal MBH capacity
D3010ENERGY SUPPLYMBHTotal power of heating system
D3020HEAT GENERATING SYSTEMSMBHTotal power of heating system
D3030COOLING GENERATING SYSTEMSTONTotal power of cooling capacity
D3040DISTRIBUTION SYSTEMSMBHPower
D3050TERMINAL & PACKAGE UNITSMBHPower
D3060CONTROLS & INSTRUMENTATIONMBHPower
D3070SYSTEMS TESTING & BALANCINGMBHPower
D3090OTHER HVAC SYSTEMS AND EQUIPMENTEANumber of special mechanical systems
D40FIRE PROTECTIONSFGross floor area
D4010FIRE ALARM & DETECTION SYSTEMSSFGross floor area
D4020FIRE SUPPRESSION WATER SUPPLY AND EQUIPMENTLFLength of system
D4030STANDPIPE SYSTEMSEANumber of sprinkler heads
D4040SPRINKLERSEANumber of sprinkler heads
D4050FIRE PROTECTION SPECIALTIESEANumber of extinguishers
D4090OTHER FIRE PROTECTION SYSTEMSEAEach system
D50ELECTRICALAMPGross floor area
D5010ELECTRICAL SERVICE & DISTRIBUTIONAMPGross floor area
D5020LIGHTING & BRANCH WIRINGSFFloor area
D5030COMMUNICATIONS & SECURITYSFFloor area
D5090OTHER ELECTRICAL SERVICESSFGross Floor area
EEQUIPMENT & FURNISHINGSSFGross Floor area
E10EQUIPMENTSFGross Floor area
E1010COMMERCIAL EQUIPMENTSFFloor area
E1020INSTITUTIONAL EQUIPMENTSFFloor area
E1030VEHICULAR EQUIPMENTEAPieces of equipment
E1090OTHER EQUIPMENT
E20FURNISHINGSSFFloor area
E2010FIXED FURNISHINGSSFFloor area
E2020MOVEABLE FURNISHINGS
FSPECIAL CONSTRUCTION & DEMOLITIONSFFloor area
F10SPECIAL CONSTRUCTIONSFFloor area
F1010SPECIAL STRUCTURESSFFloor area
F1020INTEGRATED CONSTRUCTIONSFFloor area
F1030SPECIAL CONSTRUCTION SYSTEMSSFArea of room
F1040SPECIAL FACILITIESSFArea of room
F1050SPECIAL CONTROLS AND INSTRUMENTATIONXX
F20SELECTIVE BUILDING DEMOLITIONLS
F2010BUILDING ELEMENTS DEMOLITIONLS
F2020HAZARDOUS COMPONENTS ABATEMENTLS
GSITEWORKACRTotal area of site
G10BUILDING-RELATED SITEWORK
G1010SITE PREPARATIONSACRTotal area of site
G1020SITE IMPROVEMENTSLS
G1030SITE CIVIL/MECHANICAL UTILITIESEAEach utility
G1040SITE ELECTRICAL UTILITIESEASystems total
G20NON-BUILDING-RELATED SITEWORK
G2010SITE PREPARATIONSACRTotal area of site
G2020SITE IMPROVEMENTSLS
G2030SITE CIVIL/MECHANICAL UTILITIESEAEach utility
G2040SITE ELECTRICAL UTILITIESEASystems total
G30OTHER SITE CONSTRUCTIONLS
G3010SERVICE AND PEDESTRIAN TUNNELS
G3020OTHER SITE CONSTRUCTIONXX
ZINDIRECT COSTS
Z10DESIGN CONTINGENCY
Z1010FEASIBILITY STUDY SUBMISSION
Z1020PDS SUBMISSION
Z1030CONCEPT PHASE SUBMISSION
Z1040DESIGN DEVELOPMENT PHASE SUBMISSION
Z105065% CD PHASE SUBMISSION
Z106090% CD PHASE SUBMISSION
Z1070100% CD PHASE SUBMISSION
Z20GENERAL CONDITIONS and PROFIT
Z2010NEW CONSTRUCTION - SINGLE PHASE
Z2020REPAIR AND ALTERATION - SINGLE PHASE
Z2030NEW CONSTRUCTION - MULTI-PHASED
Z2040REPAIR AND ALTERATION - MULTI-PHASED
Z30ESCALATION TO CONSTRUCTION MID-POINT
Z40CONTINGENCY AND RESERVATION
Z4010CONSTRUCTION CONTINGENCY
Z4020RESERVATION
Z50ART-IN-ARCHITECTURE