Exhibit_Z-_UWS_-_Duke_Energy.pdf

PDF 465 KB Posted

Attached to
Veterans Memorial Parkway Extension - Clearing & Grubbing for Advance Utility Removal/Relocations
Solicitation number
26-B-109JD
Issued by
Volusia County, Florida

About this file

This is a Florida Department of Transportation (FDOT) Utility Work Schedule document executed between FDOT and Duke Energy for utility relocation and adjustment work associated with the Veterans Memorial Parkway Extension project in Volusia County. The schedule details Duke Energy's overhead and underground electric facility modifications required to accommodate the roadway project, including the installation of new poles, pull boxes, underground conduit, and overhead wire, as well as the removal or reframing of existing facilities. The utility work encompasses activities from station 15+93.48'LT to station 210+51.68'LT, with 133 consecutive calendar days allocated for completion during FDOT project construction. The document was prepared based on FDOT plans dated November 17, 2025, and was executed on February 20, 2026, by Duke Energy representative Alexander Charters, an Engineering Technologist III. The utility work schedule is contingent upon FDOT providing cleared, grubbed, staked right-of-way and finished grade prior to Duke Energy facility installation.

Duke Energy's special conditions and constraints include maintaining bucket truck access to all existing and proposed poles, pull boxes, and switchgear locations throughout construction; requiring fourteen working days advance notice for any temporary bracing, holding, or relocation of facilities; prohibiting nighttime relocation activities involving energized conductors except for emergency work; and maintaining minimum clearance distances per OSHA regulations with fourteen working day notice required for de-energization of conflicting facilities. All Duke Energy facilities operate at 12,470 volts and are to remain energized and in place except as otherwise provided in the utility work schedule. Duke Energy cannot remove old facilities until new facilities are energized and existing customer services are relocated. The work must comply with the 2017 Utility Accommodation Manual and Florida Erosion and Sediment Control Design standards, with all work performed during normal business hours unless otherwise agreed.

View the file

Other files

File Type Posted
Veterans_Memorial_Parkway_Extension_-_Clearing_&_Grubbing_for_Advance_Utility_Removal_Relocations.pdf PDF
Exhibit_FF-_Conflict_Matrix.xlsx XLSX spreadsheet
Exhibit_EE-_UWS_-_Zayo.pdf PDF
Exhibit_DD-_RGBs_-_Zayo.pdf PDF
Exhibit_CC-_No_Conflict_Letter_-_Uniti_Fiber.pdf PDF
Exhibit_BB-_No_Conflict_Letter_-_Lumen.pdf PDF
Exhibit_AA-_UWS_-_Florida_Public_Utilities.pdf PDF
Exhibit_Y-_RGBs_-_Duke_Energy.pdf PDF
Exhibit_X-_UWS_-_City_of_Orange_City.pdf PDF
Exhibit_W-_RGBs_-_City_of_Orange_City.pdf PDF
Exhibit_V-_No_Facilities_-_City_of_DeLand.pdf PDF
Exhibit_U-_UWS_-_Spectrum.pdf PDF
Exhibit_T-_RGBs_-_Spectrum.pdf PDF
Exhibit_S-_UWS_-_Century_Link.pdf PDF
Exhibit_R-_RGBs_-_Century_Link.pdf PDF
Exhibit_Q-_UWS_-_ATT-Transmission.pdf PDF
RGBs_-_ATT-Transimission.pdf PDF
Exhibit_O-_Clear_-_No_Facilities-ATT-D.docx DOCX document
Exhibit_N-26-B-109JD,_Payment_and_Performance_Bond.pdf PDF
Exhibit_M-SJRWMD_Permit_Approval.pdf PDF
Exhibit_L-_Sales_Tax_Exemption_Procedures.pdf PDF
Exhibit_K-_BASE-UTILITY01.dwg DWG drawing
Exhibit_J-SURVRD01_VMP.dwg DWG drawing
Exhibit_I-_Project_Survey.pdf PDF
Exhibit_H-_Utility_Adjustment_Sheets.pdf PDF
Exhibit_G-_Pricing_Sheet,_26-B-109JD.xlsx XLSX spreadsheet
Exhibit_F-Roadway_Drainage_-_SS_MOT_Plans.pdf PDF
Exhibit_E-Roadway_Technical_Specifications.pdf PDF
Exhibit_D-_CLEARING_&_GRUBBING_PLANS.pdf PDF
Exhibit_C-Draft_Contract,_26-B-109JD,_C2086.pdf PDF
Exhibit_B-PRIME-SUB_FORM_26-B-109JD.xls XLS spreadsheet
Exhibit_A-_26-B-109JD_Veterans_Memorial_Extension-Clearing_and_Grubbing-Required_Insurance_Limits.pdf PDF
SURVRD01_VMP.dwg DWG drawing
6-Project_Survey.pdf PDF
VMP_-_CLEARING_&_GRUBBING_PLANS.pdf PDF
VMP_-_Ut._Adj._Sheets.pdf PDF
Signed_&_Sealed_VC_Tech_Specs_08.11.25_-_Exhibit_B.pdf PDF
Roadway_Drainage_-_SS_MOT_Plans.pdf PDF
Revised_Estimate_-_C&G.pdf PDF
VMP_-SJRWMD_Permit_Approval.pdf PDF
BASE-UTILITY01.dwg DWG drawing
Conflict_Matrix.xlsx XLSX spreadsheet
Project_Description_-_Scope_of_Work_-_Clearing_&_Grubbing_for_Advance_Utility_Removal-Relocations_5-28-26.docx DOCX document
Construction_Bid_Request_-_Clearing_&_Grubbing_for_Advance_Utility_Removal-Relocations(5.28.26).pdf PDF
PRIME-SUB_FORM_for_Contractors_rev._01.15.2025_(lock_before_publishing).xls XLS spreadsheet
Pricing_Sheet_-_C&G.xlsx XLSX spreadsheet
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Rule 14-46.001 F.A.C

