CDRL A004 PRODUCTION PLAN H-53 v2.pdf

PDF 321 KB Posted

Attached to
H-53E Aircraft Maintenance and Repair Services
Solicitation number
N6264920R0003
Issued by

About this file

This document contains a Contract Data Requirements List (CDRL) and details of a related federal contract opportunity for H-53E aircraft maintenance and repair services. The CDRL outlines production plan requirements for contractors performing Planned Maintenance Interval Depot events and In-Service Repair work on H-53E aircraft for the Navy and Marine Corps deployed in the Western Pacific region. Key requirements specified in the CDRL include depicting full schedules from aircraft arrival through delivery, identifying all tasks with predecessors and resource needs in Microsoft Project format, and submitting production plan revisions within five days of evaluation phases or delays. The related solicitation provides additional context, seeking contractors with H-53E experience to support Fleet Readiness Center Western Pacific through planned and unplanned depot-level maintenance, repair, and overhaul products and services for the aircraft.

View the file

Other files

File Type Posted
N6264920R0003 AMD 0004.docx DOCX document
N6264920R0003 AMD 0004 CONFORMED.docx DOCX document
ANSWERS H-53E_Q_AND_A_23MAR2020.xlsx XLSX spreadsheet
N6264920R0003_AMD_0003.pdf PDF
N6264920R0003 AMD 0002.pdf PDF
CDRL C002 PRESENTATION DOCUMENTATION H-53 v2.pdf PDF
Q and A N6264920R0003 AMD 0002.pdf PDF
N6264920R0003 AMD 0002 CONFORMED.docx DOCX document
H-53E Att 01 Performance Work Statement (PWS) (2020-01-21).docx DOCX document
N6264920R0003 MOD 0001.docx DOCX document
CDRL A002 TECHNICAL DIRECTIVES REPORT H-53 v1.pdf PDF
N6264920R0003 MOD 0001 Conformed.docx DOCX document
CDRL C002 PRESENTATION DOCUMENTATION H-53 v1.pdf PDF
CDRL D002 TRANSITION STATUS REPORT H-53 v1.pdf PDF
CDRL A003 TDC KIT RECEIPT AND REPORTING OF KIT DISCREPANCY REPORT H-53 v1.pdf PDF
CDRL A010 MAINTENANCE HISTORY SUMMARY REPORT H-53 v1.pdf PDF
H-53E Att 06 LMR Process at Contractor Facilities (2020-01-09).docx DOCX document
CDRL G001 MONTHLY MATERIAL EXPENSE REPORT H-53 v1.pdf PDF
CDRL B004 RECEIPT REPORT H-53 v1.pdf PDF
CDRL D004 CONTRACTOR TRAINING PLAN H-53 v1.pdf PDF
CDRL F001 INTEGRATED MASTER SCHEDULE H-53 v1.pdf PDF
N6264920R0003 H-53 RFP.docx DOCX document
H-53E Att 10 GFP List (2020-01-09).xlsx XLSX spreadsheet
CDRL B003 AIRCRAFT AWAITING PARTS (AWP) REPORT H-53 v1.pdf PDF
CDRL B012 COST PER BUNO REPORT H-53 v1.pdf PDF
CDRL B005 SUPPLY EFFECTIVENESS REPORT H-53 v1.pdf PDF
CDRL B008 SUPPORT EQUIPMENT (SE) MAINTENANCE HISTORY REPORT H-53 v1.pdf PDF
CDRL L001 TECHNICAL DATA INVENTORY LIST H-53 v1.pdf PDF
H-53E Att 09 Fac and AF Req (2020-01-09).docx DOCX document
H-53E Att 08 PEMA Specs (2020-01-09).docx DOCX document
H-53E_Att_14_Price_Summary_Spreadsheet_(2020-01-09).xlsx XLSX spreadsheet
H-53E Att 12 H-53E PMID Induction Schedule (2020-01-29).xlsx XLSX spreadsheet
CDRL D001 PHASE-IN TRANSITION PLAN H-53 v1.pdf PDF
CDRL C001 MEETING MINUTES H-53 v1.pdf PDF
H-53E_Att_13_Past_Performance_Questionnaire_(2020-01-09).docx DOCX document
CDRL A008 EXAMINATION & EVALUATION (E&E) DISCREPANCY REPORT H-53 v1.pdf PDF
CDRL B011 SUPPORT EQUIPMENT (SE) MAINTENANCE AND CALIBRATION REPORT H-53 v1.pdf PDF
H-53E Att 07 TEI Process at Contarctor Facilities (2020-01-09).docx DOCX document
H-53E Att 02 Gov Relationships&Resp (2020-01-09).docx DOCX document
CDRL B013 PARTS REQUIRED REPORT (PRR) H-53 v1.pdf PDF
H-53E Att 03 QASP (2020-01-09).docx DOCX document
CDRL A006 SCHEDULED REMOVAL CARDS H-53 v1.pdf PDF
CDRL B010 ANNUAL PHYSICAL INVENTORY H-53 v1.pdf PDF
CDRL B001 DAILY REQUISITION REPORT (DRR) H-53 v1.pdf PDF
CDRL B007 FINAL MATERIAL CONSUMPTION REPORT H-53 v1.pdf PDF
CDRL A005 NOTIFICATION OF AIRCRAFT DELAY H-53 v1.pdf PDF
H-53E Att 04 OSH and Env (2020-01-16).docx DOCX document
CDRL A001 TECHNICAL DIRECTIVES REPORT 10 DAY REPORT H-53 v1.pdf PDF
CDRL A009 NOTED BUT NOT CORRECTED (NBNC) REPORT H-53 v1.pdf PDF
CDRL B006 ACTIVE ITEM REPORT H-53 v1.pdf PDF
Show 40 more

Latest 50 of 56 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 1 of 2 Pages Adobe Professional 8.0

18. ESTIMATED

TOTAL PRICE

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER

D. SYSTEM/ITEM

H-53E PMID AIRCRAFT

E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO.

