AMD 001 Drawings_SIGNED.pdf

PDF 2 MB Posted

Attached to
FY20 MCAF PAF180200 APR - JET FUEL STORAGE TANKS, ROYAL AUSTRALIAN AIR FORCE BASE TINDAL, AUSTRALIA
Solicitation number
N6274221R1300
Issued by

About this file

This solicitation is for the construction of two four (4) ML (25,000 BBL ea) Cut'N'Cover bulk fuel tanks, support infrastructure including two pump houses, a liquid fuel truck fill stand, fuel stand unloading, and filter building, and all utilities, automatic tank gauging systems, site improvements, pavements, communications infrastructure, backup generator and other work necessary to provide a complete and usable facility at Royal Australian Air Force (RAAF) Base Tindal, Northern Territory, Australia. Additionally, there are three pre-priced options to construct concrete vs. asphalt pavements for heavy duty pavements, a cross over pit for fuel transfer lines, and a hydrant-hose checkout station, all in accordance with drawings and specifications. The agency is the Department of the Navy Naval Facilities Engineering Command.

View the file

Other files

File Type Posted
21R1300_Notice12-Issued.pdf PDF
21R1300_Amd8-Issued.pdf PDF
AMD0008_Attachments.pdf PDF
21R1300_Notice11-Issued.pdf PDF
21R1300_Amd7-Issued.pdf PDF
21R1300_Notice10-Issued.pdf PDF
21R1300_Amd6-Issued.pdf PDF
AMD0005_Dwgs_Attachments.pdf PDF
21R1300_Amd5-Issued.pdf PDF
21R1300_Notice9-Issued.pdf PDF
21R1300_Notice8-Issued.pdf PDF
21R1300_Amd4-Issued.pdf PDF
21R1300_Notice7-Issued.pdf PDF
20R1300_Amend0003-Issued.pdf PDF
20R1300_AMD0003_Attachments.pdf PDF
21R1300_Notice6-Issued.pdf PDF
21R1300_Amend0002-Issued.pdf PDF
AMD002section01 50 00.pdf PDF
21R1300_Notice5-Issued.pdf PDF
AMD2_Dwg17254307_E-413_Rev2_SIGN.pdf PDF
21R1300_Amd1_Attachments.zip ZIP file
21R1300_Notice4-Issued.pdf PDF
PAF180200_JA_Romteck_FireAlarmTransmitter-Redacted.pdf PDF
21R1300_Amend0001-Issued.pdf PDF
21R1300_Notice3_Issued.pdf PDF
21R1300_Notice2-Issued.pdf PDF
PAF180200_Proj_Site_Photos.pdf PDF
21R1300_Notice1-Issued.pdf PDF
2-PAF180200-Specs_SIGNED.pdf PDF
4-PAF180200-Drawings2_SIGNED.pdf PDF
3-PAF180200-Drawings1_SIGNED.pdf PDF
1-RFPN6274221R1300_Issued.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

X

X

X

X

X

X

X X

X X

X

X

X

X

X

X

X

X

X

X

X

SEE SHEET C-403

SEE SHEET C-405

SEE SHEET C-407SEE SHEET C-406

SEE SHEET C-404

SEE SHEET C-402

TARAKAN ROAD

DRAINAGE IMPROVEMENTS

PROVIDED BY WE07

CULVERTS

PROVIDED BY WE07 DRAINAGE IMPROVEMENTS

PROVIDED BY WE07

D D

D

D D D D D

SD

SD

BOX CULVERTS

GANTRY

ENLARGEMENT PLAN

SEE SHEET C-410

FILTER BUILDING

ENLARGEMENT PLAN

SEE SHEET C-411

AC

C

ES

S

R O

AD

R

IN

G R

O

AD

R

IN

G R

O

AD

SCALE:

HDR Engineering, Inc.

1001 Bishop Street Suite 400 Honolulu, HI 96813 Phone: (808) 697-6200

10/30/2020

NOTES:

1. SEE C-200 SERIES FOR SITE LAYOUT

AND DIMENSIONS.

2. SEE C-002 FOR EXISTING CONDITIONS

AND SURVEY NOTES.

3. SEE SHEET G-003 AND G-004 FOR

GENERAL NOTES AND LEGEND.

4. SEE SHEET C-420 AND C-421 FOR SITE

SECTIONS

5. SEE SHEET C-410 FOR GANTRY FINE

GRADING.

