About this file
This document contains a Contract Data Requirements List (CDRL) and details of a related federal contract opportunity. The CDRL outlines reporting requirements for a Technical Directives Requirement 10 Day Report to be submitted within 10 work days of an H-53E aircraft being inducted for Planned Maintenance Interval Depot services. It specifies the format, frequency of submission, and acceptance criteria for the report, which identifies Technical Directives required for incorporation after review of aircraft logbooks and lists.
The related federal contract opportunity is a solicitation from the Department of the Navy seeking proposals for H-53E Aircraft Maintenance and Repair Services to support the United States Marine Corps and Navy. It will provide depot-level maintenance, repair, and overhaul products and services for H-53E aircraft forward deployed or operating in the Western Pacific region through planned maintenance interval depot events and in-service repair requirements. The solicitation is issued by Fleet Logistics Center Yokosuka on behalf of Fleet Readiness Center Western Pacific and contains attachments outlining proposal submission requirements and contract data requirement lists.
View the file
Other files
Show 40 more
Latest 50 of 56 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 1 of 2 Pages Reset
18. ESTIMATED
TOTAL PRICE
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services and Communications Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
A
C. CATEGORY: X
TDP TM OTHER
D. SYSTEM/ITEM
H-53E PMID AIRCRAFT
E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A001
2. TITLE OF DATA ITEM
TECHNICAL DIRECTIVES REQUIREMENT
10 DAY REPORT H-53E
3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE
PWS
6. REQUIRING OFFICE
FRCWP Production
7. DD 250 REQ
NO
9. DIST STATEMENT
REQUIRED
NONE
10. FREQUENCY
BLK 16
12. DATE OF FIRST SUBMISSION
BLK 16
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. APP CODE
N/A
11. AS OF DATE
BLK 16
13. DATE OF SUBSEQUENT
SUBMISSION
BLK 16 Draft
Final
Reg Repro
16. REMARKS
(1) Description: Contractor shall submit Technical Directives Requirement 10 Day Report report within 10 work days after an aircraft is inducted to PMI.
(2). Purpose: This document identifies Technical Directives required for incorporation after review of the aircraft logbooks, List 02 and List 04, or the PMI special work request. This document is required also for aircraft initial inspection.
(3) Format: A sample document is attached.
(4) Frequency: 10 work days after PMI aircraft is inducted.
Shall be emailed to FRCWP at: usn.atsugi.frcwp.mbx.h53-contract@mail.mil.
Subject line of email shall include CDRL Number and Title
(5) Acceptance: The Government shall have five working days for review and acceptance/rejection of each submission. No response will indicate acceptance.
FRCWP Prod 1 FRCWP Bus Ops 1
DCMA 1
15. TOTAL 0 3 0
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
17. PRICE GROUP
mailto:usn.atsugi.frcwp.mbx.h53-contract@mail.mil
Date:
From: Contractor To: FRCWP AFC Mod Manager Via: DCMA Subj: AIRCRAFT CONFIGURATION - 10 DAY REPORT FOR T/M/S BUNO
FRCWP's DECISION
TD NO. SUBJECT KIT FUND CODE COMPLY/NBNC NOTE
AFC-519 Pt3
INTERGRADED MECHANICAL DIAGNOSTICS SYSTEM (IMDS)
INSTALLATION OF
A3/A4
AFC-540
ADVANCED DIGITAL ANTENNA PRODUCTION (ADAP) SYSTEM,
INSTALLATION OF
A2/A3
AFC-562 Pt2
CRASH ATTENUATING CREW CHIEF SEAT, INSTALLATION IN
THE MH HELICOPTERS
A1
AFC-573
REPLACEMENT OF STARBOARD FORWARD AND AFT GUN
MOUNT BRACKETS
A1
AFC-583 AM1 PANEL, TAKEOFF LANDING INSTRUCTION, REPLACEMENT OF NA
AFB-339 REV-A
ONE TIME INSPECTION FOR RADIOLOGICAL CONTAMINATION
OF AIRCRAFT AND WRA
NA
AFB-340 REV-A
SWITCH GUARD SHEARWIRE INSTALLATION PN MS25225-1,
INSPECTION OF
NA
DCB-169
MAIN GEARBOX (MGB) INPUT DRIVE SHAFT FLANGE CRACKS,
INSPECTION OF
NA