Midwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Chanute Dft 24 SEP 19 v3.0.docx

DOCX document 53 KB Posted

Attached to
Base Realignment and Closure (BRAC) Environmental Construction and Optimization Services (BECOS)
Solicitation number
FA8903
Issued by

View the file

Other files

File Type Posted
Northeast Region BECOS IDIQ PWS_Draft_18 SEP 19 v4.0.docx DOCX document
Northeast Region BECOS TO 2 PWS Attch 2 - Base Specific Req Dft Griffiss 24 SEP 19 v2.0.docx DOCX document
Southwest Region BECOS TO 1 PWS_Draft_17 OCT 19 v3.0.docx DOCX document
Northeast Region BECOS IDIQ_PWS Attachment 1 - Base Site_List_Draft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
Northeast Region BECOS IDIQ PWS Attachment 2 - Acronyms and Definitions_Draft_18 Sept 19 v1.0.docx DOCX document
Southwest Region BECOS IDIQ PWS Attachment 4 - Performance Objectives Defined_Draft_18 Sept 19 v1.0.docx DOCX document
Southwest Region BECOS TO 2 PWS Attachment 1 - Site List Dft 25 SEP 19 v1.0.xlsx XLSX spreadsheet
Southwest Region BECOS IDIQ_PWS Attachment 1 - Base Site_List_Draft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
NorCal Region BECOS TO 2 PWS Attch 2 - Base Specific Req Castle Dft 19 SEP 19 v3.0.docx DOCX document
Southwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req March Dft 20 SEP 19 v3.0.docx DOCX document
Northeast Region BECOS TO 2 PWS_Draft_25 SEP 19 v3.0.docx DOCX document
NorCal Region BECOS TO 2 PWS Attachment 1 - Site List Dft 25 SEP 19 v1.0.xlsx XLSX spreadsheet
NorCal Region BECOS TO 1 PWS_Draft_17 OCT 19 v3.0.docx DOCX document
Southwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Williams Dft 20 SEP 19 v3.0.docx DOCX document
Northeast Region BECOS TO 2 PWS Attachment 1 - Site List Dft 25 SEP 19 v2.0.xlsx XLSX spreadsheet
Southwest Region BECOS IDIQ PWS Attachment 2 - Acronyms and Definitions_Draft_18 Sept 19 v1.0.docx DOCX document
Southwest Region BECOS IDIQ PWS_Draft_18 SEP 19 v4.0.docx DOCX document
Northeast Region BECOS TO 2 PWS Attch 2 - Base Specific Req Dft Loring 24 SEP 19 v2.0.docx DOCX document
Northeast Region BECOS TO 2 PWS Attch 2 - Base Specific Req Dft Pease 24 SEP 19 v2.0.docx DOCX document
Southwest Region BECOS IDIQ PWS Attachment 3 - Deliverable Review Process_Draft_18 Sept 19 v1.0.docx DOCX document
Southwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Norton Dft 20 SEP 19 v3.0.docx DOCX document
NorCal Region BECOS TO 2 PWS Attch 2 - Base Specific Req Mather Dft 19 SEP 19 v3.0.docx DOCX document
Northeast Region BECOS TO 2 PWS Attch 2 - Base Specific Req Dft Plattsburgh 24 SEP 19 v2.0.docx DOCX document
Southwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req George Dft 20 SEP 19 v3.0.docx DOCX document
Northeast Region BECOS IDIQ PWS Attachment 4 - Performance Objectives Defined_Draft_18 Sept 19 v1.0.docx DOCX document
NorCal Region BECOS TO 2 PWS_Draft_25 SEP 19 v3.0.docx DOCX document
NORCAL Region BECOS IDIQ PWS_Draft_18 SEP 19 v4.0.docx DOCX document
Midwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Gentile Dft 24 SEP 19 v3.0.docx DOCX document
Midwest Region BECOS TO 2 PWS Attachment 1 Dft Site List 25 SEP 19 v2.0.xlsx XLSX spreadsheet
DRAFT 10242019_Southwest IDIQ_TO1_TO2 CLIN Structure and Price Model.xlsx XLSX spreadsheet
IDIQ PWS Central South Dft 18 SEP 19 v4.0.docx DOCX document
TO2 PWS Attch 1 Central South - Site List Dft 25 SEP 19 v1.0.xlsx XLSX spreadsheet
Galena - Alaska Region BECOS IDIQ PWS Attachment 2 - Acronyms and Definitions_Draft_18 Sept 19 v1.0.docx DOCX document
TO2 PWS Attch 2 Central South - Base Specific Req Kelly Dft 20 SEP 19 v3.0.docx DOCX document
Galena - Alaska Region BECOS IDIQ PWS Attachment 4 - Performance Objectives Defined_Draft_18 Sept 19 v1.0.docx DOCX document
Galena AK Region BECOS TO 1 PWS_Draft_17 OCT 19 v3.0.docx DOCX document
TO1 PWS Central South Dft 17 OCT 19 v3.0.docx DOCX document
20191114_Section_M_Draft RFP.docx DOCX document
Midwest Region BECOS IDIQ_PWS Attachment 1 - Base Site_List_Draft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
TO2 PWS Attch 2 Central South - Base Specific Req Bergstrom Dft 20 SEP 19 v3.0.docx DOCX document
Midwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req KI Sawyer Dft 24 SEP 19 v3.0.docx DOCX document
IDIQ PWS Attch 1 Central South - Base Site List Dft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
Midwest Region BECOS TO 1 PWS_Draft_17 OCT 19 v3.0.docx DOCX document
NorCal Region BECOS IDIQ_PWS Attachment 1 - Base Site_List_Draft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
Draft RFP BECOS Questions and Answers Template.xlsx XLSX spreadsheet
Galena Alaska Region BECOS IDIQ_PWS Attachment 1 - Base Site_List_Draft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
DRAFT 10242019_Galena IDIQ_TO1_TO2 CLIN Structure and Price Model_v2.xlsx XLSX spreadsheet
Midwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Wurtsmith Dft 24 SEP 19 v3.0.docx DOCX document
TO2 PWS Attch 2 Central South - Base Specific Req England Dft 20 SEP 19 v3.0.docx DOCX document
TO2 PWS Attch 2 Central South - Base Specific Req Brooks Dft 20 SEP 19 v3.0.docx DOCX document
Show 40 more