PA

F1

AP

R

JE

T

FU

EL

S

TO

R

AG

E

TA

N

KS

R O

YA

L

AU

ST

R

AL

IA

N

A

IR

F O

R C

E R

AA

F

BA

SE

T

IN

D

AL

. A U

ST

R

AL

IA

1606003

DA

LE

JC

LE

AS SHOWN

17254212

CT CT RA

O

VE

R

AL

L G

R

AD

IN

G

A N

D D

R

AI

N

AG

E

PL

AN

C-401

LE

AD

ER

T

EX

T

R

EV

IS

ED

J

AN

01/13/2021

HDR Engineering, Inc.

1001 Bishop Street Suite 400 Honolulu, HI 96813 Phone: (808) 697-6200

10/30/2020

NOTES:

1. SELECT FILL IS TYPE A UNLESS SHOWN

OTHERWISE.

2. SEE C-200 SERIES FOR SITE PLAN

LAYOUT AND DIMENSIONS.

3. SEE C-400 SERIES FOR SITE GRADING

PLANS.

4. SEE STRUCTURAL DRAWINGS FOR

TANK DESIGN AND DIMENSIONS

5. TEMPORARY EXCAVATIONS UP TO 1 M

DEEP IN STIFF (OR STRONGER) CLAYS

MAY REMAIN NEAR VERTICAL FOR

SHORT PERIODS OF TIME, PROVIDED

THAT THEY REMAIN DRY AT THE TIME

OF CONSTRUCTION AND THERE ARE NO

LOADS, SERVICES, STRUCTURES OR

TRAFFIC LOCATED WITHIN A DISTANCE

FROM THE CREST OF THE BATTER

EQUAL TO THE SLOPE HEIGHT.

DEEPER TEMPORARY DRY

UN-SHORED OR UN-RETAINED

EXCAVATIONS SHOULD BE

BATTERED TO A TEMPORARY SLOPE

OF NO STEEPER THAN 1.5H:1V FOR

CLAYEY SANDS AND SANDY CLAY

SOILS OVERLYING LIMESTONE. IF SOFT

CLAY OR LOOSE SAND MATERIALS ARE

ENCOUNTERED, THEN TEMPORARY

BATTERS MAY NEED TO BE

CONSIDERABLY FLATTER, SAY

NOMINALLY AT 2H:1V, AND WOULD BE

SUBJECT TO GEOTECHNICAL

INSPECTION AT THE TIME OF

EXCAVATION.

IF GROUNDWATER IS ENCOUNTERED

AT THE TIME OF EXCAVATION,

ADDITIONAL GEOTECHNICAL ADVICE

SHOULD BE SOUGHT FROM PROJECT

GEOTECHNICAL ENGINEER. DEEP

EXCAVATIONS THAT ENCOUNTER SOFT

OR WET MATERIALS WILL PROBABLY

REQUIRE THE USE OF A ROCK

BRIDGING LAYER ACROSS THEIR BASE

TO FACILITATE COMPACTION OF

SUBSEQUENT FILLING. ADDITIONAL

ADVICE SHOULD BE SOUGHT FROM

PROJECT GEOTECHNICAL ENGINEER IN

THIS REGARD, AS NECESSARY.

6. SLOPES BETWEEN DIFFERENT FILL

TYPES ASSUMED TO BE 1(H):1(V) FOR

ESTIMATION AND GRAPHICAL

PURPOSES ONLY.

PA

F1

AP

R

JE

T

FU

EL

S

TO

R

AG

E

TA

N

KS

R O

YA

L

AU

ST

R

AL

IA

N

A

IR

F O

R C

E R

AA

F

BA

SE

T

IN

D

AL

. A U

ST

R

AL

IA

1606003

DA

LE

JP

LE

AS SHOWN

17254221

CT CT RA

SI

TE

S

EC

TI

O

N S

C-420

G

EO

TE

C

H N

IC

AL

R

EV

IS

IO

N

J

AN

HDR Engineering, Inc.

1001 Bishop Street Suite 400 Honolulu, HI 96813 Phone: (808) 697-6200

10/30/2020

NOTES:

1. SELECT FILL IS TYPE A UNLESS SHOWN OTHERWISE.

2. SEE C-200 SERIES FOR SITE PLAN LAYOUT AND

DIMENSIONS.

