Exhibit_Q-_UWS_-_ATT-Transmission.pdf

PDF 279 KB Posted

Attached to
Veterans Memorial Parkway Extension - Clearing & Grubbing for Advance Utility Removal/Relocations
Solicitation number
26-B-109JD
Issued by
Volusia County, Florida

About this file

This is an AT&T Enterprises utility schedule sheet for the Veterans Memorial Parkway Extension project in Volusia County, Florida. The document outlines AT&T's existing fiber optic cable (FOC) infrastructure along the project corridor and specifies AT&T's requirements for the construction activities. AT&T currently maintains a 6-1.5" HDPE long line transmission cable extending from Station 159+43 along Veterans Memorial Parkway through Station 212+03, with additional segments along Dr. MLK Beltway. The project requires AT&T to relocate its existing facilities to accommodate the proposed roadway construction. AT&T anticipates a total of 180 days to complete the relocation work, preceded by a 90-day pre-construction period for permitting (30 days), engineering (30 days), and material procurement (30 days). Construction activities include furnishing and installing approximately 16,000 feet of fiber optic cable, multiple Quazite handholes at designated stations, tie-ins, splicing events, and site restoration.

AT&T has established specific construction requirements that the FDOT contractor must follow, including providing two business days' notice to Sunshine One Call prior to work near AT&T facilities, implementing "hand dig only" protocols within 5 feet of active cables and structures, and maintaining coordination with AT&T field representatives throughout all field verification and construction activities. AT&T requires permanent access to all manholes and specifies that the proposed facilities installation shall not impede manhole access or facility availability. AT&T intends to utilize the project's Traffic Control Plan unless otherwise noted in the utility permit. The cable and facilities are to be relocated as indicated in the project plans, with the existing FOC offset to the centerline of Veterans Memorial Parkway at varying distances from the baseline.

View the file

Other files

File Type Posted
Veterans_Memorial_Parkway_Extension_-_Clearing_&_Grubbing_for_Advance_Utility_Removal_Relocations.pdf PDF
Exhibit_FF-_Conflict_Matrix.xlsx XLSX spreadsheet
Exhibit_EE-_UWS_-_Zayo.pdf PDF
Exhibit_DD-_RGBs_-_Zayo.pdf PDF
Exhibit_CC-_No_Conflict_Letter_-_Uniti_Fiber.pdf PDF
Exhibit_BB-_No_Conflict_Letter_-_Lumen.pdf PDF
Exhibit_AA-_UWS_-_Florida_Public_Utilities.pdf PDF
Exhibit_Z-_UWS_-_Duke_Energy.pdf PDF
Exhibit_Y-_RGBs_-_Duke_Energy.pdf PDF
Exhibit_X-_UWS_-_City_of_Orange_City.pdf PDF
Exhibit_W-_RGBs_-_City_of_Orange_City.pdf PDF
Exhibit_V-_No_Facilities_-_City_of_DeLand.pdf PDF
Exhibit_U-_UWS_-_Spectrum.pdf PDF
Exhibit_T-_RGBs_-_Spectrum.pdf PDF
Exhibit_S-_UWS_-_Century_Link.pdf PDF
Exhibit_R-_RGBs_-_Century_Link.pdf PDF
RGBs_-_ATT-Transimission.pdf PDF
Exhibit_O-_Clear_-_No_Facilities-ATT-D.docx DOCX document
Exhibit_N-26-B-109JD,_Payment_and_Performance_Bond.pdf PDF
Exhibit_M-SJRWMD_Permit_Approval.pdf PDF
Exhibit_L-_Sales_Tax_Exemption_Procedures.pdf PDF
Exhibit_K-_BASE-UTILITY01.dwg DWG drawing
Exhibit_J-SURVRD01_VMP.dwg DWG drawing
Exhibit_I-_Project_Survey.pdf PDF
Exhibit_H-_Utility_Adjustment_Sheets.pdf PDF
Exhibit_G-_Pricing_Sheet,_26-B-109JD.xlsx XLSX spreadsheet
Exhibit_F-Roadway_Drainage_-_SS_MOT_Plans.pdf PDF
Exhibit_E-Roadway_Technical_Specifications.pdf PDF
Exhibit_D-_CLEARING_&_GRUBBING_PLANS.pdf PDF
Exhibit_C-Draft_Contract,_26-B-109JD,_C2086.pdf PDF
Exhibit_B-PRIME-SUB_FORM_26-B-109JD.xls XLS spreadsheet
Exhibit_A-_26-B-109JD_Veterans_Memorial_Extension-Clearing_and_Grubbing-Required_Insurance_Limits.pdf PDF
SURVRD01_VMP.dwg DWG drawing
6-Project_Survey.pdf PDF
VMP_-_CLEARING_&_GRUBBING_PLANS.pdf PDF
VMP_-_Ut._Adj._Sheets.pdf PDF
Signed_&_Sealed_VC_Tech_Specs_08.11.25_-_Exhibit_B.pdf PDF
Roadway_Drainage_-_SS_MOT_Plans.pdf PDF
Revised_Estimate_-_C&G.pdf PDF
VMP_-SJRWMD_Permit_Approval.pdf PDF
BASE-UTILITY01.dwg DWG drawing
Conflict_Matrix.xlsx XLSX spreadsheet
Project_Description_-_Scope_of_Work_-_Clearing_&_Grubbing_for_Advance_Utility_Removal-Relocations_5-28-26.docx DOCX document
Construction_Bid_Request_-_Clearing_&_Grubbing_for_Advance_Utility_Removal-Relocations(5.28.26).pdf PDF
PRIME-SUB_FORM_for_Contractors_rev._01.15.2025_(lock_before_publishing).xls XLS spreadsheet
Pricing_Sheet_-_C&G.xlsx XLSX spreadsheet
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AT&T ENTERPRISES SCHEDULE SHEET

