Exhibit_EE-_UWS_-_Zayo.pdf

PDF 499 KB Posted

Attached to
Veterans Memorial Parkway Extension - Clearing & Grubbing for Advance Utility Removal/Relocations
Solicitation number
26-B-109JD
Issued by
Volusia County, Florida

About this file

This Utility Work Schedule (UWS) is a Florida Department of Transportation (FDOT) document executed between FDOT and Zayo Group LLC, a utility company, regarding utility relocation and adjustment work for the Veterans Memorial Parkway Extension project (Financial Project ID: P5894) in Volusia County on County Road 484. The schedule authorizes Zayo to perform utility work based on FDOT plans dated February 27, 2026, and establishes a framework for coordinating the utility company's activities with the overall road construction project. Zayo's work will occur during FDOT project construction and consists of three primary activities: installing a proposed 24"x36"x30" handhole at station 163+92.65' with 51.07' right offset (5 calendar days), removing an existing handhole at the same location (2 calendar days), and trenching and connecting three 1.25" HDPE fiber optic ducts between the existing and proposed handhole locations (10 calendar days), for a total of 17 days of work during construction.

The UWS establishes specific conditions and constraints for Zayo's performance, including that relocation activities cannot commence until the utility company receives approved permits and the finalized UWS based on FDOT's road plans. Zayo's inspector must attend the pre-construction meeting and serve as the primary point of contact throughout the project duration. Work is limited to Monday through Friday, 7:30 a.m. to 5:00 p.m., excluding holidays, with any after-hours work requiring advance notice through Zayo's field representative. The road contractor must provide 48-hour notice before construction commencement. Zayo retains access rights throughout the project to monitor and maintain its facilities to ensure service continuity. The document was signed by Engineer of Record Amir H. Malek, P.E., on May 6, 2026, with project contact Jake Sansom, Regional OSP Operations Specialist, serving as both the UAO project representative and field representative.

View the file

Other files

File Type Posted
Veterans_Memorial_Parkway_Extension_-_Clearing_&_Grubbing_for_Advance_Utility_Removal_Relocations.pdf PDF
Exhibit_FF-_Conflict_Matrix.xlsx XLSX spreadsheet
Exhibit_DD-_RGBs_-_Zayo.pdf PDF
Exhibit_CC-_No_Conflict_Letter_-_Uniti_Fiber.pdf PDF
Exhibit_BB-_No_Conflict_Letter_-_Lumen.pdf PDF
Exhibit_AA-_UWS_-_Florida_Public_Utilities.pdf PDF
Exhibit_Z-_UWS_-_Duke_Energy.pdf PDF
Exhibit_Y-_RGBs_-_Duke_Energy.pdf PDF
Exhibit_X-_UWS_-_City_of_Orange_City.pdf PDF
Exhibit_W-_RGBs_-_City_of_Orange_City.pdf PDF
Exhibit_V-_No_Facilities_-_City_of_DeLand.pdf PDF
Exhibit_U-_UWS_-_Spectrum.pdf PDF
Exhibit_T-_RGBs_-_Spectrum.pdf PDF
Exhibit_S-_UWS_-_Century_Link.pdf PDF
Exhibit_R-_RGBs_-_Century_Link.pdf PDF
Exhibit_Q-_UWS_-_ATT-Transmission.pdf PDF
RGBs_-_ATT-Transimission.pdf PDF
Exhibit_O-_Clear_-_No_Facilities-ATT-D.docx DOCX document
Exhibit_N-26-B-109JD,_Payment_and_Performance_Bond.pdf PDF
Exhibit_M-SJRWMD_Permit_Approval.pdf PDF
Exhibit_L-_Sales_Tax_Exemption_Procedures.pdf PDF
Exhibit_K-_BASE-UTILITY01.dwg DWG drawing
Exhibit_J-SURVRD01_VMP.dwg DWG drawing
Exhibit_I-_Project_Survey.pdf PDF
Exhibit_H-_Utility_Adjustment_Sheets.pdf PDF
Exhibit_G-_Pricing_Sheet,_26-B-109JD.xlsx XLSX spreadsheet
Exhibit_F-Roadway_Drainage_-_SS_MOT_Plans.pdf PDF
Exhibit_E-Roadway_Technical_Specifications.pdf PDF
Exhibit_D-_CLEARING_&_GRUBBING_PLANS.pdf PDF
Exhibit_C-Draft_Contract,_26-B-109JD,_C2086.pdf PDF
Exhibit_B-PRIME-SUB_FORM_26-B-109JD.xls XLS spreadsheet
Exhibit_A-_26-B-109JD_Veterans_Memorial_Extension-Clearing_and_Grubbing-Required_Insurance_Limits.pdf PDF
SURVRD01_VMP.dwg DWG drawing
6-Project_Survey.pdf PDF
VMP_-_CLEARING_&_GRUBBING_PLANS.pdf PDF
VMP_-_Ut._Adj._Sheets.pdf PDF
Signed_&_Sealed_VC_Tech_Specs_08.11.25_-_Exhibit_B.pdf PDF
Roadway_Drainage_-_SS_MOT_Plans.pdf PDF
Revised_Estimate_-_C&G.pdf PDF
VMP_-SJRWMD_Permit_Approval.pdf PDF
BASE-UTILITY01.dwg DWG drawing
Conflict_Matrix.xlsx XLSX spreadsheet
Project_Description_-_Scope_of_Work_-_Clearing_&_Grubbing_for_Advance_Utility_Removal-Relocations_5-28-26.docx DOCX document
Construction_Bid_Request_-_Clearing_&_Grubbing_for_Advance_Utility_Removal-Relocations(5.28.26).pdf PDF
PRIME-SUB_FORM_for_Contractors_rev._01.15.2025_(lock_before_publishing).xls XLS spreadsheet
Pricing_Sheet_-_C&G.xlsx XLSX spreadsheet
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Rule 14-46.001 F.A.C