3. SEE C-400 SERIES FOR SITE GRADING PLANS.

4. SEE POL DRAWINGS FOR TANK DESIGN AND

DIMENSIONS.

5. TEMPORARY EXCAVATIONS UP TO 1 M DEEP IN STIFF

(OR STRONGER) CLAYS MAY REMAIN NEAR VERTICAL

FOR SHORT PERIODS OF TIME, PROVIDED THAT THEY

REMAIN DRY AT THE TIME OF CONSTRUCTION AND

THERE ARE NO LOADS, SERVICES, STRUCTURES OR

TRAFFIC LOCATED WITHIN A DISTANCE FROM THE

CREST OF THE BATTER EQUAL TO THE SLOPE

HEIGHT.

DEEPER TEMPORARY DRY UN-SHORED OR

UN-RETAINED EXCAVATIONS SHOULD BE

BATTERED TO A TEMPORARY SLOPE OF NO

STEEPER THAN 1.5H:1V FOR CLAYEY SANDS AND

SANDY CLAY SOILS OVERLYING LIMESTONE. IF SOFT

CLAY OR LOOSE SAND MATERIALS ARE

ENCOUNTERED, THEN TEMPORARY BATTERS MAY

NEED TO BE CONSIDERABLY FLATTER, SAY

NOMINALLY AT 2H:1V, AND WOULD BE SUBJECT TO

GEOTECHNICAL INSPECTION AT THE TIME OF

EXCAVATION.

IF GROUNDWATER IS ENCOUNTERED AT THE TIME OF

EXCAVATION, ADDITIONAL GEOTECHNICAL ADVICE

SHOULD BE SOUGHT FROM PROJECT GEOTECHNICAL

ENGINEER. DEEP EXCAVATIONS THAT ENCOUNTER

SOFT OR WET MATERIALS WILL PROBABLY REQUIRE

THE USE OF A ROCK BRIDGING LAYER ACROSS

THEIR BASE TO FACILITATE COMPACTION OF

SUBSEQUENT FILLING. ADDITIONAL ADVICE SHOULD

BE SOUGHT FROM PROJECT GEOTECHNICAL

ENGINEER IN THIS REGARD, AS NECESSARY.

6. REFER TO SPECIFICATION 32 11 23 FOR SELF

COMPACTING GRAVEL MATERIAL.

7. TANK PIT TO BE LINED ALONG EXCAVATION SLOPE

WITH GEOTEXTILE LINER.

8. SLOPES BETWEEN DIFFERENT FILL TYPES ASSUMED

TO BE 1(H):1(V) FOR ESTIMATION AND GRAPHICAL

PURPOSES ONLY.

