Other files

File Type Posted
Northeast Region BECOS IDIQ PWS_Draft_18 SEP 19 v4.0.docx DOCX document
Northeast Region BECOS TO 2 PWS Attch 2 - Base Specific Req Dft Griffiss 24 SEP 19 v2.0.docx DOCX document
Southwest Region BECOS TO 1 PWS_Draft_17 OCT 19 v3.0.docx DOCX document
Northeast Region BECOS IDIQ_PWS Attachment 1 - Base Site_List_Draft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
Northeast Region BECOS IDIQ PWS Attachment 2 - Acronyms and Definitions_Draft_18 Sept 19 v1.0.docx DOCX document
Southwest Region BECOS IDIQ PWS Attachment 4 - Performance Objectives Defined_Draft_18 Sept 19 v1.0.docx DOCX document
Southwest Region BECOS TO 2 PWS Attachment 1 - Site List Dft 25 SEP 19 v1.0.xlsx XLSX spreadsheet
Southwest Region BECOS IDIQ_PWS Attachment 1 - Base Site_List_Draft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
NorCal Region BECOS TO 2 PWS Attch 2 - Base Specific Req Castle Dft 19 SEP 19 v3.0.docx DOCX document
Southwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req March Dft 20 SEP 19 v3.0.docx DOCX document
Northeast Region BECOS TO 2 PWS_Draft_25 SEP 19 v3.0.docx DOCX document
NorCal Region BECOS TO 2 PWS Attachment 1 - Site List Dft 25 SEP 19 v1.0.xlsx XLSX spreadsheet
NorCal Region BECOS TO 1 PWS_Draft_17 OCT 19 v3.0.docx DOCX document
Southwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Williams Dft 20 SEP 19 v3.0.docx DOCX document
Northeast Region BECOS TO 2 PWS Attachment 1 - Site List Dft 25 SEP 19 v2.0.xlsx XLSX spreadsheet
Southwest Region BECOS IDIQ PWS Attachment 2 - Acronyms and Definitions_Draft_18 Sept 19 v1.0.docx DOCX document
Southwest Region BECOS IDIQ PWS_Draft_18 SEP 19 v4.0.docx DOCX document
Northeast Region BECOS TO 2 PWS Attch 2 - Base Specific Req Dft Loring 24 SEP 19 v2.0.docx DOCX document
Northeast Region BECOS TO 2 PWS Attch 2 - Base Specific Req Dft Pease 24 SEP 19 v2.0.docx DOCX document
Southwest Region BECOS IDIQ PWS Attachment 3 - Deliverable Review Process_Draft_18 Sept 19 v1.0.docx DOCX document
Southwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Norton Dft 20 SEP 19 v3.0.docx DOCX document
NorCal Region BECOS TO 2 PWS Attch 2 - Base Specific Req Mather Dft 19 SEP 19 v3.0.docx DOCX document
Northeast Region BECOS TO 2 PWS Attch 2 - Base Specific Req Dft Plattsburgh 24 SEP 19 v2.0.docx DOCX document
Southwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req George Dft 20 SEP 19 v3.0.docx DOCX document
Northeast Region BECOS IDIQ PWS Attachment 4 - Performance Objectives Defined_Draft_18 Sept 19 v1.0.docx DOCX document
NorCal Region BECOS TO 2 PWS_Draft_25 SEP 19 v3.0.docx DOCX document
NORCAL Region BECOS IDIQ PWS_Draft_18 SEP 19 v4.0.docx DOCX document
Midwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Gentile Dft 24 SEP 19 v3.0.docx DOCX document
Midwest Region BECOS TO 2 PWS Attachment 1 Dft Site List 25 SEP 19 v2.0.xlsx XLSX spreadsheet
DRAFT 10242019_Southwest IDIQ_TO1_TO2 CLIN Structure and Price Model.xlsx XLSX spreadsheet
IDIQ PWS Central South Dft 18 SEP 19 v4.0.docx DOCX document
TO2 PWS Attch 1 Central South - Site List Dft 25 SEP 19 v1.0.xlsx XLSX spreadsheet
Galena - Alaska Region BECOS IDIQ PWS Attachment 2 - Acronyms and Definitions_Draft_18 Sept 19 v1.0.docx DOCX document
TO2 PWS Attch 2 Central South - Base Specific Req Kelly Dft 20 SEP 19 v3.0.docx DOCX document
Galena - Alaska Region BECOS IDIQ PWS Attachment 4 - Performance Objectives Defined_Draft_18 Sept 19 v1.0.docx DOCX document
Galena AK Region BECOS TO 1 PWS_Draft_17 OCT 19 v3.0.docx DOCX document
TO1 PWS Central South Dft 17 OCT 19 v3.0.docx DOCX document
20191114_Section_M_Draft RFP.docx DOCX document
Midwest Region BECOS IDIQ_PWS Attachment 1 - Base Site_List_Draft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
TO2 PWS Attch 2 Central South - Base Specific Req Bergstrom Dft 20 SEP 19 v3.0.docx DOCX document
IDIQ PWS Attch 1 Central South - Base Site List Dft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
Midwest Region BECOS TO 1 PWS_Draft_17 OCT 19 v3.0.docx DOCX document
NorCal Region BECOS IDIQ_PWS Attachment 1 - Base Site_List_Draft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
Draft RFP BECOS Questions and Answers Template.xlsx XLSX spreadsheet
Galena Alaska Region BECOS IDIQ_PWS Attachment 1 - Base Site_List_Draft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
Midwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Chanute Dft 24 SEP 19 v3.0.docx DOCX document
DRAFT 10242019_Galena IDIQ_TO1_TO2 CLIN Structure and Price Model_v2.xlsx XLSX spreadsheet
Midwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Wurtsmith Dft 24 SEP 19 v3.0.docx DOCX document
TO2 PWS Attch 2 Central South - Base Specific Req England Dft 20 SEP 19 v3.0.docx DOCX document
TO2 PWS Attch 2 Central South - Base Specific Req Brooks Dft 20 SEP 19 v3.0.docx DOCX document
Show 40 more