A004

2. TITLE OF DATA ITEM

PRODUCTION PLAN H-53E

3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE

PWS

6. REQUIRING OFFICE

FRCWP Production

7. DD 250 REQ

NO

9. DIST STATEMENT

REQUIRED

NONE

10. FREQUENCY

BLOCK 16

12. DATE OF FIRST SUBMISSION

BLOCK 16

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

BLOCK 16

13. DATE OF SUBSEQUENT

SUBMISSION

BLOC

K 16

Draft Final

Reg Repro

16. REMARKS

(1) Purpose: The Contractor’s Production Plan (PP) will provide the Government a detailed and effective tool for understanding the Contractor’s production process for an aircraft in flow. The Government will use the Plan to track progress, aid in understanding the Contractor's US Government dependencies and track changes throughout the PMI.

(2) Requirements:

(a) The PP shall portray the schedule from aircraft arrival through to return of the aircraft to the Government. The plan shall demonstrate how the contractor will meet the CDD. While the CDD is set using calendar days, the PP shall accurately indicate days work is being performed. Holidays and weekends shall not lists tasks unless the Contractor intends to perform work on those days.

(b) The PP shall include the following phases as applicable: Induction, Disassembly, Strip, Paint, Evaluation/Inspection, Repair, Reassembly, Operational Checks, Functional Check Flight (FCF) and Delivery.

(c) The PP shall list every task that is required to be performed prior to the aircraft completing PMI, including modifications, CSRs, etc. Individual tasks shall be grouped under the applicable phase and each individual task shall be no longer than 15 days without Government COR concurrence. Tasks may be grouped if they have common predecessors and resource constraints (for example, most tasks would generally be 1-4 days in length (i.e.

Repair Corrosion Zone 1).

(d) Each task shall indicate all other tasks, called predecessors, which are required for its completion. Tasks that are interchangeable in order shall not be listed as predecessors.

(e) The PP shall indicate what major constrained resources are needed for a particular task (i.e. 2 mechanics, 1 avionics, paint hanger, etc.) and lay the schedule out chronologically avoiding any resource constraints. Tasks shall not be made predecessors to account only for resource constraints.

(f) The PP shall identify and document Request for Engineering Instruction (REI) and Material Requisitioning submission as identified in CDRL A003, and the latest need by date for their return. These need by dates shall be the same across all CDRLs. The PP shall also account for work that is not performed by the Contractor but is needed for completion of

PMI,

FRCWP Prod 1

DCMA

15. TOTAL 0 3 0

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

17. PRICE GROUP

FRCWP Bus Ops

FRCWP Comptroller 1

A

Reset

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER

D. SYSTEM/ITEM

H-53 PMID AIRCRAFT

E. CONTRACT/PR NO. F. CONTRACTOR

16. REMARKS (Continued) however tasks performed by external entities need not be broken down and can exceed 15 days.

(g) The PP shall explicitly identify the critical path in the process. All REIs and parts affecting the critical path shall be clearly indicated.

(3) Format: The PP shall be submitted as a Microsoft Project document or Government approved equivalent (Excel is acceptable); along with an Adobe PDF copy of the Gantt View. The PP shall contain the Gantt chart and a minimum of the following fields: Task Name, % Complete, Baseline Start and Finish, Current (Scheduled) Start and Finish, Actual Start and Finish, Duration, Predecessors and Resources. Deviations from these minimum fields may be approved with the concurrence of the COR.

(4) Frequency:

(a) An initial PP shall be submitted with the Contractor’s response to the Government’s Induction Package for each Aircraft. For the initial submission, tasks that will be performed after the completion of the evaluation phase may be planned at a high level, can exceed 15 days in duration and do not need to include supply or REI need by dates or resources.

(b) A revised PP shall be submitted within 5 work days from completion of the Evaluation Phase to include the submission and need by dates for all REIs and parts not already in stock. The Repair phase shall account for all non-NBNC discrepancies found during the Evaluation phase. If the work required for the discrepancies will cause the schedule to extend the TAT the Contractor shall inform the Government at this time for consideration of possible extensions. Once the post-evaluation PP has been accepted by the Government extensions for excessive discrepancies discovered during the Evaluation Phase may not be granted.

(c) A revised PP shall be provided alongside notifications of delay.

(d) Each new PP revision shall be re-base-lined (i.e. Baseline 1, 2, 3, etc.); progress updates shall not be re-base-lined.

(e) The PP progress shall be updated and available for review and/or discussion during all production status meetings, technical interchange meetings, and Program management Reviews (PMR). This includes updating actual start and finish dates and % complete. Percent complete shall be time-based (i.e. not number of work cards completed), however the Contractor may choose the calculation method (i.e. days of work remaining, 0% start & 100% finish, etc.).

(5) Initial Production Plan and all revisions shall be emailed to FRCWP/DCMA at: usn.atsugi.frcwp.mbx.h53-contract@mail.mil Subject line of email shall include CDRL Number and Title

(6) The Government shall have five working days for review and acceptance/rejection of each submission. No response will indicate acceptance.

DD FORM 1423-1, FEB 2001 Page 2 of 2 Pages mailto:usn.atsugi.frcwp.mbx.h53-contract@mail.mil