Project ID #: P5894 Veterans Memorial Pkwy Extension County: Volusia

Primary Road: Veterans Memorial Pkwy Cross Street: N Kentucky Ave

AT&T Enterprises Long Line (Transmission) Construction Requests:

1. AT&T Enterprises requests two (2) business days notice to (Sunshine One Call) from FDOT contractor prior to working around all AT&T Enterprises facility. AT&T to provide field locates to identify/protect, per statute.

2. AT&T Enterprises requests FDOT contractor to “Hand Dig Only” when working within 5 feet of active cable(s) & structure(s).

3. FDOT contractor shall coordinate with AT&T Enterprises field representative during all field verification & all

AT&T Enterprises facility associated construction activities. Permit to be submitted 90 days prior to FDOT let date.

4. AT&T Enterprises requires access to manholes at all times. The proposed facilities installation shall not impede permanent AT&T Enterprises manhole access and facility availability.

5. AT&T Enterprises cable & facilities to be relocated to accommodate proposed construction, as indicated.

Unless otherwise noted in the AT&T Enterprises Utility Permit, AT&T Enterprises generally intends to use the

Construction Plan’s Traffic Control Plan.

6. AT&T Enterprises anticipates 180 Days of Construction to Relocate.

UTILITY FACILITIES OFFSET TO CENTERLINE VETERAN’S MEMORIAL PKWY

EXISTING:

Existing AT&T Enterprises Long Line FOC in 6-1.5” HDPE, o/s varies from B/L of Survey Veterans Memorial Pkwy, unless otherwise noted.