PA

F1

AP

R

JE

T

FU

EL

S

TO

R

AG

E

TA

N

KS

R O

YA

L

AU

ST

R

AL

IA

N

A

IR

F O

R C

E R

AA

F

BA

SE

T

IN

D

AL

. A U

ST

R

AL

IA

1606003

DA

LE

JP

LE

AS SHOWN

17254222

CT CT RA

SI

TE

S

EC

TI

O

N S

C-421

N O

TE

R

EV

IS

ED

J

AN

W W

W W

W W

W

W

FOS

FOSFOSFOS

FOS

FO

S

FO

S

FOS

FOSFOSFOS

FOS

FW

FW

FW

FOSFOSFOSFO

S

FOS

SS

SS

SS

SS

SS

SS

SS

FO

S

FO

S

FOS

FOS

FO

S

FO

S

W

W

W

W

W

W

W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W

W W

W W

W W

W W

W W

W W

W W W

W W

W W

W W

W

W

W

W

W

W

W

W

W

W

W

W

W

W

W

W

FOS FOS

FO

S

FO

S

FO

S

FOS FOS

FOS

W W W W W W

W

W W

W

W W

WWWWWWWWWWWWWWWWWW

SS

SS

SS

SS

SS

SS

TARAKAN ROAD

SUBSOIL OUTLET SEE

INV: 129.000

DRAINAGE DITCH BY WE07

CLEANOUT SEE

INV: 129.517

CLEANOUT SEE

INV: 129.554

7.5m OF 100mm

SLOTTED PVC PIPE

@ 0.5%

CLEANOUT SEE

INV: 130.790

30m OF 100mm

SLOTTED PVC PIPE

@ 4.2%

30m OF 100mm

SLOTTED PVC PIPE

@ 3.7%

INV: 131.901

INV: 131.794

INV: 132.376

21.5m OF 100mm

SLOTTED PVC PIPE

@ 0.5%

INV: 132.462

29m OF 100mm

SLOTTED PVC PIPE

@ 4.5%

CLEANOUT SEE

INV: 131.155

INV: 132.137

INV: 130.687

15m OF 100mm

SLOTTED PVC PIPE

@ 0.5%

CLEANOUT SEE

INV: 132.212

CLEANOUT SEE

INV: 132.362

30m OF 100mm

SLOTTED PVC PIPE

@ 0.5%

30m OF 100mm

SLOTTED PVC PIPE

@ 0.5%

CLEANOUT SEE

INV: 132.512

CLEANOUT SEE

INV: 132.000

CLEANOUT SEE

INV: 132.362

30m OF 100mm

SLOTTED PVC PIPE

@ 0.5%

25m OF 100mm

SLOTTED PVC PIPE

@ 1.2%

23.3m OF 100mm

SLOTTED PVC PIPE

@ 0.5%

INV: 132.117

B3 C-609

B3 C-609

B3 C-609

B3 C-609

SUBSOIL OUTLET SEE B2

C-609

SCALE:

HDR Engineering, Inc.

1001 Bishop Street Suite 400 Honolulu, HI 96813 Phone: (808) 697-6200

10/30/2020

NOTES

1. PROVIDE PAVEMENT DRAINS AS

INDICATED ON THE DRAWINGS.

2. OUTLETS ARE TO BE SPACED

AT A MAXIMUM OF 120m APART.

3. CLEANOUTS ARE TO BE SPACED

AT A MAXIMUM OF 30m APART.

4. PAVEMENT DRAINS ARE

LOCATED 150mm BEHIND BACK

OF KERB. REFER TO PAVEMENT

DRAIN DETAIL AND TYPICAL

ROAD SECTIONS.

PA

F1

AP

R

JE

T

FU

EL

S

TO

R

AG

E

TA

N

KS

R O

YA

L

AU

ST

R

AL

IA

N

A

IR

F O

R C

E R

AA

F

BA

SE

T

IN

D

AL

. A U

ST

R

AL

IA

1606003

DA

LE

JC

LE

AS SHOWN

17254233

CT CT RA

O

VE

R

AL

L

PA

VE

M

EN

T

SU

BS

O

IL

D R

AI

N

AG

E

PL

AN

C-440

LEGEND:

CONCRETE PAVEMENT

PAVEMENT DRAIN

PAVEMENT DRAIN CLEANOUT

PAVEMENT DRAIN HEADWALL

SC

AL

E

BA

R R

EV

IS

ED

D

EC

AM

EN

D M

EN

T

D

EC

PA

F1

AP

R

JE

T

FU

EL

S

TO

R

AG

E

TA

N

KS

R O

YA

L

AU

ST

R

AL

IA

N

A

IR

F O

R C

E R

AA

F

BA

SE

T

IN

D

AL

. A U

ST

R

AL

IA

1606003

DA

LE

JP

LE

AS SHOWN

17254240

CT CC RA

SI

TE

U

TI

LI

TI

ES

FI

R

E

LO

O P

- S

TA

+3

T

O

+4

C-507

HDR Engineering, Inc.

1001 Bishop Street Suite 400 Honolulu, HI 96813 Phone: (808) 697-6200

10/30/2020

0+350 0+360 0+370 0+380 0+390 0+400 0+410 0+420

SCALE:

SCALE:

NOTES:

1. FIRE HYDRANT LINE TO BE LOCATED 3m

BEHIND EDGE OF PAVEMENT.

2. PROVIDE MINIMUM COVER OF 600mm IN NON-TRAFFICABLE AREAS AND 750mm

IN TRAFFICABLE AREAS.

3. PROVIDE MINIMUM HORIZONTAL

CLEARANCE OF 600mm AND MINIMUM VERTICAL CLEARANCE OF 500mm FROM

FUEL AND SEWER LINES.

4. SEE C-510 SERIES FOR POL PIPE

LAYOUTS AND SYSTEM CONNECTIVITY.

5. SEE DETAIL A4 ON SHEET C-611 FOR

FIRE HYDRANT AND GATE VALVE

CONNECTION TO FIRE LINE.

