This document is a Standard Form 30 Amendment of Solicitation/Modification of Contract for the CMc Services, Coburn Gore Land Port of Entry (LPOE) project in Maine. Amendment 0002 extends the receipt of offers deadline from December 17, 2025, to January 28, 2026, at 2:00 pm local time. The amendment updates the solicitation documents by designating specific attachments as Controlled Unclassified Information (CUI) and adding new documents to the Master Attachment List, including housing package plans, renderings, and narratives.
Additional modifications include updating the Davis-Bacon Act Wage Determination for Franklin County, ME, and extending the deadline for questions to January 9, 2026, at 12:00 pm. The amendment also incorporates supplementary documents such as an LPOE Quick Reference Guide, a cross-agency funding responsibility matrix, and a Geothermal Study Final. The solicitation is issued by the PBS Office of Acquisition Management/Capital Project Acquisition Delivery Division, Capital Contracting Branch - Northeast, with the solicitation number 47PB0025R0044.
View the file
Other files
Show all 50
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
9/15/2025
Molly Lewis, Contracting Officer
EQ1PC-25-00330002
PBS Office of Acquisition Management/Capital Project Acquisition Delivery Division Capital Contracting Branch - Northeast 1800 F Street NW Washington , DC 20405 USA
47PB0025R0044
PQAA
PBS Office of Acquisition Management/Capital Project Acquisition Delivery Division Capital Contracting Branch - Northeast 1800 F Street NW Washington , DC 20405 USA
PQAA
12/10/2025
[See Description of Modification Continuation Page]
INSTRUCTIONS (Back Page):
Instructions for items other than those that are self-explanatory, are as follows:
Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.
Item 3 (Effective date).
(1)
(2)
(3)
(4)
(5)
For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.
For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.
For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.
For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.
For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.
(a)
(b)
(c)
(d)
(e)
(f)
Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.
Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.
Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.
Item 12 (Accounting and Appropriation Data).
When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:
(2) Accounting classification Net decrease $
Include subject matter or short title of solicitation/contract where feasible.
Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.
(i)
NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".
Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)
Item 14 (Description of Amendment/Modification).
Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.
Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:
(i) Total contract price increased by $
(ii) Total contract price decreased by $
(iii) Total contract price unchanged.
State reason for modification.
When removing, reinstating, or adding funds, identify the contract items and accounting classifications.
(g)
(h)
When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --
(i) A reference to the letter determination; and
(ii) A statement of the net amount determined to be due in settlement of the contract.
(1)
(2)
(3)
(4)
(5)
(6)
STANDARD FORM 30 (REV. 11/2016) BACK
(1) Accounting classification Net increase $
Description of Modification Continuation Page
Amendment 0002 for Solicitation, 47PB0025R0044 the CMc Services, Coburn Gore LPOE, ME project will be incorporating the following into the Solicitation:
1.) RFP, Solicitation Section I.G., Receipt of Offers. The due date for receipt of offers is extended from 2:00 pm local time, December 17, 2025, to 2:00pm local time, January 28, 2026.
2.) RFP, Solicitation Section I.B., List of Solicitation Documents. The Master Attachment List at Solicitation Documents are modified to designate Attachments 21 Coburn Gore LPOE â Housing Package Plans 2025 12 05, Attachment 22 Coburn Gore LPOE â Housing Package Renderings 2025 12 05 and Attachment 23 Coburn Gore LPOE â Housing Package Narrative 2025 12 08 as Controlled Unclassified Information (CUI).
3.) RFP, Solicitation Section I.B., List of Solicitation Documents. The following documents are added to the Master Attachment List:
a. 21. Coburn Gore LPOE â Housing Package Plans dated 2025 12 05
b. 22. Coburn Gore LPOE â Housing Package Renderings dated 2025 12 05
c. 23. Coburn Gore LPOE â Housing Package Narrative dated 2025 12 08
4.) RFP, Solicitation Section I.B., List of Solicitation Documents have been updated:
a. Davis-Bacon Act Wage Determination â for Franklin County, ME, General Decision Number: ME20250007, Modification 4 (12/05/2025)
5.) RFP, Solicitation Section III.B., Requests for Clarification or Interpretation. The due date for Questions is extended to 09 January 2026 by 12:00pm. The following Questions and Answers have been updated from the Q&A date 10/27/2025 to the V2 Q&A dated 12/10/2025. The attached documents outlined below supplement information to the clarification in the Q&A.
i. LPOE 2023 DS Quick Reference Guide (RFI Line 80) dated 2023 12 06
ii. Cross agency Funding responsibility matrix (RFI Line 62) dated 2025 12 10
iii. Coburn Gore LPOE Geothermal Study Final (RFI Line 64) dated 2025 09 06
Offerors are reminded to acknowledge receipt of this amendment by one of the methods cited in Block 11.
All other information remains the same.
47PB0025R0044/0002
File details come from the government source that posted it. Updated .