FLORIDA DEPARTMENT OF TRANSPORTATION

UTILITY WORK SCHEDULE

December 14, 2016

Pursuant to Section 337.403 F.S., the UAO and FDOT agree to the UAO’s need for relocation or adjustment to its utilities and FDOT’s need for a schedule for the UAO to effect the relocation or adjustment. This utility work schedule is based on FDOT plans dated in the project information box below. Any deviation by FDOT or its contractor from these plans, may void this utility work schedule. Upon notification by FDOT of a change to these plans, the UAO may negotiate a new utility work schedule. The UAO agrees to notify FDOT and the contractor in writing prior to starting, stopping, resuming, and completing work in accordance with this utility work schedule. The UAO shall obtain a utility permit and comply with requirements of the 2017 Utility Accommodation Manual (UAM) for all work done under this utility work schedule. The UAO is not responsible for events beyond the control of the UAO that could not be reasonably anticipated by the UAO and which could not be avoided by the UAO with exercise of due diligence at the time of the occurrence.

FDOT PROJECT INFORMATION

Financial Project ID: P5894- Veterans Mem Pkwy Ext Federal Project ID: N/A State Road Number: CR-484 County: Volusia FDOT Plans Dated: 02.27.2026 District Document No.: 5

UTILITY AGENCY/OWNER (UAO)

Utility Company: ZAYO Group LLC UAO Project Rep: Jake Sansom Phone: 656-200-2320 E-mail: Jake.Sansom@zayo.com UAO Field Rep: Jake Sansom Phone: 656-200-2320 E-mail: Jake.Sansom@zayo.com

UTILITY SIGNATURE

I have reviewed the FDOT plans referenced above and submit this utility work schedule in compliance with UAM Section 5 and agree to be bound by the terms of this utility work schedule.

UAO Rep. Date / / Name Jake Sansom

Title Regional OSP Operations Specialist

ENGINEER OF RECORD SIGNATURE

I attest this utility work schedule is compatible with the FDOT plans referenced above.

EOR. Date: 2026.05.06 Name Amir H. Malek, P.E.

Title Engineer of Record

APPROVAL BY DISTRICT UTILITIES

This utility work schedule is complete and acceptable to FDOT.

FDOT Rep. Date / / Name

Title

SECTION A: SUMMARY OF UTILITY WORK

The below days are the total numbers of days shown for all activities in Section C of this utility work schedule. The breakdown of how these days are to be incorporated into the FDOT project and the dependence of these days upon the completion of other activities by the UAO or others is shown in Section C.

Days prior to FDOT project construction: 0 Days during FDOT project construction: 17

FLORIDA DEPARTMENT OF TRANSPORTATION

UTILITY WORK SCHEDULE

December 14, 2016

Financial Project ID: P5984- Veterans Mem Pkwy Ext Utility Company: ZAYO Group LLC FDOT Plans Dated: 02.27.2026

SECTION B: UAO SPECIAL CONDITIONS/CONSTRAINTS

1: Zayo Relocation Activities will not commence until receipt of Approved UWS which was created based on FDOT road plans dated on this UWS form, and Approved Permits.

construction letting.

2: Zayo Inspector will be available for the pre-construction meeting in the field and be the point of contact for Zayo Construction for the Road Contractor for the duration of the project.

3: Zayo Working Days are during normal business hours, Monday – Friday, 7:30 am – 5:00 pm (excluding Holidays). Zayo will arrange any work after hours with an advance notice through Zayo field representative.

4: The Road Contractor is to notify Zayo, 48 hours prior to start of construction.

5: Zayo is to have access throughout the duration of the project to monitor and maintain Zayo facilities for the ability to provide service.

6: Caution is to be used when excavating near or around Zayo facilities.

FLORIDA DEPARTMENT OF TRANSPORTATION

UTILITY WORK SCHEDULE

December 14, 2016

Financial Project ID: P5984- Veterans Mem Pkwy Ext Utility Company: ZAYO Group LLC FDOT Plans Dated: 02.27.2026

SECTION C: UAO’s WORK ACTIVITIES

Act.

No.

Utility Facility (type, size, material, status)

From Station/ Offset

To Station/ Offset

Utility Work Activity Description

Dependent Activity TCP Phase

Consecutive Calendar Days

Prior to During Const. Const.

1 Proposed ZAYO 24”x36”x30”

HH

163+92.65’, 51.07’ RT

163+92.65’, 51.07’ RT Install Zayo Handhole Staking of roadway limits, and sidewalk N/A 0 5

2 Existing ZAYO 24”x36”x30”

HH

163+92.65’, 25.82’ RT

163+92.65’, 25.82’ RT Remove Zayo Handhole

Completion of all Zayo trenching and proposed HH placement and fiber cutover for continuity.

N/A 0 2

3 Trench ZAYO (3) 1.25" HDPE

DUCTS E/W (1) 144CT FOC

163+92.65’, 25.82’ RT

163+92.65’, 51.07’ RT

Trench and connect Zayo conduit from existing HH location to proposed HH location.

Staking of roadway limits, and sidewalk N/A 0 10