6. SEE DETAIL C3 ON SHEET C-611 FOR

UTILITY CROSSING DETAIL.

7. CONNECTIONS BETWEEN THE PVC PIPE

AND DIP (DICL) FLANGES SHALL BE

WITH THE USE OF A PVC STUB FLANGE.

8. FOR THRUST BLOCK ANCHORS,

SEE DRAWING C-611.

9. BOLT FITTINGS AND APPURTENANCES

TOGETHER THAT ABUT EACH OTHER

WITHIN 300mm.

10. ALL BACKING, FLANGES, NUTS, BOLTS,

AND WASHERS TO BE MANUFACTURED

FROM GRADE 316 STAINLESS STEEL.

PI

PE

M

AT

ER

IA

L R

EV

IS

ED

J

AN

N12 CONTINUOUS

20 CHAMFER (TYP)

N12 X VAR

@ 300 OC

HYDROCARBON RESISTANT SEALANT

CONCRETE PAVEMENT

BOND BREAKER TAPE

CONTAINMENT KERB SEE

N12 - 200 EW EF (IF > 150 SLAB REQUIRES 2

LAYERS OF REINFORCEMENT) OR

N12 - 150 EW (IF<150 ONE LAYER OF STEEL)

NOTES:

1. SEALANT AT THE BASE OF KERB IS NOT REQUIRED IF

THE SLAB AND KERB ARE MONOLITHIC.

2. PROVIDE KERB CONTROL JOINT TO MATCH SLAB

CONTROL JOINT SPACING.

1% SLOPE

200X200mm CLASS D COVER

AND ACCESS GROUND BOX.

100Ø BRASS LOCKING

CAP WITH LOCK

WELL SCREEN CUT TO

100mm BELOW FINISHED

PAVEMENT LEVEL

UNDERGROUND

TANK

100Ø SLOTTED CLASS 12

PVC PIPE WRAPPED IN

GEOFABRIC

ANCHOR BEAM

100Ø PVC SCREW CAP

TO BOTTOM OF LEAKAGE

DETECTION TUBE

150mm FUEL RESISTANT WATERSTOP

(REQUIRED IF KERB FORMED

SEPARATE FROM SLAB)

CONTAINMENT KERB.

SEE A3

C-603

NOTES

1. BACKFILL MATERIAL TO BE 5-10mm (MAX.) GRAVEL.

2. OBSERVATION WELL AND PARTS TO BE IN

ACCORDANCE WITH AS4897.

3. TEMPORARY EXCAVATIONS UP TO 1 M DEEP IN

STIFF (OR STRONGER) CLAYS MAY REMAIN NEAR

VERTICAL FOR SHORT PERIODS OF TIME,

PROVIDED THAT THEY REMAIN DRY AT THE TIME

OF CONSTRUCTION AND THERE ARE NO LOADS,

SERVICES, STRUCTURES OR TRAFFIC LOCATED

WITHIN A DISTANCE FROM THE CREST OF THE

BATTER EQUAL TO THE SLOPE HEIGHT.

DEEPER TEMPORARY DRY UN-SHORED OR

UN-RETAINED EXCAVATIONS SHOULD BE

BATTERED TO A TEMPORARY SLOPE OF NO

STEEPER THAN 1.5H:1V FOR CLAYEY SANDS AND

SANDY CLAY SOILS OVERLYING LIMESTONE. IF

SOFT CLAY OR LOOSE SAND MATERIALS ARE

ENCOUNTERED, THEN TEMPORARY BATTERS MAY

NEED TO BE CONSIDERABLY FLATTER, SAY

NOMINALLY AT 2H:1V, AND WOULD BE SUBJECT TO

GEOTECHNICAL INSPECTION AT THE TIME OF

EXCAVATION.

IF GROUNDWATER IS ENCOUNTERED AT THE TIME

OF EXCAVATION, ADDITIONAL GEOTECHNICAL

ADVICE SHOULD BE SOUGHT FROM PROJECT

GEOTECHNICAL ENGINEER. DEEP EXCAVATIONS

THAT ENCOUNTER SOFT OR WET MATERIALS WILL

PROBABLY REQUIRE THE USE OF A ROCK

BRIDGING LAYER ACROSS THEIR BASE TO

FACILITATE COMPACTION OF SUBSEQUENT

FILLING. ADDITIONAL ADVICE SHOULD BE SOUGHT

FROM PROJECT GEOTECHNICAL ENGINEER IN

THIS REGARD, AS NECESSARY.

