TO2 PWS Attch 2 Central South - Base Specific Req Bergstrom Dft 20 SEP 19 v3.0.docx

DOCX document 53 KB Posted

Attached to
Base Realignment and Closure (BRAC) Environmental Construction and Optimization Services (BECOS)
Solicitation number
FA8903
Issued by

View the file

Other files

File Type Posted
Northeast Region BECOS IDIQ PWS_Draft_18 SEP 19 v4.0.docx DOCX document
Northeast Region BECOS TO 2 PWS Attch 2 - Base Specific Req Dft Griffiss 24 SEP 19 v2.0.docx DOCX document
Southwest Region BECOS TO 1 PWS_Draft_17 OCT 19 v3.0.docx DOCX document
Northeast Region BECOS IDIQ_PWS Attachment 1 - Base Site_List_Draft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
Northeast Region BECOS IDIQ PWS Attachment 2 - Acronyms and Definitions_Draft_18 Sept 19 v1.0.docx DOCX document
Southwest Region BECOS IDIQ PWS Attachment 4 - Performance Objectives Defined_Draft_18 Sept 19 v1.0.docx DOCX document
Southwest Region BECOS TO 2 PWS Attachment 1 - Site List Dft 25 SEP 19 v1.0.xlsx XLSX spreadsheet
Southwest Region BECOS IDIQ_PWS Attachment 1 - Base Site_List_Draft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
NorCal Region BECOS TO 2 PWS Attch 2 - Base Specific Req Castle Dft 19 SEP 19 v3.0.docx DOCX document
Southwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req March Dft 20 SEP 19 v3.0.docx DOCX document
Northeast Region BECOS TO 2 PWS_Draft_25 SEP 19 v3.0.docx DOCX document
NorCal Region BECOS TO 2 PWS Attachment 1 - Site List Dft 25 SEP 19 v1.0.xlsx XLSX spreadsheet
NorCal Region BECOS TO 1 PWS_Draft_17 OCT 19 v3.0.docx DOCX document
Southwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Williams Dft 20 SEP 19 v3.0.docx DOCX document
Northeast Region BECOS TO 2 PWS Attachment 1 - Site List Dft 25 SEP 19 v2.0.xlsx XLSX spreadsheet
Southwest Region BECOS IDIQ PWS Attachment 2 - Acronyms and Definitions_Draft_18 Sept 19 v1.0.docx DOCX document
Southwest Region BECOS IDIQ PWS_Draft_18 SEP 19 v4.0.docx DOCX document
Northeast Region BECOS TO 2 PWS Attch 2 - Base Specific Req Dft Loring 24 SEP 19 v2.0.docx DOCX document
Northeast Region BECOS TO 2 PWS Attch 2 - Base Specific Req Dft Pease 24 SEP 19 v2.0.docx DOCX document
Southwest Region BECOS IDIQ PWS Attachment 3 - Deliverable Review Process_Draft_18 Sept 19 v1.0.docx DOCX document
Southwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Norton Dft 20 SEP 19 v3.0.docx DOCX document
NorCal Region BECOS TO 2 PWS Attch 2 - Base Specific Req Mather Dft 19 SEP 19 v3.0.docx DOCX document
Northeast Region BECOS TO 2 PWS Attch 2 - Base Specific Req Dft Plattsburgh 24 SEP 19 v2.0.docx DOCX document
Southwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req George Dft 20 SEP 19 v3.0.docx DOCX document
Northeast Region BECOS IDIQ PWS Attachment 4 - Performance Objectives Defined_Draft_18 Sept 19 v1.0.docx DOCX document
NorCal Region BECOS TO 2 PWS_Draft_25 SEP 19 v3.0.docx DOCX document
NORCAL Region BECOS IDIQ PWS_Draft_18 SEP 19 v4.0.docx DOCX document
Midwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Gentile Dft 24 SEP 19 v3.0.docx DOCX document
Midwest Region BECOS TO 2 PWS Attachment 1 Dft Site List 25 SEP 19 v2.0.xlsx XLSX spreadsheet
DRAFT 10242019_Southwest IDIQ_TO1_TO2 CLIN Structure and Price Model.xlsx XLSX spreadsheet
IDIQ PWS Central South Dft 18 SEP 19 v4.0.docx DOCX document
TO2 PWS Attch 1 Central South - Site List Dft 25 SEP 19 v1.0.xlsx XLSX spreadsheet
Galena - Alaska Region BECOS IDIQ PWS Attachment 2 - Acronyms and Definitions_Draft_18 Sept 19 v1.0.docx DOCX document
TO2 PWS Attch 2 Central South - Base Specific Req Kelly Dft 20 SEP 19 v3.0.docx DOCX document
Galena - Alaska Region BECOS IDIQ PWS Attachment 4 - Performance Objectives Defined_Draft_18 Sept 19 v1.0.docx DOCX document
Galena AK Region BECOS TO 1 PWS_Draft_17 OCT 19 v3.0.docx DOCX document
TO1 PWS Central South Dft 17 OCT 19 v3.0.docx DOCX document
20191114_Section_M_Draft RFP.docx DOCX document
Midwest Region BECOS IDIQ_PWS Attachment 1 - Base Site_List_Draft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
Midwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req KI Sawyer Dft 24 SEP 19 v3.0.docx DOCX document
IDIQ PWS Attch 1 Central South - Base Site List Dft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
Midwest Region BECOS TO 1 PWS_Draft_17 OCT 19 v3.0.docx DOCX document
NorCal Region BECOS IDIQ_PWS Attachment 1 - Base Site_List_Draft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
Draft RFP BECOS Questions and Answers Template.xlsx XLSX spreadsheet
Galena Alaska Region BECOS IDIQ_PWS Attachment 1 - Base Site_List_Draft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
Midwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Chanute Dft 24 SEP 19 v3.0.docx DOCX document
DRAFT 10242019_Galena IDIQ_TO1_TO2 CLIN Structure and Price Model_v2.xlsx XLSX spreadsheet
Midwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Wurtsmith Dft 24 SEP 19 v3.0.docx DOCX document
TO2 PWS Attch 2 Central South - Base Specific Req England Dft 20 SEP 19 v3.0.docx DOCX document
TO2 PWS Attch 2 Central South - Base Specific Req Brooks Dft 20 SEP 19 v3.0.docx DOCX document
Show 40 more