FLORIDA DEPARTMENT OF TRANSPORTATION

UTILITY WORK SCHEDULE

December 14, 2016

INTERNAL

Pursuant to Section 337.403 F.S., the UAO and FDOT agree to the UAO’s need for relocation or adjustment to its utilities and FDOT’s need for a schedule for the UAO to effect the relocation or adjustment. This utility work schedule is based on FDOT plans dated in the project information box below. Any deviation by FDOT or its contractor from these plans, may void this utility work schedule. Upon notification by FDOT of a change to these plans, the UAO may negotiate a new utility work schedule. The UAO agrees to notify FDOT and the contractor in writing prior to starting, stopping, resuming, and completing work in accordance with this utility work schedule. The UAO shall obtain a utility permit and comply with requirements of the 2017 Utility Accommodation Manual (UAM) for all work done under this utility work schedule. The UAO is not responsible for events beyond the control of the UAO that could not be reasonably anticipated by the UAO and which could not be avoided by the UAO with exercise of due diligence at the time of the occurrence.

FDOT PROJECT INFORMATION

Financial Project ID: Federal Project ID:

State Road Number: Veteran's Memorial Parkway County: Volusia

FDOT Plans Dated: Nov 17, 2025 District Document No.:

UTILITY AGENCY/OWNER (UAO)

Utility Company: Duke Energy

UAO Project Rep: Alexander Charters Phone: 407-319-4463 E-mail: alexander.charters@duke-energy.com

UAO Field Rep: Phone: E-mail:

UTILITY SIGNATURE

I have reviewed the FDOT plans referenced above and submit this utility work schedule in compliance with UAM Section 5 and agree to be bound by the terms of this utility work schedule.

UAO Rep. Date 2 / 20 / 2026

Name Alexander Charters

Title Engineering Technologist III

ENGINEER OF RECORD SIGNATURE

I attest this utility work schedule is compatible with the FDOT plans referenced above.

EOR. Date

Name

Title

APPROVAL BY DISTRICT UTILITIES

This utility work schedule is complete and acceptable to FDOT.

FDOT Rep. Date / /

Name

Title

SECTION A: SUMMARY OF UTILITY WORK

The below days are the total numbers of days shown for all activities in Section C of this utility work schedule. The breakdown of how these days are to be incorporated into the FDOT project and the dependence of these days upon the completion of other activities by the UAO or others is shown in Section C.