1% SLOPE

CONTAINMENT KERB SEE A3

C-603

TK: 133.47

BK: 133.32

NOTES

1. SEE MECHANICAL DRAWINGS FOR TANK MANHOLES AND ROLLING COVERS DETAILS.

2. SEE SPECIFICATION SECTIONS FOR CONCRETE, FORMWORK, WATERSTOPS,

REINFORCEMENT, PLACEMENT AND CURING.

3. LAP SPLICES AND CONCRETE COVER SHALL CONFORM TO REQUIREMENTS

OF S-001 WHERE NOT SPECIFICALLY INDICATED ON THESE DETAILS.

4. JOINT SEALANT SHALL CONFORM TO DETAIL A3 SHEET C-610.

5. SEE DETAIL A1 SHEET C-610 FOR CONSTRUCTION JOINT (CJ) DETAILS.

6. SEE DETAIL A5 SHEET C-604 FOR SLAB PENETRATIONS

7. SEE DETAIL D5 SHEET C-610 FOR KEYED JOINT (KJ) DETAILS.

CONTAINMENT KERB SEE A3

C-603

1% SLOPE

1% SLOPE

CONTAINMENT INLET SEE

A4

C-612

1% SLOPE

A3 C-603

CONTAINMENT INLET SEE

A4

C-612

EXCAVATION SLOPE

SEE NOTE 3

EL. 133.197

CONTAINMENT INLET

SEE A4

C-612TK:133.35

BK:133.20

NOTES

1. SEE MECHANICAL DRAWINGS FOR TANK MANHOLES AND ROLLING COVERS DETAILS.

2. SEE SPECIFICATION SECTIONS FOR CONCRETE, FORMWORK, WATERSTOPS,

REINFORCEMENT, PLACEMENT AND CURING.

3. LAP SPLICES AND CONCRETE COVER SHALL CONFORM TO REQUIREMENTS

OF S-001 WHERE NOT SPECIFICALLY INDICATED ON THESE DETAILS.

4. JOINT SEALANT SHALL CONFORM TO DETAIL A3 SHEET C-610.

5. SEE DETAIL A1 SHEET C-610 FOR CONSTRUCTION JOINT (CJ) DETAILS.

6. SEE DETAIL A5 SHEET C-604 FOR SLAB PENETRATIONS.

TK:133.35

BK:133.20TK:133.35

BK:133.20

TK:133.35

BK:133.20

EL: 133.033

TK:133.35

BK:133.033

TK: 133.47

BK: 133.32

TK: 133.47

BK: 133.32

TK: 133.47

BK: 133.32

TK: 133.47

BK: 133.197

C J

C J

KJ

C J

C J

SEALED EXPANSION JOINT A2

C-610

EXPANSION JOINT (EJ)

EXPANSION JOINT (EJ)

50mm SAND BEDDING WITH 200um BUILDERS PLASTIC

100mm DEPTH OF SUBGRADE

COMPACTED TO 95% M.M.D.D MIN CBR 10.

PA

F1

AP

R

JE

T

FU

EL

S

TO

R

AG

E

TA

N

KS

R O

YA

L

AU

ST

R

AL

IA

N

A

IR

F O

R C

E R

AA

F

BA

SE

T

IN

D

AL

. A U

ST

R

AL

IA

1606003

DA

LE

JC

LE

AS SHOWN

17254268

CT AD RA

C

IV

IL

D

ET

AI

LS

C-603

HDR Engineering, Inc.

1001 Bishop Street Suite 400 Honolulu, HI 96813 Phone: (808) 697-6200

10/30/2020

G

EO

TE

C

H N

IC

AL

R

EV

IS

IO

N

J

AN

2021-01-14T14:53:19-1000
EVAN MIZUE
I authorize this document.
2021-01-14T14:53:34-1000
EVAN MIZUE
I authorize this document.
2021-01-14T14:53:34-1000
EVAN MIZUE
I authorize this document.
2021-01-14T14:53:46-1000
EVAN MIZUE
I authorize this document.
2021-01-14T14:54:00-1000
EVAN MIZUE
I authorize this document.
2021-01-14T14:54:01-1000
EVAN MIZUE
I authorize this document.
2021-01-14T14:54:01-1000
EVAN MIZUE
I authorize this document.