Latest 50 of 93 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4890-06-R-9999

Attachment 1

APRIL XX, 2009

- final –

BECOS TO 2

ATTACHMENT 2

20 September 2019

1.1 Scope

The former Bergstrom Air Force Base (AFB) is located in Austin, Texas. Bergstrom AFB was closed on 30 September 1993. Whole-base transfer completed in August 2005. The City of Austin now operates Bergstrom International Airport on 2,864 aces that reverted to the city.

At the former Bergstrom AFB, the 17 sites are being addressed following the Resource Conservation & Recovery Act (RCRA) process or Military Munitions Response Program (MMRP). Decision Documents have been completed for all RCRA sites and remedies are in place. Five sites require landfill long-term maintenance (LTM) (Sites LF003, LF004, LF005, LF006, and LF007). One RCRA site is not anticipated to achieve closure in FY20 (Site SS031). Three MMRP sites are anticipated to achieve closure in FY20 (Sites XU403, XU407, and GR408). If closure is not achieved, these sites will be included in this PBR contract. All 17 Sites require Land Use Control/Institutional Control (LUC/IC) monitoring/reporting and Five-Year Reviews.

In addition to the requirements presented in this PWS, this scope includes the following:

· No additional requirements.

Contractors are not responsible for the following:

· No additional base-specific exclusions.

1.3 Applicable Documents

Key Documents

Entry No.
Document Title
Location
Date Issued
1.
Technical Report, Final Closure of North Landfills 1 and 2
AR#491
August 1999
2.
Final Decision Document, LF-1
AR#519
July 1990
3.
Final Decision Document, LF-2
AR#520
July 1990
4.
Technical Report Final Closure of Combined Southeast Landfills
AR#s480-485
August 1999
5.
Draft Decision Document, Combined Southeast Landfill Area and South Fork Drainage Ditch, 1996
AR#375
August 1996
6.
Final Decision Document, SS-14
AR#524
July 1990
7.
Closure Report for Installation Restoration Program (IRP) Site SD- 17
AR#412
August 1997
8.
RCRA Facility Assessment/RCRA Facility Investigation, Site Closure Report, Solid Waste Management Unit 9, FT-23
AR#s476.1 & 476.2
December 1998
9.
Final Decision Document, Fire Department Training Area, FT-23
AR#212
April 1992
10.
RCRA Facility Assessment/RCRA Facility Investigation Draft Final Corrective Measures Study for Solid Waste Management Unit 76 Area 1 and Area 2
AR#588
July 1998

1.4 Work Ramp-Up and Transition

Transition of Work

Contract No.
Project Name
Field Support

Complete Reporting Complete

FA8903-09-D-8565-0007
Performance-Based Remediation at Former Bergstrom AFB, TX, Former Carswell AFB, TX, Former Eaker AFB, AR, Former Homestead AFB, FL, Former Richards-Gebaur AFB, MO
9/24/2020
9/24/2020
W9128F-14-D-0036
Air Force Military Munitions Response Program Site Inspections, Former Bergstrom AFB, TX, and Former Eaker AFB, AR
9/30/2020
9/30/2020

1.5 Remedial System Components

· See Attachment 1 regarding remedial system components.

2.6.1 Meeting/Teleconference Support

· The Contractor participate in Quarterly Teleconferences with the United States Air Force (USAF) representatives to discuss the progress toward accomplishing project objectives.

2.6.2 Public Meetings and Hearings

· There are no base-specific meetings or hearing requirements.

2.6.5 Site Access: Permits, Easements, and Work Site Access

· There are no base-specific permit/easement requirements.

2.9 Contractor Documentation

· No base-specific requirements.

3.4 Computer Aided Design Drawing (CADD) and Geographic Information Systems (GIS) Updates

· No base-specific requirements.

6.14 Land Use Controls (LUC)

· The Contractor shall conduct annual LUC/IC monitoring at all sites and prepare a report. The first LUC/IC monitoring event is due in 2020.

6.15 Five-Year Reviews

· The Contractor shall prepare a Five-Year Review Report for sites managed under the RCRA/MMRP Program as a policy review. The signature date for the Fourth Bergstrom Five-Year Review Report is due June 2021.