Latest 50 of 93 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4890-06-R-9999

Attachment 1

APRIL XX, 2009

- final –

BECOS TO 2

ATTACHMENT 2

24 September 2019

1.1 Scope

The former Chanute Air Force Base (AFB) (Comprehensive Environmental Response, Compensation, and Liability Information System identification IL1570024157), located in Champaign County, Village of Rantoul, Illinois, was closed in 1993. For the purposes of environmental investigation and remediation, the former Chanute AFB was divided into two operable units (OUs): OU-1 and OU-2. On 1 December 2000, the 428-acre portion of the former Chanute AFB constituting OU-2 was proposed for addition to the National Priorities List (NPL) (Volume 65 Federal Register No. 232, 2000). The USEPA NPL Site Narrative focused on the Fire Training Areas and Landfills in OU-2, particularly Sites LF016 and LF017. Migration of contaminants from OU-2 into Salt Fork Creek (SFC) was the primary concern and the reason behind the proposed NPL listing. A No Further Action Record of Decision (ROD) for SFC was signed in 2013 (Administrative Record [AR] 3745, Shaw Environmental, Inc. [Shaw], 2013). No OU-1 sites are included in the USEPA-proposed NPL listing. To date, the OU-2 portion of the former Chanute AFB has not been added to the NPL, but remains in the proposed NPL site status. RODs have been signed for all Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) sites and Remedy in Place (RIP) has been achieved for all sites included in this TO.

There are six sites included in this PBR TO that are being addressed following the CERCLA process. Four CERCLA sites are capped landfills (LF016, LF017, LF018, and LF019) with ongoing post-closure activities that include the performance of routine, preventive, predictive, scheduled, and unscheduled inspections aimed at preventing equipment or systems failure or decline. Land use controls (LUCs) have also been implemented at the landfills as well as for lead-contaminated soil (concentrations above 400 milligrams per kilogram) outside the landfill cap at Site LF016. The fifth site is a former fire training area (FT021) with ongoing groundwater treatment and LUCs. The FT021 remedy includes restrictions on future use. The sixth site is the location of a trichloroethene spill (SS041), also with ongoing groundwater remediation and interim LUCs until cleanup goals are achieved.

