Attachment N - 01 45 35_Statement_of_Special_Inspections.xlsx

XLSX spreadsheet 161 KB Posted

Attached to
Design-Bid-Build, USCG Offshore Patrol Cutters (OPC) Homeport Pier, Naval Station Newport, Newport RI
Solicitation number
N4008526R0001
Issued by

About this file

This is a Statement of Special Inspections for the USCG Offshore Patrol Cutters (OPC) Homeport Pier project located at Naval Station Newport, Rhode Island (Project #1826479). The document establishes inspection and compliance requirements for a seismic design category E structure with a risk category III classification, one story above grade, and a structure height of 40 feet.

The file mandates that a Special Inspector of Record (SIOR) must be assigned prior to construction start. The SIOR must be a registered professional engineer independent of the general contractor and subcontractors, though may serve as the project structural engineer of record. Key inspection responsibilities include monitoring the lateral force-resisting system (LFRS), specifically pile-to-cap connections and the concrete topping slab to precast planks within the pier deck system. The document also identifies Designated Seismic Systems (DSS) that must comply with UFC 3-301-01 requirements, remain operable after a design earthquake, and include manufacturer Certificates of Compliance. A final walk-down inspection by the Registered Design Professional in Responsible Charge is required, with documentation maintained in an "Equipment Certification Documentation" file as part of the final project Operations & Maintenance Manual. The contractor must complete the associated Schedule of Special Inspections template referenced in the UFC 3-301-01 criteria document.

View the file

Other files

File Type Posted
USCG OPC Pier Amendment 0009 Drawings.pdf PDF
2026-0816-HAI-USCG Homeport OPC Pier-Geotech Engineering Report Rev 2.pdf PDF
Amendment 0009 USCG OPC.pdf PDF
Updated Attachment H - USCG OPC Pier Price Proposal Form REV 5.docx DOCX document
Amendment 0008 USCG OPC.pdf PDF
Amendment 0007 SPC USCG OPC Pier Appendix D (With Placeholders).pdf PDF
Updated Attachment H - USCG OPC Pier Price Proposal Form REV 6.docx DOCX document
USCG OPC Pier Amendment 0008 Drawings.pdf PDF
USCG OPC Pier Amendment 007 Drawings.pdf PDF
Amendment 0007 USCG OPC.pdf PDF
Attachment Z - Pier 1 - Amendment 006 Drawings.pdf PDF
Appendix A - Telecom Room Photos.pdf PDF
Updated Attachment H - UCCG OPC Pier Price Proposal Form REV 4.docx DOCX document
Amendment 0006 USCG OPC.pdf PDF
24.168 NOAA OMAO Prime Pier Pile Driving Summary Report.pdf PDF
Pier Pile Plan.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.26.24 to 08.30.24 (1).pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 07.22.24 to 07.26.24.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 07.15.24 to 07.19.24.pdf PDF
Attachment Y - Appendix A Record drawing 11836 125 Submarine Cable Relocation.pdf PDF
SUB-0123 Interim PDA and Test Pile Logs - Trestle Piles 10B 14B.pdf PDF
SUB-0TBD Interim PDA and Test Pile Logs For Trestle Pile 17B.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.26.24 to 08.30.24.pdf PDF
Updated Attachment H - UCCG OPC Pier Price Proposal Form REV 3.docx DOCX document
SUB-0105 Trestle Piles 4C 6B - PDA and Test Pile Logs.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.20.24 to 08.23.24.pdf PDF
24.107 NOAA OMAO Ship & Support Facility Relocation Newport RI - PDA Report - Pier Bent 19.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 06.25.24 to 06.27.24.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 07.31.24 to 08.01.24.pdf PDF
SUB-0284 PDA49B_A.pdf PDF
SUB-0262 Interim PDA Test Pile Logs for Pier Piles - Bent 35 B - A.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.07.24 to 08.08.24.pdf PDF
Trestle Summary.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.20.24 to 08.23.24 (1).pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 07.01.24 - 07.02.24.pdf PDF
Bulkhead Pile Plan.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 09.03.24 to 09.06.24.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.13.24 to 08.15.24.pdf PDF
Attachment W - Pier 1 - Amendment 005 Drawings.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 07.11.24.pdf PDF
24.107 NOAA OMAO Ship Support Facility Relocation Newport RI - PDA Report - Pier Bent 25 and 27.pdf PDF
NOAA OMAO Survey Reports 100 Percent Pre-Final Submittal 04072022.pdf PDF
Amendment 0005 USCG OPC.pdf PDF
Attachment X - Appendix A Record Drawing 12819 135 Submarine Cable.pdf PDF
Attachment U - Appendix A - Pier 1 Extension 1968.pdf PDF
Attachment V - Pier 1 - Amendment 004 Drawings.pdf PDF
Updated Attachment K - WD RI20260001 05-18-2026.pdf PDF
Amendment 0004 USCG OPC.pdf PDF
Attachment T - REF(m) Existing Pier 1 Drawings 1 of 2.pdf PDF
Attachment C - Construction Experience Project Data Sheet.docx DOCX document
Show 40 more

Latest 50 of 90 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Project:USCG OPC Pier ProjectUSER NOTES (Not intended to print)
Location:NAVSTA Newport, RI
Project #:1826479
Date:

STATEMENT OF SPECIAL INSPECTIONS < Edit Blue text/cells only

Seismic Design Category:ESPECIAL INSPECTOR OF RECORD (SIOR) DETERMINATIONAIYes
Risk Category:IIIBIINo
Number of Stories above Grade:1< The Special Inspector of Record (SIOR) is a DOD mandate. Enter the requested data to determine whether an SIOR is required or is not required.CIII
Structure Height Above Grade (ft):40DIV
Hazardous Occupancy or attached to such?NoGroup H OccupanciesEV
F
Special Inspector of Record (SIOR)
A Special Inspector of Record (SIOR)ISrequired (per UFGS 01 45 35, Section 1.3.7)
SIOR Name (Registered Professional):Contractor to provide prior to construction start.
Professional Registration Number:< For DB contracts insert the SIOR contact information. For DBB contracts enter, "Contractor to provide prior to construction start".
Consulting Firm Name (if any):
SIOR Office AND Mobile Phone Number:< The SIOR must be a registered professional engineer, and must not be an employee of the General Contractor or sub-contractor, but may be the project structural engineer of record if desired. Where did this come from?
Lateral Force Resisting System (LFRS)
2024 IBC 1704.3.2 and 1704.3.3LATERAL FORCE RESISTING SYSTEM IDENTIFICATION
Following is a listing of critical elements of the main wind/seismic force-resisting system for this structure. Carefully inspect these elements as part of the roles and responsiblities of the Special Inspector (reference the Schedule of Special Inspections for inspection checklists).
Vertical LFRS ElementsNotes
ASCE 61 Pile to Cap ConnectionsPier Piles to Piles Caps
Horizontal LFRS ElementsNotes
Concrete Topping slab to pre-cast planksPier deck system
Statement of Special Inspections Page 1 of 2
Project:USCG OPC Pier Project
Location:NAVSTA Newport, RIDESIGNATED SEISMIC SYSTEMS (DSS)
Project #:1826479This section identifies whether Designated Seismic Systems apply to this project or do not apply. Additionally, and where DSS apply, some explanation is provided below for what a Designated Seismic System is for this specific project.
Date:12/31/99
Designated Seismic Systems (DSS)
(2024 IBC 1705.13.4) (ASCE 7-22, 13.2.3, C13.2.2) (UFC 3-301-1, 2-5.3)
'Designated Seismic Systems' (DSS) must remain operable and continue to contain hazardous substances following a design earthquake. Accordingly, all Designated Seismic Systems must be listed below and must be certified by the manufacturer to remain both operable and/or to contain hazardous substances after a design earthquake per UFC 3-301-01, Section 3-5.2. Submit said Certificates of Compliance to the Contracting Officer for each DSS after they have been reviewed and accepted by the EOR/DOR. Additionally, the below listed Designated Seismic Systems must be carefully inspected by the Special Inspector according to the requirements noted in the Schedule of Special Inspections, Section BB.
ELECTRICAL Components that are part of the Designated Seismic System (DSS) , which require a Certificate of Compliance< Designated Seismic Systems APPLY to this project. List all Designated Seismic Systems in the blue tables below. Some DSS suggestions are already populated, delete or keep as necessary.
DSS for this project are nonstructural components with an importance factor of 1.5 AND with the following project conditions (UFC 3-301-01 SECTION 3-3.3) (ASCE 7-22, 13.2.3):
1.N/A
2.
3.
4.1. The component is required to function for life-safety purposes after an earthquake, including fire sprinkler systems and egress stairways (RC I thru V + SDC C thru F).
5.
If additional space is required, append an additional sheet listing the remaining DSS
MECHANICAL/PLUMBING Components that are part of the Designated Seismic System (DSS), which require a Certificate of Compliance2. The component conveys, supports, or otherwise contains toxic, highly toxic, or explosive substances where the quantity of the material exceeds a threshold quantity established by the Authority Having Jurisdiction and is sufficient to pose a threat to the public if released (RC I thru V + SDC C thru F).
1.N/A
2.
3.
4.
5.3. The component conveys, supports, or otherwise contains hazardous substances and is attached to a structure, or portion thereof, classified by the authority having jurisdiction as a hazardous occupancy (RC I thru V + SDC C thru F).
6.
If additional space is required, append an additional sheet listing the remaining DSS
OTHER Designated Seismic Systems (DSS) requiring a Certificate of Compliance
1.N/A
2.
3.
4.
5.
6.
Final Walk-Down Inspection and Report
(UFC 3 301 01 SECTION 2-5.4)FINAL WALK DOWN INSPECTION AND REPORT FOR DSS
Designated Seismic Systems shall receive a final walk-down inspection by the Registered Design Professional in Responsible Charge
< A DSS final walk down inspection applies to this project
Final Walk-Down Report, Prepared by the Registered Design Professional in Responsible Charge, must Include:
1. Record observations of Final Walk-Down Inspection
2. Document that Inspections were performed in accordance with the Schedule of Special Inspections
3. Document that all Designated Seismic Systems are installed according to construction/manufacturer document requirements, and that Compliance Certificates have been collected (UFC 03 301 01, 3-5.2, 13.2.3.2).< …Certificates of compliance documenting that the requirements are met shall be maintained in a file identified as "Equipment Certification Documentation". This file shall be part of the final project O&M Manual

Statement of Special Inspections Page 2 of 2

NEXT: COMPLETE THE SCHEDULE OF SPECIAL INSPECTIONS TEMPLATE.
Edit, print, and append the Schedule of Special Inspections Template to this Statement of Special Inspections and insert both at the back of the Special Inspections Specification. SI schedule template: https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-301-01

Example entries are provided, replace/delete as necessary image1.png image2.jpeg image3.jpeg