21R1300_Notice12-Issued.pdf
PDF 671 KB Posted
- Attached to
- FY20 MCAF PAF180200 APR - JET FUEL STORAGE TANKS, ROYAL AUSTRALIAN AIR FORCE BASE TINDAL, AUSTRALIA
- Solicitation number
- N6274221R1300
About this file
This document contains questions and answers related to a solicitation for construction of jet fuel storage tanks and support infrastructure at Royal Australian Air Force Base Tindal in Australia. The solicitation seeks a design-build contractor to construct two 25,000-barrel cut-and-cover bulk fuel tanks, along with two pump houses, a liquid fuel truck fill stand, fuel stand unloading and filter building, utilities, automatic tank gauging systems, site improvements, pavements, communications infrastructure, a backup generator, and other work to provide a complete and usable facility. Additionally, there are three pre-priced options for concrete vs. asphalt pavements, a cross over pit for fuel transfer lines, and a hydrant-hose checkout station. The document provides answers to clarify that unexploded ordnance clearance will be completed prior to site possession and certification will be provided to the contractor. Security escort requirements and limitations are also defined.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE NAVY
NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND, PACIFIC
258 MAKALAPA DR., STE. 100
JBPHH, HI 96860-3134
RFP N62742-21-R-1300
Notice No. 12
25 February 2021
PRE-PROPOSAL QUESTIONS & ANSWERS
RFP N62742-21-R-1300
WON 1606003, FY20 MCAF PROJECT
PAF180200 APR JET FUEL STORAGE TANKS,
ROYAL AUSTRALIAN AIR FORCE (RAAF) BASE TINDAL,
AUSTRALIA
NOTE: The following questions and answers are provided for INFORMATION ONLY. The RFP remains unchanged unless it is amended in writing on a Standard Form 30.
RESPONSES DEFERRED FROM NOTICE NO. 8 DATED FEBRUARY 9, 2021:
99. Section 01 14 00, Paragraph 1.4.3.2, Security Escort, describes the necessity of this observation during construction. To determine contractor costs, we require additional definition of this requirement.
a. What is the timeline for the contractor personnel to receive the training and authorization?
b. Is there a fee involved to obtain the escort authorization?
c. Can the contractor personnel have collateral duties as a member of the crew?
d. Is there a limit in the size of a crew a single escort is responsible for?
ANSWER:
a. There is no escort training available.
b. There is no fee to obtain the escort authorization.
c. Yes, the Contractor personnel may have collateral duties as long as they can fulfill their full-time occupation.
d. Single escort is limited to a crew size of 6 persons.
101. Unexploded Ordnances
Section 31 11 00 – Clause 3.1.1.4 States - ‘The works area has previously been cleared of unexploded ordinances.
Section 01 35 13.01 of General Requirements P 2.1.4 (Item ‘n’) Handover Takeover
(HOTO) Phase States – ‘Provided the following HOTO submittals 14 calendar days before Beneficial Occupancy Date (BOD)’ – ‘Unexploded Ordnance (UXO) certifications with maps and GPS points of boundaries clearance (plus to the required depth)
RFP N62742-21-R-1300
Can you please clarify that UXO will be cleared prior to site possession and a UXO Certification will be provided to the Contractor for inclusion in the HOTO Phase documentation?
ANSWER: The works area has previously been cleared of unexploded ordinances as specified in Section 31 11 00. UXO Certification will be provided.