Revised_Estimate_-_C&G.pdf
PDF 173 KB Posted
- Attached to
- Veterans Memorial Parkway Extension - Clearing & Grubbing for Advance Utility Removal/Relocations
- Solicitation number
- 26-B-109JD
- Issued by
- Volusia County, Florida
About this file
This is a Construction Cost Estimate for Clearing & Grubbing work on the Veterans Memorial Parkway Extension project in Volusia County, Florida (Project #P5894-A). The project encompasses clearing and grubbing activities across the new right-of-way of Veterans Memorial Parkway, temporary construction easements, Kentucky Avenue, and Pond Parcel #100, with work extending from Graves Avenue to Dr. Martin Luther King Boulevard. The estimate details work across approximately 23.50 acres of clearing and grubbing, along with associated sediment control measures, inlet protection, and gopher tortoise relocation. All work must comply with Florida Erosion and Sediment Control Design and Reviewer Manual standards and Best Management Practices. The estimate was prepared by Amir H. Malek, PE (Florida Professional Engineer #72482) and does not specify response dates, bid due dates, site visits, or bidders' conferences.
The total project cost is estimated at $1,538,546.76, which includes mobilization costs of $116,336.24, maintenance of traffic costs of $58,168.12, sediment barrier and inlet protection totaling $34,178.71, clearing and grubbing costs of $1,054,183.68, and gopher tortoise relocation at $75,000.00, with a 15 percent contingency of $200,680.01. Pricing is based on FDOT Statewide Average Unit Cost Data with a date range of April 1, 2025, through March 31, 2026. The estimate does not reference set-asides, incumbent contractors, funding sources, or renewal options.
View the file
Other files
Show all 46
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Construction Cost Estimate Clearing & Grubbing Plans Veterans Memorial Parkway Extension (Graves Ave. to
Dr. Martin Luther King Bltwy.)
Volusia County Project #P5894 -A
FINAL
ITEM
NUMBER
DESCRIPTION UNIT QUANT UNIT PRICE TOTAL
101-1 MOBILIZATION (LUMP SUM) EA 1 $116,336 $116,336.24
102- 1 MAINTENANCE OF TRAFFIC (LUMP SUM) EA 1 $58,168 $58,168.12
104-10-3 SEDIMENT BARRIER LF 9,649 $3.47 $33,482.03
104-18 INLET PROTECTION EA 4 $174.17 $696.68
110-1-1 CLEARING AND GRUBBING AC 23.50 $44,858.88 $1,054,183.68
999-1 GOPHER TORTOISE RELOCATION LS 1 $75,000.00 $75,000.00
PROJECT SUB-TOTAL (W/O MOB. & MOT) $1,163,362.39
PROJECT SUB-TOTAL (W/ MOB. & MOT) $1,337,866.75
CONTINGENCY 15% $200,680.01
TOTAL $1,538,546.76
Estimate Prepared by:
Amir H. Malek, PE Florida Professional Engineer #72482
Pricing Source: FDOT Statewide Average Unit Cost Data Date Range: 2025.04.01 TO 2026.03.31
File details come from the government source that posted it. Updated .