GSA 01 32 00 Construction Progress Documentation.docx

DOCX document 3 MB Posted

Attached to
Design Build Construction Services for the Santa Teresa Land Port of Entry (LPOE) Border Roadway Improvement & Construction (BRIC)/Paving Project, Santa Teresa, NM
Solicitation number
47PH0825R0007
Issued by
Not on record

About this file

This document is a Construction Progress Documentation section (Section 013200) for the Santa Teresa Land Port of Entry Border Roadway Improvement & Construction (BRIC) Project in Santa Teresa, New Mexico. The file outlines detailed requirements for documenting construction progress, including mandates for electronic submission of various reports into the Kahua PMIS system. Contractors must submit multiple schedules and reports within specific timeframes after the Notice to Proceed, such as a schedule of inspections and tests (within 10 calendar days) and a schedule of submittals (within 14 calendar days).

The documentation requirements include daily construction reports capturing site activities, personnel counts, weather conditions, accidents, meetings, delays, and work summaries; material location reports to be submitted weekly; field correction reports for deviations from contract documents; and unusual event reports for significant site occurrences. All reports must be electronically uploaded to the PMIS system and submitted to the Contracting Officer or Contracting Officer's Representative within specified timeframes (ranging from 3 to 7 calendar days depending on the report type). The document is part of a small business set-aside project involving pavement repair and replacement at the Santa Teresa Land Port of Entry.

View the file

Other files

File Type Posted
Amendment 3 - 47PH0825R0007 2026 01 29.pdf PDF
Pricing Sheet 2026 01 16.xlsx XLSX spreadsheet
Amendment 2 - 47PH0825R0007 2026 01 16.pdf PDF
Amendment 1 - 47PH0825R0007 2026 01 09.pdf PDF
SOLICITATION 47PH0825R0007 2025 12 12.pdf PDF
GSA 01 33 00 Submittal Procedures.docx DOCX document
GSA 01 60 00 PRODUCT REQUIREMENTS.docx DOCX document
GSA 01 32 20 Photographic Documentation.docx DOCX document
GSA 01 31 10 Prospectus CPM Schedule Specs.docx DOCX document
CBS Submittal Matrix.pdf PDF
P-120 PBS Cost and Schedule Management.pdf PDF
C. GSA 527-21 - Contractor's Qualifications and Financial Information.pdf PDF
D. Standard Form 24 Bid Bond.pdf PDF
E. SF1442 47PH0825R0007 2025 12 12.pdf PDF
B. 2. NM20250035 Highway 2025 06 06.pdf PDF
A. Past Performance Questionnaire Factor 1.pdf PDF
GSA 01 31 00 PROJECT MANAGEMENT COORDINATION.docx DOCX document
GSA 01 40 00 QUALITY ASSURANCE QUALITY CONTROL REQUIREMENTS.docx DOCX document
GSA 01 24 00 Options.docx DOCX document
GSA 01 77 00 CLOSEOUT PROCEDURES.docx DOCX document
GSA 01 73 20 SELECTIVE DEMOLITION.docx DOCX document
GSA 01 27 00 Unit Prices.docx DOCX document
GSA 01 10 00 SUMMARY.docx DOCX document
GSA 01 59 30 SECURITY REGULATIONS.docx DOCX document
PBS_Core_Building_Standards_Memorandum 24FEB25.pdf PDF
SOW 47PH0825R0007 2025 12 12.pdf PDF
B. 1. NM20250039 Heavy 2025 01 24.pdf PDF
GSA 01 73 10 CUTTING PATCHING.docx DOCX document
GSA 01 59 50 - SAFETY AND HEALTH.docx DOCX document
GSA 01 29 00 PAYMENT PROCEDURES.docx DOCX document
GSA 01 25 00 Subst. Procedures.docx DOCX document
GSA 01 50 00 TEMPORARY FACILITIES and CONTROLS.docx DOCX document
DB Communications Plan Template FY25.docx DOCX document
AGREEMENT 47PH0825R0007 2025 12 12.pdf PDF
F. Pricing Sheet Santa Teresa LPOE 08_14_2025.xlsx XLSX spreadsheet
GSA 01 74 19 CONSTRUCTION NONHAZARDOUSE WASTE REMOVAL.docx DOCX document
GSA 01 30 00 PROJECT MANAGEMENT INFORMATION SYSTEM.docx DOCX document
GSA 01 70 00 EXECUTION REQUIREMENTS.docx DOCX document
GSA 01 78 10 PROJECT RECORD DOCUMENTS.docx DOCX document
GSA 01 14 00 Work Restrictions.docx DOCX document
GSA 01 42 00 GENERAL REFERENCES.docx DOCX document
Santa Teresa LPOE - Geotechnical Report.pdf PDF
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Santa Teresa Land Port of Entry BRIC Santa Teresa, New Mexico Kahua #353

SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION

PART 1 GENERAL

1.1 SUMMARY

A. This section includes certain schedules and reports required for documenting the progress of construction during performance of the Work.

B. Coordinate the timing for preparation and processing of schedules and reports with the performance of other construction activities and maintain a consistent and logical correlation between updated schedules and reports.

C. All construction progress documentation should be created and transmitted electronically into the PMIS system.

1.2 SCHEDULE OF INSPECTIONS AND TESTS

A. Prepare and submit a schedule of inspections, tests and similar services required by the Contract Documents within 10 calendar days after issuance of the Notice to Proceed.

B. Contractor shall coordinate the schedule of inspections and tests with the Construction Schedule and other related documents. Prepare the schedule in tabular form, including but not limited to the following information:

1. Specification section number.

2. Description.

3. Identification of applicable standards.

4. Identification of methods to be used.

5. Number of inspections, tests or similar services.

6. Time schedule or time span.

7. Responsible entity.

8. Requirements for taking samples.

9. Unique characteristics.

C. Distribution: Submit in (Kahua) PMIS electronic copies of the schedule of inspection and tests to the Contracting Officer, entities designated by the Contracting Officer, and each party involved in performance of portions of the Work where inspections, tests and similar services are required.

1.3 SCHEDULE OF SUBMITTALS

A. Prepare and submit a schedule of submittal required by the Contract Documents within 14 calendar days after issuance of the Notice to Proceed.

B. Contractor shall create in (Kahua) PMIS the schedule of submittals and other related documents. Prepare the schedule in tabular form.

1.4 REPORTS

A. Daily Construction Reports: Prepare electronic daily construction reports recording the following information concerning but not limited to events at the site. All daily reports are to be uploaded to PMIS Include:

1. List of subcontractors at the site.

2. List of separate contractors at the site.

3. Count of personnel at the site.

4. High and low temperatures, general weather conditions.

5. Accidents.

6. Meetings and significant decisions.

7. Unusual events (see D. Unusual Event Reports below).

8. Stoppages, delays, shortages, and losses.

9. Emergency procedures.

10. Orders and requests of governing authorities.

11. Change Orders received or implemented.

12. Services connected or disconnected.

13. Partial completions or occupancies.

14. Summary of all work performed.

B. Material Location Reports: At not more than weekly intervals, prepare a comprehensive list of materials delivered to and stored at the site. The list shall be cumulative, showing materials previously reported plus items recently delivered. Include a statement of progress on and delivery dates for materials or items or equipment fabricated or stored away from the site. Within 7 Calendar days submit copies of the list to the Contracting Officer (CO) or Contracting Officer's Representative (COR).

C. Field Correction Reports: When the need to take corrective action requires a departure from the Contract Documents, prepare a detailed report. Include a statement describing the problem and recommended changes. Indicate reasons the Contract Documents cannot be followed. Within 3] Calendar days submit a copy to the Contracting Officer or Contracting Officer's representative for approval.

D. Unusual Event Reports: When an event of an unusual and significant nature occurs at the site, prepare a detailed report. List the chain of events, persons participating, response by the Contractor's personnel, evaluation of the results or effects, and similar pertinent information. Within 3 Calendar days submit a copy to the Contracting Officer or Contracting Officer's representative immediately. Advise the Contracting Officer or Contracting Officer's representative in advance when such events are known or predictable.

PART 2 PRODUCTS (Not applicable) PART 3 EXECUTION (Not applicable)

END OF SECTION 013200