In 2016, the Air Force installed a leachate treatment system (LTS) to remove perfluorooctanoic acid (PFOA) and perfluorooctane sulfonate (PFOS) from Site LF017 (Landfill 2) leachate prior to discharge to the Village of Rantoul Publicly Owned Treatment Works (POTW) in accordance with Water Pollution Control Permit Number 2016-EB-61048. The LTS became operational on 11 July 2016 and includes a granular-activated carbon (GAC) adsorption unit (a three-bed GAC system) for the primary removal of PFOS and PFOA.

In addition to the requirements presented in this PWS, this scope includes the following:

· Evaluation and implementation, if feasible, of discharging LTS effluent to Salt Fork Creek.

· Modifying LTS permit to allow treatment of RDW/IDW from other sites where feasible, particularly sites contaminated with PFOS/PFOA.

Contractors are not responsible for the following:

· No base-specific exclusions.

1.3 Applicable Documents

Key Documents

Entry No.
Document Title
Location
Date Issued
1
Final Record of Decision Operable Unit (OU) 1 and OU-2: Landfill 1 (LF016); and OU-2: Landfill 2 (LF017), Landfill 3 (LF018), and Landfill 4 (LF019), Former Chanute Air Force Base Rantoul, Illinois
AR 421585
July 2014
2
Final Group 8 – Record of Decision for Operable Unit 2: Fire Training Area 2 (FT021) and Area 130 TCE Disposal Pit (WP080), Former Chanute Air Force Base, Rantoul, Illinois
AR 3710
May 2012

1.4 Work Ramp-Up and Transition

Transition of Work

Contract No.
Project Name
Field Support

Complete Reporting Complete

Contract FA4890-06-D-0010, Task Order 0002
Chanute PBR (SS041 and FT021 Groundwater Remedy)
12/30/2020
12/30/2020
Contract GS10F0280V, Order Number FA8903-16-F-0014
PBR, Central Region BRAC Installations (Landfills and FT021 LTM)
4/27/2021
6/27/2021

1.5 Remedial System Components

· See Attachment 1 regarding remedial system components.

2.6.1 Meeting/Teleconference Support

· Chanute BCT meetings are generally held monthly via PBR contractor-hosted teleconference calls. In addition, onsite BCT meetings are held on an as-needed basis approximately 2 times per year and are typically scheduled to occur the same week as other Air Force meetings (e.g., RAB meetings, public meetings, stakeholder meetings). Onsite meetings are typically held at the former base in the main conference room of the Rantoul Business Center.

2.6.2 Public Meetings and Hearings

· The Chanute RAB has been adjourned; however, public meetings are held on a semiannual basis; typically the third Thursday of May and November at 12 noon. RAB meetings are in held at the former base in the main conference room of the Rantoul Business Center. The PBR contractor is required to facilitate and mail read-ahead materials for RAB members. A court reporter is also required for all RAB meetings.

· The Chanute RAB has adjourned; however, the Air Force may elect to conduct Ad-Hoc meetings to inform the Rantoul community of the environmental cleanup progress. The PBR contractor will be required to facilitate the meeting location and logistics, prepare a poster for the Rantoul library, issue a newspaper notice, and prepare meeting materials (agenda, presentation, handouts, etc.).

2.6.5 Site Access: Permits, Easements, and Work Site Access

· Discharge from the landfill leachate treatment system is subject to provisions of the Illinois State Construction/Operating Permit Program. The existing operating permit (2016-EB-61048), issued July 14, 2016, expires June 30, 2021. Renewals will be required in this PBR.

2.9 Contractor Documentation

· No additional base-specific requirements.

3.4 Computer Aided Design Drawing (CADD) and Geographic Information Systems (GIS) Updates

· No additional base-specific requirements.

6.14 Land Use Controls (LUC)

· Annual LUC inspections are required.

6.15 Five-Year Reviews

· The third Five-Year Review will be completed under the current PBR and is due April 2020. The fourth Five-Year Review due April 2025 is included in this PBR.