Veterans Memorial Parkway Extension - Clearing & Grubbing for Advance Utility Removal/Relocations
Solicitation number
26-B-109JD
Issued by
Volusia County, Florida

About this file

This is a Utility Work Schedule document issued by the Florida Department of Transportation (FDOT) in coordination with Florida Public Utilities Company for utility relocation and adjustment work associated with the Veterans Memorial Parkway Extension project in Volusia County, Florida. The document outlines the requirements and timeline for Florida Public Utilities to relocate or adjust three separate gas main facilities within the project limits: a 6-inch HDPE main gas pipe between stations MLK 11+80 and MLK 12+80 that crosses existing facilities; a 6-inch HDPE main gas line near and parallel to a storm drain between stations MLK 15+00 and MLK 16+50; and a 4-inch HDPE main gas crossing between stations MLK 16+80 and MLK 26+00. All three utility work activities are dependent on contractor notification and are scheduled to occur during FDOT project construction, with each activity assigned one consecutive calendar day for completion. The utility company project representative is Fernando Van-Leeuwen (561-389-2338) and the field representative is Matt Ryan (561-531-3847).

The utility work schedule document specifies several special conditions and constraints that must be observed during construction. Florida Public Utilities representatives must be present when construction occurs within five feet of the buried gas main, with two weeks' advance notice required. The road contractor is responsible for performing staking with offset and elevation measurements and for completing clearing and grubbing activities prior to Florida Public Utilities' work. In the event of any damage, disturbance, or puncture to gas facilities, the contractor must immediately notify the right-of-way owner, Florida Public Utilities, and the local Fire Department. An emergency contact number of 1-800-427-7712 is provided for nights, weekends, and holidays. The utility work schedule is compatible with FDOT plans dated December 14, 2016, and any deviation from those plans may void the schedule, though the utility company may negotiate a new schedule upon notification of plan changes by FDOT.

View the file

Other files

File Type Posted
Veterans_Memorial_Parkway_Extension_-_Clearing_&_Grubbing_for_Advance_Utility_Removal_Relocations.pdf PDF
Exhibit_FF-_Conflict_Matrix.xlsx XLSX spreadsheet
Exhibit_EE-_UWS_-_Zayo.pdf PDF
Exhibit_DD-_RGBs_-_Zayo.pdf PDF
Exhibit_CC-_No_Conflict_Letter_-_Uniti_Fiber.pdf PDF
Exhibit_BB-_No_Conflict_Letter_-_Lumen.pdf PDF
Exhibit_Z-_UWS_-_Duke_Energy.pdf PDF
Exhibit_Y-_RGBs_-_Duke_Energy.pdf PDF
Exhibit_X-_UWS_-_City_of_Orange_City.pdf PDF
Exhibit_W-_RGBs_-_City_of_Orange_City.pdf PDF
Exhibit_V-_No_Facilities_-_City_of_DeLand.pdf PDF
Exhibit_U-_UWS_-_Spectrum.pdf PDF
Exhibit_T-_RGBs_-_Spectrum.pdf PDF
Exhibit_S-_UWS_-_Century_Link.pdf PDF
Exhibit_R-_RGBs_-_Century_Link.pdf PDF
Exhibit_Q-_UWS_-_ATT-Transmission.pdf PDF
RGBs_-_ATT-Transimission.pdf PDF
Exhibit_O-_Clear_-_No_Facilities-ATT-D.docx DOCX document
Exhibit_N-26-B-109JD,_Payment_and_Performance_Bond.pdf PDF
Exhibit_M-SJRWMD_Permit_Approval.pdf PDF
Exhibit_L-_Sales_Tax_Exemption_Procedures.pdf PDF
Exhibit_K-_BASE-UTILITY01.dwg DWG drawing
Exhibit_J-SURVRD01_VMP.dwg DWG drawing
Exhibit_I-_Project_Survey.pdf PDF
Exhibit_H-_Utility_Adjustment_Sheets.pdf PDF
Exhibit_G-_Pricing_Sheet,_26-B-109JD.xlsx XLSX spreadsheet
Exhibit_F-Roadway_Drainage_-_SS_MOT_Plans.pdf PDF
Exhibit_E-Roadway_Technical_Specifications.pdf PDF
Exhibit_D-_CLEARING_&_GRUBBING_PLANS.pdf PDF
Exhibit_C-Draft_Contract,_26-B-109JD,_C2086.pdf PDF
Exhibit_B-PRIME-SUB_FORM_26-B-109JD.xls XLS spreadsheet
Exhibit_A-_26-B-109JD_Veterans_Memorial_Extension-Clearing_and_Grubbing-Required_Insurance_Limits.pdf PDF
SURVRD01_VMP.dwg DWG drawing
6-Project_Survey.pdf PDF
VMP_-_CLEARING_&_GRUBBING_PLANS.pdf PDF
VMP_-_Ut._Adj._Sheets.pdf PDF
Signed_&_Sealed_VC_Tech_Specs_08.11.25_-_Exhibit_B.pdf PDF
Roadway_Drainage_-_SS_MOT_Plans.pdf PDF
Revised_Estimate_-_C&G.pdf PDF
VMP_-SJRWMD_Permit_Approval.pdf PDF
BASE-UTILITY01.dwg DWG drawing
Conflict_Matrix.xlsx XLSX spreadsheet
Project_Description_-_Scope_of_Work_-_Clearing_&_Grubbing_for_Advance_Utility_Removal-Relocations_5-28-26.docx DOCX document
Construction_Bid_Request_-_Clearing_&_Grubbing_for_Advance_Utility_Removal-Relocations(5.28.26).pdf PDF
PRIME-SUB_FORM_for_Contractors_rev._01.15.2025_(lock_before_publishing).xls XLS spreadsheet
Pricing_Sheet_-_C&G.xlsx XLSX spreadsheet
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Rule 14-46.001 F.A.C