1. Sta. 159+43, o/s 50’ Rt. To Sta. 163+88, o/s 30’ Rt. (FOC)

2. Sta. 163+88, o/s 30’ Rt. (P.I.)

3. Sta. 163+88, o/s 30’ Rt. To Sta. 163+88, o/s 50’ Rt. (FOC)

4. Sta. 163+88, o/s 50’ Rt. (HHs # 454 & 455)

5. Sta. 163+88, o/s 50’ Rt. To Sta. 163+88, o/s 100’ Rt. (FOC to Kentucky Ave.)

6. Leaving construction limits at Sta. 163+88, o/s 100’ Rt.

7. Reentering construction limits at Sta. 193+50, o/s 50’ Rt.

8. Sta. 193+50, o/s 50’ Rt. To Sta. 212+03, o/s 45’ Rt. (FOC from Kentucky Ave.)

9. Station Equation Sta. 212+03 BK (Veteran’s Memorial Pkwy) / 10+00 AH (MLK Beltway)

10. Sta 10+00, o/s 45’ Rt. To Sta. 20+20, o/s 90’ Rt. Dr. MLK Beltway (B/L of Survey MLK Beltway) (FOC)

11. Sta. 20+20, o/s 90’ Rt. Dr. MLK Beltway (HHs # 450 & 451)

12. Sta. 20+20, o/s 90’ Rt. Dr. MLK Beltway To Sta. 29+25, o/s 120’ Rt. Dr. MLK Beltway (FOC)

13.

PROPOSED:

AT&T ENTERPRISES SCHEDULE SHEET

Project ID #: P5894 Veterans Memorial Pkwy Extension County: Volusia

Primary Road: Veterans Memorial Pkwy Cross Street: N Kentucky Ave

Prior to Construction: (90 Days)

13. Permitting (30 Days)

14. Engineering (30 Days)

15. Material Procurement (30 Days)

After ROW Acquisition Completed, Clear and Grub Completion During Construction: (180 Days)

16. At Sta. 160+55, o/s 50’ Rt. Tie-In. (5 Days)

17. From Sta. 160+55, o/s 50’ Rt. To Sta. 164+40, o/s 65’ Rt. Furnish and Install 6-1.5” HDPE. (10 Days)

18. At Sta. 164+40, o/s 65’ Rt. Furnish and Install (2) 48” x 30” x 18” Quazite Handholes. (5 Days)

19. From Sta. 164+40, o/s 65’ Rt. To Sta. 180+00, o/s 65’ Rt. Furnish and Install 6-1.5” HDPE. (After fill, 15 Days)

20. At. Sta. 180+00, o/s 65’ Rt. Furnish and Install (2) 48” x 30” x 18” Quazite Handholes. (5 Days)

21. From Sta. 180+00, o/s 65’ Rt. To Sta. 198+00, o/s 90’ Rt. Furnish and Install 6-1.5” HDPE. (After fill, 15 Days)

22. At. Sta. 198+20, o/s 90’ Rt. Furnish and Install (2) 48” x 30” x 18” Quazite Handholes. (5 Days)

23. From Sta. 198+20, o/s 90’ Rt. To Sta. 209+40, o/s 93’ Rt. Furnish and Install 6-1.5” HDPE (10 Days)

24. At. Sta. 209+40, o/s 93’ Rt. Furnish and Install (2) 48” x 30” x 18” Quazite Handholes. (5 Days)

25. From Sta. 209+40, o/s 93’Rt. To Sta. 212+03.1, o/s 67’ Rt. Furnish and Install 6-1.5” HDPE (10 Days)

26. Station Equation Sta. 212+03.1, o/s 67’ Rt. (VMP) To Sta. 10+00, o/s 67’ Rt.

27. From Sta. 10+00, o/s 67’ Rt. To Sta. 11+75, o/s 45’ Rt. Furnish and Install 6-1.5” HDPE (10 Days)

28. At Sta. 10+00, o/s 67’ Rt. Tie-In. (5 Days)

29. Install 16000’ FOC (10 Days)

30. Splice Event(s) at Various Stations. (45 Days)

31. Recovering FOC after Splice Event. Throughout Project. (5 Days)

32. Restoration. Throughout Project. (20 Days)