GSA 01 32 20 Photographic Documentation.docx

DOCX document 3 MB Posted

Attached to
Design Build Construction Services for the Santa Teresa Land Port of Entry (LPOE) Border Roadway Improvement & Construction (BRIC)/Paving Project, Santa Teresa, NM
Solicitation number
47PH0825R0007
Issued by
Not on record

About this file

This document is a Section 013220 Photographic Documentation specification for the Santa Teresa Land Port of Entry Border Roadway Improvement & Construction (BRIC) Project in Santa Teresa, New Mexico. The specification details comprehensive requirements for photographic and video documentation during the construction project, mandating that the contractor capture and submit digital photographs and videos with specific technical parameters, including a minimum 16-megapixel digital camera resolution, JPEG format, and detailed metadata for each image.

The photographic documentation requirements include preconstruction site photographs (minimum 10 images), weekly construction progress photos (minimum 5 images per session), and special photographs (at least 48 total images taken 6 times during construction). Contractors must submit digital files to the GSA's Kahua PMIS system within 3 calendar days of capture, with each image and video labeled with project details such as project name, number, location, photographer information, weather conditions, and contract number. Construction videos must document concrete and asphalt placements, with continuous running time displayed and weather conditions recorded at the start of each video.

View the file

Other files

File Type Posted
Amendment 3 - 47PH0825R0007 2026 01 29.pdf PDF
Amendment 2 - 47PH0825R0007 2026 01 16.pdf PDF
Pricing Sheet 2026 01 16.xlsx XLSX spreadsheet
Amendment 1 - 47PH0825R0007 2026 01 09.pdf PDF
SOLICITATION 47PH0825R0007 2025 12 12.pdf PDF
GSA 01 33 00 Submittal Procedures.docx DOCX document
GSA 01 60 00 PRODUCT REQUIREMENTS.docx DOCX document
GSA 01 31 10 Prospectus CPM Schedule Specs.docx DOCX document
CBS Submittal Matrix.pdf PDF
P-120 PBS Cost and Schedule Management.pdf PDF
B. 1. NM20250039 Heavy 2025 01 24.pdf PDF
GSA 01 73 10 CUTTING PATCHING.docx DOCX document
GSA 01 59 50 - SAFETY AND HEALTH.docx DOCX document
GSA 01 29 00 PAYMENT PROCEDURES.docx DOCX document
GSA 01 25 00 Subst. Procedures.docx DOCX document
GSA 01 50 00 TEMPORARY FACILITIES and CONTROLS.docx DOCX document
DB Communications Plan Template FY25.docx DOCX document
AGREEMENT 47PH0825R0007 2025 12 12.pdf PDF
F. Pricing Sheet Santa Teresa LPOE 08_14_2025.xlsx XLSX spreadsheet
GSA 01 74 19 CONSTRUCTION NONHAZARDOUSE WASTE REMOVAL.docx DOCX document
GSA 01 30 00 PROJECT MANAGEMENT INFORMATION SYSTEM.docx DOCX document
GSA 01 70 00 EXECUTION REQUIREMENTS.docx DOCX document
GSA 01 78 10 PROJECT RECORD DOCUMENTS.docx DOCX document
GSA 01 14 00 Work Restrictions.docx DOCX document
GSA 01 42 00 GENERAL REFERENCES.docx DOCX document
Santa Teresa LPOE - Geotechnical Report.pdf PDF
C. GSA 527-21 - Contractor's Qualifications and Financial Information.pdf PDF
D. Standard Form 24 Bid Bond.pdf PDF
E. SF1442 47PH0825R0007 2025 12 12.pdf PDF
B. 2. NM20250035 Highway 2025 06 06.pdf PDF
A. Past Performance Questionnaire Factor 1.pdf PDF
GSA 01 31 00 PROJECT MANAGEMENT COORDINATION.docx DOCX document
GSA 01 40 00 QUALITY ASSURANCE QUALITY CONTROL REQUIREMENTS.docx DOCX document
GSA 01 24 00 Options.docx DOCX document
GSA 01 77 00 CLOSEOUT PROCEDURES.docx DOCX document
GSA 01 73 20 SELECTIVE DEMOLITION.docx DOCX document
GSA 01 27 00 Unit Prices.docx DOCX document
GSA 01 10 00 SUMMARY.docx DOCX document
GSA 01 32 00 Construction Progress Documentation.docx DOCX document
GSA 01 59 30 SECURITY REGULATIONS.docx DOCX document
PBS_Core_Building_Standards_Memorandum 24FEB25.pdf PDF
SOW 47PH0825R0007 2025 12 12.pdf PDF
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Santa Teresa Land Port of Entry BRIC Santa Teresa, New Mexico Kahua #353