Days prior to FDOT project construction: Days during FDOT project construction: 133

Amir H. Malek, PE Principal

2026 /03 /13

ACharte Pen senchht

FLORIDA DEPARTMENT OF TRANSPORTATION

UTILITY WORK SCHEDULE

December 14, 2016

INTERNAL

Financial Project ID:

Utility Company: Duke Energy

FDOT Plans Dated: Nov 17, 2025

SECTION B: UAO SPECIAL CONDITIONS/CONSTRAINTS

1)Emergency number for nights, weekends and Duke Energy Florida holidays is (800) 228-8485

2)A copy of the approved contractors CPM (critical path method) is requested within 5 days of approval.

3)Duke Energy requests the contractor to provide right of way cleared, grubbed, staked and finished grade, as well as stationing as required for, and prior to installation of Duke Energy facilities. Duke Energy understands that work identified as prior to construction, FDOT will be able to provide ROW staking.

4)This UAO's poles scheduled to be removed will be removed within 10 days from when they are cleared by all joint users.

5)Any temporary bracing or holding of this UAO's poles, existing or proposed, required for FDOT construction will require fourteen

(14)working days advance notice by FDOT to this UAO's representative.

6)Any temporary relocation of this UAO's existing or proposed facilities that may require FDOT construction will require fourteen

(14)working days advance notice by FDOT to this UAO's representative.

7)Bucket Truck access must be maintained to all of this UAO's existing and proposed pole, pull box and switchgear locations throughout the duration of this projects construction for maintenance and outage restoration, except for access blockages that are reasonably necessary to accomplish the project.

8)Duke Energy Distribution cannot remove old facilities until new facilities are energized and existing customer services have been relocated.

9)Duke Energy resources can also be affected by weather not directly contacting the Florida region as the company supports other companies in surrounding areas and states.

10)All Duke Energy facilities are energized at 12,470 v "Except as otherwise may be provided in Part C "Description of Utility Work" of this

Utility Work Schedule, Duke Energy overhead electric facilities to remain energized and in place. Table A "Minimum Clearances Distances specified in Subpart CC of OSHA Rule 29 CFR Part 1926 (as they pertain to crane/derrick operation), and/or those minimum distances specified in CFR1910.33©(3) for work in proximity to power lines not covered by this Subpart CC", must be maintained. If minimum clearances outlined in the OSHA regulations set forth in the previous sentence than Duke Energy Distribution will require a fourteen

(14)working days advance notification in order to successfully de-energize these facilities in conflict so appropriate clearances can be maintained.

11)All normal relocation activities performed by this UAO are intended to be performed during normal working business hours unless other arrangements have been agreed to by Duke Energy and the Department. No night time relocation activities involving energized conductors orequipment will be perfomed, with the exception of outage restoration or other such emergency work (UAO's Safety Manual Regulation).

FLORIDA DEPARTMENT OF TRANSPORTATION

Utility Company: Duke Energy

FDOT Plans Dated: Nov 17, 2025

SECTION C: UAO’s WORK ACTIVITIES

Act.

No.

Utility Facility

(type, size, material, status)

From

Station/Offset

To

Station/Offset

Utility Work Activity

Description

Dependent

Activity

TCP

Phase

Consecutive

Calendar Days

Prior to During

Const. Const.