FLORIDA DEPARTMENT OF TRANSPORTATION

UTILITY WORK SCHEDULE

December 14, 2016

Pursuant to Section 337.403 F.S., the UAO and FDOT agree to the UAO’s need for relocation or adjustment to its utilities and FDOT’s need for a schedule for the UAO to effect the relocation or adjustment. This utility work schedule is based on FDOT plans dated in the project information box below. Any deviation by FDOT or its contractor from these plans, may void this utility work schedule. Upon notification by FDOT of a change to these plans, the UAO may negotiate a new utility work schedule. The UAO agrees to notify FDOT and the contractor in writing prior to starting, stopping, resuming, and completing work in accordance with this utility work schedule. The UAO shall obtain a utility permit and comply with requirements of the 2017 Utility Accommodation Manual (UAM) for all work done under this utility work schedule. The UAO is not responsible for events beyond the control of the UAO that could not be reasonably anticipated by the UAO and which could not be avoided by the UAO with exercise of due diligence at the time of the occurrence.

FDOT PROJECT INFORMATION

Financial Project ID: Federal Project ID:

State Road Number: County: VOLUSIA COUNTY

FDOT Plans Dated: District Document No.:

UTILITY AGENCY/OWNER (UAO)

Utility Company: FLORIDA PUBLIC UTILITY

UAO Project Rep: FERNANDO VAN-LEEUWEN Phone: 561-389-2338 E-mail: fvanleeuwen@chpk.com

UAO Field Rep: MATT RYAN Phone: 561-531-3847 E-mail: mryan@chpk.com

UTILITY SIGNATURE

I have reviewed the FDOT plans referenced above and submit this utility work schedule in compliance with UAM Section 5 and agree to be bound by the terms of this utility work schedule.

UAO Rep. Date 1 / 27 / 2026

Name BILLY RODRIGUEZ

Title ENGINEERING TECH

ENGINEER OF RECORD SIGNATURE

I attest this utility work schedule is compatible with the FDOT plans referenced above.

EOR. Date

Name

Title

APPROVAL BY DISTRICT UTILITIES

This utility work schedule is complete and acceptable to FDOT.

FDOT Rep. Date / /

Name

Title

SECTION A: SUMMARY OF UTILITY WORK

The below days are the total numbers of days shown for all activities in Section C of this utility work schedule. The breakdown of how these days are to be incorporated into the FDOT project and the dependence of these days upon the completion of other activities by the UAO or others is shown in Section C.

Days prior to FDOT project construction: Days during FDOT project construction: 3

Amir H. Malek, PE

Principal

2026.03.13

FLORIDA DEPARTMENT OF TRANSPORTATION

UTILITY WORK SCHEDULE

December 14, 2016

Financial Project ID:

Utility Company: FLORIDA PUBLIC UTILITY

FDOT Plans Dated:

SECTION B: UAO SPECIAL CONDITIONS/CONSTRAINTS

1.Florida Public Utilities (FPU) Company representatives must be present when construction is being done within 5-feet of the buried gas main, including for activities as listed in Section C. Please provide 2 week in advance notice of such construction to FPU.

2.Emergency number for nights, weekends, and FPU Holidays is 1-800-427-7712.

3.Contractor shall notify the Right of Way Owner (FDOT, County, or City), FPU and the Fire Department immediately in case of damage, disturbance, puncture, dislocation, cracking, buckling, ect. to the gas main during construction.

4.FPU request for staking with offset and elevation to be performed by the Road Contractor prior to activities as listed in Section C.

5.Clearing/grubbing activities to be performed by the Road Contractor prior to activities as listed in Section C.

6.Work Descriptions:

-Monitor: an FPU Representative or FPU Contractor will be onsite.

-Protect: may include but, not limited to, holding, bracing, shielding (by hand/material or apparatus).

FLORIDA DEPARTMENT OF TRANSPORTATION

UTILITY WORK SCHEDULE

December 14, 2016

Financial Project ID:

Utility Company: FLORIDA PUBLIC UTILITY

FDOT Plans Dated:

SECTION C: UAO’s WORK ACTIVITIES

Act.

No.

Utility Facility

(type, size, material, status)

From

Station/

Offset

To

Station/

Offset

Utility Work Activity

Description

Dependent

Activity TCP Phase

Consecutive

Calendar Days

Prior to During

Const. Const.

6" HDPE MAIN GAS

PIPE BETWEEN S-313 & S-

MLK

11+80

MLK

12+80

(CROSSES)

EXISTING FACILITIES TO

BE RELOCATED /

ADJUSTED AT MLK 11+50

When Notified by

Contractor 1 0 1

6" HDPE MAIN GAS

NEAR & PARALLEL TO

STORM NEAR

S-307 & S-308

MLK

15+00

MLK

16+50

EXISTING FACILITIES TO

BE ADJUSTED AT

11+10 TO 16+80

When Notified by

Contractor 1 0 1

4" HDPE MAIN GAS

CROSSING OF PIPE

BETWEEN

S-301 AND S-302

MLK

16+80

MLK

26+00

EXISTING FACILITIES TO

BE ADJUSTED AT

MLK 22+80

When Notified by

Contractor 1 0 1