47PB0025R0044_0003 Amendment SF30 .pdf
PDF 638 KB Posted
- Solicitation number
- 47PB0025R0044
About this file
This document is Standard Form 30 (Amendment of Solicitation/Modification of Contract), Amendment 0003 to solicitation 47PB0025R0044 issued by PBS Office of Acquisition Management/Capital Project Acquisition Delivery Division, Capital Contracting Branch - Northeast on January 22, 2026. The amendment extends the offer receipt deadline from 2:00 pm local time on January 28, 2026, to 2:00 pm local time on February 25, 2026, for the CMc Services, Coburn Gore LPOE project in Maine. The amendment adds six new attachments to the solicitation: Additional Drawing VHB (Attachment 24), Division 1 Template Sections (Attachment 25), Division 1 Table of Contents (Attachment 26), Overall Impacts document (Attachment 27), Parcel Acquisition document (Attachment 28), and FFE Proposal Worksheet (Attachment 29), all dated between January 20 and January 22, 2026.
The amendment also updates existing solicitation documents including the Statement of Work dated January 22, 2026, SF 1442 form, Contract Price Form, and Davis-Bacon Act Wage Determination for Franklin County, Maine (General Decision Number ME20260007, effective January 2, 2026). Additionally, the deadline for submitting questions and requesting clarifications is extended to February 6, 2026, by 12:00 pm, with updated Questions and Answers (Version 3) dated January 22, 2026, replacing the previous Version 2 dated December 10, 2025. Offerors must acknowledge receipt of this amendment by completing and returning the form or by separate written or electronic communication referencing the solicitation and amendment numbers prior to the extended offer deadline. Failure to acknowledge by the specified deadline may result in offer rejection.
View the file
Other files
Show all 50
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
9/15/2025
Molly Lewis, Contracting Officer
EQ1PC-25-00330003
PBS Office of Acquisition Management/Capital Project Acquisition Delivery Division Capital Contracting Branch - Northeast 1800 F Street NW Washington , DC 20405 USA
47PB0025R0044
PQAA
PBS Office of Acquisition Management/Capital Project Acquisition Delivery Division Capital Contracting Branch - Northeast 1800 F Street NW Washington , DC 20405 USA
PQAA
1/22/2026
[See Description of Modification Continuation Page]
INSTRUCTIONS (Back Page):
Instructions for items other than those that are self-explanatory, are as follows:
Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.
Item 3 (Effective date).
(1)
(2)
(3)
(4)
(5)
For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.
For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.
For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.
For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.
For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.
(a)
(b)
(c)
(d)
(e)
(f)
Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.
Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.
Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.
Item 12 (Accounting and Appropriation Data).
When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:
(2) Accounting classification Net decrease $
Include subject matter or short title of solicitation/contract where feasible.
Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.
(i)
NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".
Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)
Item 14 (Description of Amendment/Modification).
Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.
Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:
(i) Total contract price increased by $
(ii) Total contract price decreased by $
(iii) Total contract price unchanged.
State reason for modification.
When removing, reinstating, or adding funds, identify the contract items and accounting classifications.
(g)
(h)
When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --
(i) A reference to the letter determination; and
(ii) A statement of the net amount determined to be due in settlement of the contract.
(1)
(2)
(3)
(4)
(5)
(6)
STANDARD FORM 30 (REV. 11/2016) BACK
(1) Accounting classification Net increase $
Description of Modification Continuation Page
Amendment 0003 for Solicitation, 47PB0025R0044 the CMc Services, Coburn Gore LPOE, ME project will be incorporating the following into the Solicitation:
1.) RFP, Solicitation Section I.G., Receipt of Offers. The due date for receipt of offers is extended from 2:00 pm local time, January 28, 2026, to 2:00pm local time, February 25, 2026.
2.) RFP, Solicitation Section I.B., List of Solicitation Documents. The following documents are added to the Master Attachment List:
a. Attachment 24. Coburn Gore LPOE - Additional Drawing VHB dated 2026 01 21
b. Attachment 25. Coburn Gore LPOE - Division 1 Template Sections dated 2025 07 02
c. Attachment 26. Coburn Gore LPOE - Division 1 Table of Contents dated 2026 01 20
d. Attachment 27. Coburn Gore Overall Impacts 2026 01 13
e. Attachment 28. Coburn Gore Parcel Acquisition 2026 01 13
f. Attachment 29. Coburn Gore LPOE- FFE Proposal Worksheet dated 2026 01 20
3.) RFP, Solicitation Section I.B., List of Solicitation Documents have been updated:
a. 47PB0025R0044, Coburn Gore LPOE Statement of Work, Dated 2026 01 22
b. Attachment 1, SF1442 dated 2026 01 22
c. Attachment 2 Contract Price Form, 47PB0025R0044 Dated 2026 01 22
d. Davis-Bacon Act Wage Determination â for Franklin County, ME, General Decision Number: ME20260007, Modification 0 (01/02/2026)
4.) RFP, Solicitation Section III.B., Requests for Clarification or Interpretation. The due date for Questions is extended to 06 February 2026 by 12:00pm. The following Questions and Answers have been updated from the V2 Q&A dated 2025 12 10 to V3 Q&A dated 2026 01 22. The attached documents outlined below supplement information to the clarification in the Q&A.
a. Attachment 24. Coburn Gore LPOE - Additional Drawing VHB dated 2026 01 21
b. Attachment 25. Coburn Gore LPOE - Division 1 Template dated 2025 07 02
c. Attachment 26. Coburn Gore LPOE - Division 1 Table of Contents dated 2026 01 20
d. 47PB0025R0044, Coburn Gore LPOE Statement of Work, Dated 2026 01 22
e. Attachment 27. Coburn Gore Overall Impacts 2026 01 13
f. Attachment 28. Coburn Gore Parcel Acquisition 2026 01 13
Offerors are reminded to acknowledge receipt of this amendment by one of the methods cited in Block 11.
All other information remains the same.
47PB0025R0044/0003
File details come from the government source that posted it. Updated .