NorCal Region BECOS TO 2 PWS Attch 2 - Base Specific Req Castle Dft 19 SEP 19 v3.0.docx
DOCX document 52 KB Posted
- Attached to
- Base Realignment and Closure (BRAC) Environmental Construction and Optimization Services (BECOS)
- Solicitation number
- FA8903
View the file
Other files
Show 40 more
Latest 50 of 93 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA4890-06-R-9999
Attachment 1
APRIL XX, 2009
- final –
BECOS TO 2
ATTACHMENT 2
19 September 2019
1.1 Scope
The former Castle AFB is listed on the National Priorities List (NPL) and has a Federal Facility Agreement (FFA) in place. A Preliminary Closeout Report was prepared by the United States Environmental Protection Agency (USEPA) in 2006. Records of Decision (RODs) have been signed for all Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) sites included in this task order and Last Remedy in Place (LRIP) has been achieved for the base.
The 18 sites included in this task order are being addressed following the CERCLA process or state corrective action program (non-CERCLA). There are two CERCLA sites in remedial action-operation (RA-O) and all CERCLA sites require IC monitoring and Five Year Review. Groundwater pump and treat systems are currently operating at these two of the sites (OT029 and OT030). The Operable Unit (OU)-1 Basewide Phase 3 groundwater treatment plant is currently operating at OT029 and the OU-2 groundwater treatment plant (Main Base Plant) is currently operating at OT030. Groundwater contamination associated with former Air Force activities has migrated beyond the former base property boundaries. Seven of the CERCLA sites are associated with three capped landfills/sites with ongoing Long-term Management. One CERCLA site has ICs and requires Five-Year Review only. Eight petroleum-contaminated sites have ICs and require non-CERCLA Five Year Review only.
In addition to the requirements presented in this PWS, this scope includes the following:
· Monitoring for 1,2,3-TCP.
· Replacement of wells that are dry due to lowering groundwater table, as needed.
Contractors are not responsible for the following:
· No additional base-specific exclusions.
1.3 Applicable Documents
Key Documents
| Entry No. |
| Document Title |
| Location |
| Date Issued |
| 1 |
| FFA |
| AR 1007 |
| July 1, 1989 |
| 2 |
| Comprehensive Basewide (CB) ROD - Part 1 (Groundwater) |
| AR 1586 |
| January 31, 1997 |
| 3 |
| CB ROD - Part 2 |
| AR 2747 |
| July 31, 2006 |
| 4 |
| Source Control Operable Unit (SCOU) ROD - Part 1 |
| AR 2246 |
| September 1, 2002 |
| 5 |
| SCOU ROD - Part 2 |
| AR 2244 |
| May 1, 2003 |
| 6 |
| Revised SCOU ROD - Part 3 |
| AR 2736 |
| September 16, 2005 |
1.4 Work Ramp-Up and Transition
Transition of Work
| Contract No. |
| Project Name |
| Field Support |
Complete Reporting Complete
| FA8903-16-F-0018 |
| Castle/Mather/Norton PBR Contract |
| 9/30/2021 |
| 9/30/2021 |
1.5 Remedial System Components
· See Attachment 1 regarding remedial system components.
2.6.1 Meeting/Teleconference Support
· BRAC Cleanup Team (BCT) meetings are conducted annually at the former McClellan AFB (or comparable mutually agreed location for future meetings). Periodic technical meetings are conducted as needed in person or by teleconference.
2.6.2 Public Meetings and Hearings
· The Restoration Advisory Board has been adjourned and no other public meetings are currently scheduled. The contractor shall support public meeting requirements as necessary in association with contractor’s implementation plans
2.6.5 Site Access: Permits, Easements, and Work Site Access
· All existing off-base easements extend beyond this task order POP.
2.9 Contractor Documentation
· No base-specific requirements.
3.4 Computer Aided Design Drawing (CADD) and Geographic Information Systems (GIS) Updates
· No base-specific requirements.
6.14 Land Use Controls (LUC)
· The contractor shall conduct annual inspections and reviews to confirm compliance with all CERCLA and non-CERCLA environmental restrictions associated with the sites. Where possible, the contractor shall obtain and provide copies to the Air Force of annual reporting required by state covenants for applicable sites by respective property owners. An annual inspection report shall be provided or otherwise included in site reports by the contractor to confirm implementation of environmental restrictions.
· The contractor shall provide supporting information and technical support to the Air Force for property owner requests to remove restrictive covenants.
6.15 Five-Year Reviews
· The current PBR contractor will complete the Five-Year Review in March 2019. The next Five-Year Review is due in March 2024.