Switching Location Staking 30

Pull Box 192+62,68’RT Install Pull Box 2

Pole Wood 50-3 195+52,55’LT Install Term Pole 4

UG Bore and Conduit 192+62,68’RT 195+52,55’LT Install UG Bore and Conduit 14

Pole Wood 50-3 197+72,67’LT Install Tangent Pole 3

OH Wire 195+52,55’LT 197+72,67’LT Install OH Wire 1

Pole Wood 50-3 200+13,69’LT Install Tangent Pole 3

OH Wire 197+72,67’LT 200+13,69’LT Install OH Wire 1

Pole Wood 50-3 202+60,68’LT Install Tangent Pole 3

OH Wire 200+13,69’LT 202+60,68’LT Install OH Wire 1

Pole Wood 50-3 207+55,68’LT Install Tangent Pole 3

OH Wire 202+60,68’LT 207+55,68’LT Install OH Wire 1

Pole Wood 50-3 209+65,68’LT Install Tangent Pole 3

OH Wire 207+55,68’LT 209+65,68’LT Install OH Wire 1

Pole Wood 50-3 210+51,68’LT Install Deadend Pole 3

OH Wire 209+65,68’LT 210+51,68’LT Install OH Wire 1

Pole Wood 50-3 210+48,47’LT Existing Pole to be Reframed 1

Pole Wood 45-4 192+84,60’RT Existing Pole to be Removed 1

OH Wire 190+86,168’RT 192+84,60’RT Existing Wire to be Removed 1

Pole Wood 45-4 197+72,27’LT Existing Pole to be Removed 1

OH Wire 192+84,60’RT 197+72,27’LT Existing Wire to be Removed 1

Pole Wood 45-4 200+13,25’LT Existing Pole to be Removed 1

OH Wire 197+72,27’LT 200+13,25’LT Existing Wire to be Removed 1

Pole Wood 45-4 202+60,25’LT Existing Pole to be Removed 1

OH Wire 200+13,25’LT 202+60,25’LT Existing Wire to be Removed 1

Pole Wood 45-4 207+58,26’LT Existing Pole to be Removed 1

OH Wire 202+60,25’LT 207+58,26’LT Existing Wire to be Removed 1

Pole Wood 45-4 209+65,37’LT Existing Pole to be Removed 1

OH Wire 207+58,26’LT 209+65,37’LT Existing Wire to be Removed 1

OH Wire 209+65,37’LT 210+48,47’LT Existing Wire to be Removed 1

Pole Wood 45-4 190+86,168’RT Existing Pole to be Removed 1

OH Wire 15+93,48’LT 18+18,23’LT Existing Wire to be Removed 1

Pole Wood 45-4 18+18,23’LT Existing Pole to be Removed 1

FLORIDA DEPARTMENT OF TRANSPORTATION

Utility Company: Duke Energy

FDOT Plans Dated: Nov 17, 2025

SECTION C: UAO’s WORK ACTIVITIES

Act.

No.

Utility Facility

(type, size, material, status)

From

Station/Offset

To

Station/Offset

Utility Work Activity

Description

Dependent

Activity

TCP

Phase

Consecutive

Calendar Days

Prior to During

Const. Const.

Pole Wood 45-4 15+93,48’LT Existing Pole to be Reframed 1

Pole Wood 40-3 18+17,28’RT Existing Pole to be Removed 1

OH Wire 18+18,23’LT 18+17,28’RT Existing Wire to be Removed 1

Pole Wood 45-4 20+63,18’RT Existing Pole to be Removed 1

OH Wire 18+18,23’LT 20+63,18’RT Existing Wire to be Removed 1

Pole Wood 45-4 22+62,116’RT Existing Pole to be Removed 1

OH Wire 20+63,18’RT 22+62,116’RT Existing Wire to be Removed 1

Pole Wood 45-4 23+98,267’RT Existing Pole to be Removed 1

OH Wire 22+62,116’RT 23+98,267’RT Existing Wire to be Removed 1

Pole Wood 45-4 25+88,427’RT Existing Pole to be Removed 1

OH Wire 23+98,267’RT 25+88,427’RT Existing Wire to be Removed 1

OH Wire 25+88,427’RT 190+86,168’RT Existing Wire to be Removed 1

Pole Wood 50-3 17+7,51’LT Install Tangent Pole 3

OH Wire 15+93,48’LT 17+7,51’LT Install OH Wire 1

Pole Wood 50-3 18+56,53’LT Install Double Deadend Pole 3

OH Wire 17+7,51’LT 18+56,53’LT Install OH Wire 1

Pole Wood 50-3 19+78,35’RT Install Deadend Pole 3

OH Wire 18+56,53’LT 19+78,35’RT Install OH Wire 1

Pole Wood 50-3 21+20,72’RT Install Term Pole 4

OH Wire 19+78,35’RT 21+20,72’RT Install OH Wire 1

UG Bore and Conduit 21+20,72’RT 192+62,68’RT Install UG Bore and Conduit 14