TO2 PWS Attch 2 Central South - Base Specific Req Kelly Dft 20 SEP 19 v3.0.docx
DOCX document 54 KB Posted
- Attached to
- Base Realignment and Closure (BRAC) Environmental Construction and Optimization Services (BECOS)
- Solicitation number
- FA8903
View the file
Other files
Show 40 more
Latest 50 of 93 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA4890-06-R-9999
Attachment 1
APRIL XX, 2009
- final –
BECOS TO 2
ATTACHMENT 2
20 September 2019
1.1 Scope
The former Kelly AFB is not listed on the National Priorities List (NPL). Environmental restoration is executed through the Texas Commission on Environmental Quality (TCEQ) issued Resource Conservation and Recovery Act (RCRA) post-closure care permit and compliance plan, consequently there is no Federal Facility Agreement or Records of Decision. Property transfer at the former Kelly AFB was completed in 2010.
There are 27 total sites included in this PBR TO, of which 26 sites are being addressed following the RCRA process. One active compliance site (Building 98 Underground Storage Tanks [USTs]) is included and is following the TCEQ’s Leaking Petroleum Storage Tank (LPST) program requirements. Basewide operation and maintenance of remedial systems and Long Term Monitoring (LTM) requirements are specified in the latest approved RCRA Permit and Compliance Plan. This document outlines the requirements for former Kelly AFB. All sites included in this contract require Land Use Control /Institutional Control (LUC/IC) monitoring and Five-Year Reviews only. All sites listed in in the site list, which are following the RCRA process, must be addressed in the annual RCRA permit and compliance plan reports and Five-Year Reviews.
Seven sites have ongoing groundwater pump and treat operations (SS003, ST006, WP021, WP022, SS036, SS037, and ST038) and one of these sites (WP021) also has a groundwater collection trench. The Zone 2 Groundwater Treatment Plant (GWTP) is the only active GWTP. The Zone 4 and Zone 5 GWTPs will be decommissioned by the current contractor. Operations and maintenance (O&M) of the Zone 2 GWTP, including but not limited to PFAS monitoring and GAC changeouts, will be required under this PBR contract. There is currently no TCEQ NPDES discharge standard for PFAS, however Air Force Policy requires removal of PFAS prior to discharge. Six sites contain permeable reactive barriers (PRBs), low permeability barriers, and/or slurry walls. All remediation systems, either the current remediation systems or new remediation systems installed under this contract, will require operation and maintenance and system decommissioning once site closure has been achieved. Sampling results are documented in the Annual Compliance Plan Report and submitted to TCEQ in January of each year.
There is one compliance site under active remediation at the former Kelly AFB (Building 98 USTs Nature and extent of contamination has been defined for Building 98 USTs by the current contractor. Remediation of the site is included in this PBR.
Completion of Five-Year Reviews will be required in 2025 as part of the PBR. Additionally, the PBR Contractor shall implement all Five-Year Review recommendations included in the 2020 Kelly AFB Five-Year Review being prepared by another Contractor (the PBR contractor will have an opportunity to review the 2020 document prior to submittal to the regulators).
In addition to the requirements presented in this PWS, this scope includes the following:
· Properly plug and abandon all former Kelly AFB shallow groundwater wells no longer regulatory required in Zones 2, 3, 4 and 5 and outside the former Kelly AFB’s base boundary and not needed for future PFC investigations.
Contractors are not responsible for the following:
· PFAS investigations and mitigation. However PFAS treatment in the Zone 2 Groundwater Treatment Facility is required as identified in Section 1.0.
1.3 Applicable Documents
Key Documents
| Entry No. |
| Document Title |
| Location |
| Date Issued |
| 1 |
| Class 2 Permit and Compliance Plan Modification – Hazardous Waste Permit and Compliance Plan No. 50310, Industrial Solid Waste Registration No. 31750, Former Kelly Air Force Base, San Antonio, Texas |
| Not on AR |
| October 15, 2015 |
| 2 |
| Hazardous Waste Permit and Compliance Plan No. 50310, Industrial Solid Waste Registration No. 31750, Former Kelly Air Force Base, San Antonio, Texas. Permit and Compliance Plan renewal will likely occur prior to award of this PBR. |
| AR3926 |
| April 13, 2009 |
1.4 Work Ramp-Up and Transition
Transition of Work
| Contract No. |
| Project Name |
| Field Support |
Complete Reporting Complete
| Worldwide Environmental Restoration and Construction 2009 (WERC-09) Contract FA8903-09-D-8580, Task Order No. 11 |
| Performance Based Remediation Services at the Former Kelly Air Force Base and Joint Base San Antonio – Lackland (JBSA-LAK) |
| 6/30/2020 |
| 9/25/2020 |
1.5 Remedial System Components
· See Attachment 1 regarding remedial system components.
2.6.1 Meeting/Teleconference Support
· Former Kelly BCT meetings are held on a semi-annually basis. BCT meetings are typically held in San Antonio at an off-site location, typically at a hotel located in proximity to the former Kelly AFB.
2.6.2 Public Meetings and Hearings
· The Contractor is responsible for all community involvement requirements to meet RCRA and other regulatory requirements including public meetings and public notices in English and Spanish.
· The former Kelly AFB restoration advisory board (RAB) has been adjourned, however, the Air Force may elect to conduct Ad-Hoc meetings to inform the San Antonio community of the environmental cleanup progress.
2.6.5 Site Access: Permits, Easements, and Work Site Access
· The Contractor may be required to prepare and to obtain regulatory approval for modifications to existing Kelly AFB RCRA Permit based upon the Contractor’s proposed technical approach for achieving the objectives of this TO.
· The Contractor shall be responsible for creating and updating semiannually a web based GIS system of all current shallow groundwater wells and adding any new wells as they are installed during this TO.
2.9 Contractor Documentation
· No base-specific requirements.
3.4 Computer Aided Design Drawing (CADD) and Geographic Information Systems (GIS) Updates
· No base-specific requirements.
6.14 Land Use Controls (LUC)
· LUC inspections are required annually for all IRP and Compliance Sites which have not achieved UU/UE. Updates to the LUC Implementation Plan (LUC/IC) will be completed by the contractor as required by Air Force LUC/IC guidance.
6.15 Five-Year Reviews
· The fourth Five-Year Review will be completed under the current PBR and is due August 2021. The fifth Five-Year Review due August 2026 is included in this PBR.