SECTION 013220 - PHOTOGRAPHIC DOCUMENTATION

PART 1 GENERAL

1.1 GENERAL

A. Regular Construction Progress Photos. Contractor shall document on a monthly basis, key components of the contract document. In addition, Contractor shall document milestones such as inspections, concrete/asphalt placements and other significant occurrences as necessary or with the daily reports.

1.2 SUBMITTALS

A. Digital Photographs: Contractor shall submit and/or upload to (Kahua) PMIS electronic files of each view to the GSA. Submit image files within 3 (three) calendar days of taking photographs.

1. Digital Camera: Minimum resolution of 16 megapixels.

2. Format: Minimum 1080 by 720 pixels, in unaltered original files, with same aspect ratio as the sensor, un-cropped, in a folder named by date of photograph.

3. Identification: Provide the following information with each image description in file metadata tag:

a. Name of Project.

b. Project number.

c. Facility name/location where photo was taken.

d. Project region.

e. Name and contact information for photographer.

f. Name of Architect.

g. Name of Contractor.

h. Contract number.

i. Date photographs were taken.

j. Weather conditions.

B. Construction Videos: Contractor shall upload concrete/asphalt placements to (Kahua) PMIS each video to GSA within 3 days of recording. Videos shall

1. Identify each video with the same identification information stated under Digital Photographs.

2. Transcript: Photographer shall upload to (Kahua) PMIS an electronic narrative for each video with each video submission to GSA. Include the same label information as provided on the corresponding video.

C. Web-Based Photographic Documentation: N/A

1.3 USAGE RIGHTS

Comply with General Services Administration Acquisition Manual (GSAM) Clause 552.227-70, Government Rights (Unlimited). See the construction contract for more information.

PART 2 PRODUCTS

2.1 PHOTOGRAPHIC MEDIA

A. Digital Images: JPEG format with minimum sensor size of 35 resolution minimum 1080 by 720 megapixels or greater.

B. Video Format: Standard definition DVDs or CDs.

1. Identification: Each copy shall have an applied label containing the same identification information stated under Digital Photographs

PART 2 EXECUTION

2.1 COOPERATION WITH PHOTOGRAPHER

A. N/A

2.2 CONSTRUCTION PHOTOGRAPHS

A. Preconstruction Photographs: Before construction is started, photographers shall take photographs of the site and surrounding properties from different points of view selected by GSA. The contractor may choose to provide additional photographs.

1. Take not less than 10 photographs to show the context of the work area for exterior as required by the scope of services, of existing buildings and conditions adjacent to the project work area in sufficient detail to record the physical conditions at the start of construction.

2. Frequency: Take photographs weekly coinciding with the cutoff date associated with each application for payment.

3. Number: Take not less than 5 (Five) photographs each time, to best show the status of construction and progress since taking previous photographs.

B. Special Photographs: In addition to periodic photographs, Contractor shall take special photographs of subject matter for purposes of acceptance & turnover of each section of payment.

1. Frequency: Take special photographs at least 6 times during construction. Take at least 8 photographs each time, for a cumulative total of not less than 48 special photographs.

2. At the completion of an area, when requested by GSA and working with GSA representatives, provide 10 Ten exterior photographs as directed.

2.3 CONSTRUCTION VIDEOS

A. Video: Show area of construction and activities during concrete or asphalt placement. Continuous running time shall be displayed at all times. At the start of each video, weather conditions shall be recorded, including temperature reading at the project site.

B. Preconstruction Video: Before construction is started, photographers shall record video of the site and surrounding properties from different points of view selected by GSA.

C. Construction Period Videos: At intervals during construction, photographers shall record video of the project's progress from different points of view. Vantage points shall be selected by the photographer unless otherwise directed by GSA.

1. Frequency: Record videos monthly coinciding with the cutoff date associated with each application for payment.

2. Frequency: Record videos weekly, with timing each month adjusted to coincide with the cutoff date associated with each application for payment.

Recording Time: Minimum recording time for each video session shall be as necessary to show critical work in progress at significant stages such as concrete or asphalt placements.

END OF SECTION