Latest 50 of 93 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4890-06-R-9999

Attachment 1

APRIL XX, 2009

- final –

BECOS TO 2

ATTACHMENT 2

24 September 2019

1.1 Scope

The former K.I. Sawyer Air Force Base (AFB) (referred to as K.I. Sawyer in this and other reference documents) is located in Marquette County approximately 13 miles south of the City of Marquette and three miles east of Gwinn in the north-central region of Michigan’s Upper Peninsula. The property encompassed approximately 7.7 square miles (approximately 4,923 acres) with airfield operations facilities, industrial/disposal facilities, housing, recreational facilities, and undeveloped lands. Routine maintenance, supply, transportation, and fire training activities at the base used organic-based solvents and fuels and necessitated using, accumulating, treating, and disposing of refuse, materials, and wastes. Some activities resulted in impacts to soils and groundwater. One site is located remotely - Site OT013 - the former Defense Fuel Supply Point (DFSP), is located in Escanaba, Michigan, about 50 miles from the main base. The base was officially closed on October 1, 1995 and placed under the jurisdiction of the Air Force Real Property Agency (AFRPA) (formerly the Air Force Base Conversion Agency).

There are eight sites included in this PBR TO that are being addressed following the Michigan Part 201 process and CERCLA. This project provides for groundwater (GW) monitoring, remedial systems operations, maintenance and monitoring (OM&M) , land use control/institutional control (LUC/IC) inspections, and well decommissioning at three sites (ST004, LF008, LF010/011) at K.I. Sawyer. In addition, this project provides for conducting separate CERCLA Five-Year Reviews and annual LUC inspections for K.I. Sawyer and DFSP Escanaba Site OT013. Sites SS017 and XE027 will be included in the event they do not achieve SC under current PBR contract.

Site ST004, the former POL Yard, has a free product recovery system to prevent discharge of a jet fuel free-product plume into an adjacent creek, along with monitoring for natural attenuation of dissolved phase benzene, toluene, ethylbenzene, and xylenes (BTEX) plume. The site is currently going through additional remediation actions for treatment of the free product plume with a goal of reaching Response Complete (RC). If the additional remedial action achieves its goal, then only limited free product monitoring, system decommissioning will be required at this site, in addition to annual LUC inspections and five-year review. If not, then the scope will continue toward RC, and include continued operations, monitoring, and maintenance of the current treatment system.

Site LF008 is a capped and closed 21-acre landfill, with groundwater impacted by vinyl chloride. Site LF010/011 is a site combined of two closed landfills, with iron and manganese in groundwater above Part 201 drinking water criteria. Routine landfill cap and site maintenance, irrigation, and groundwater monitoring is the ongoing remedy at these sites.

Site XE027 is a former munitions landfill and in the process of site closure (SC). Routine landfill cap and site maintenance and irrigation is the ongoing remedy at this site and will be required if the site cannot be closed under the current PBR.

Site SS017 is the former fuel hydrant system, and the source of BTEX contamination in soil and groundwater. This site is also undergoing additional remedial actions to achieve site closure under the current PBR. Site FT007 is the former fire training area 2. This site is expected to close within current PBR, but if that is not achieved, annual LUCs and five-year reviews will be required for this site.

In addition to the IRP sites, the scope also includes maintenance of the in-home treatment systems for PFOS/PFOA contaminated water one residence with effort at any additional residences addressed as the need arises.

This project shall be conducted in accordance with the Basewide Remedial Action Plan for K.I. Sawyer (December 2004) and as updated in the Basewide No Further Action (NFA) Report of 2014.

The regulatory framework for K.I. Sawyer includes Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) and Michigan Act 451 Michigan Environmental Response Program (Act 451 Part 201 including cleanup criteria under R299.44, .46 .48, and .49) and the Michigan Safe Drinking Water Act. The Basewide Remedial Action Plan (RAP) of 2004 is the Decision Document for all IRP sites.

USEPA is no longer involved in the BCT.

In addition to the requirements presented in this PWS, this scope includes the following:

· No additional scope.

Contractors are not responsible for the following:

· No base-specific exclusions.

1.3 Applicable Documents

Key Documents

Entry No.
Document Title
Location
Date Issued
1.
Final Air Sparge/Biosparge Design Analysis and Work Plan for ST004
AR # 574124
March 2018
2.
Monthly Operations and Maintenance Report, January 2018, Site ST004 Operations and Maintenance Services, Groundwater Remediation System
AR # 574122
March 2018
3.
Technical and Management Report Landfill LF008, LF010/011, and XE027 Irrigation and Maintenance September – October 2017
AR # 573800
November 2017
4.
Monthly Operations and Maintenance Report, May 2017, Site ST004 Operations and Maintenance Services, Groundwater Remediation System
AR # 574121
August 2017
5.
Annual Operations and Maintenance Report, 2016, Site ST004, Groundwater Remediation System
AR # 573798
July 2017
6.
Final Consolidated Pre-Design Investigation Work Plan for ST004 and SS017
AR # 574126
June 2017
7.
Monthly Operations and Maintenance Report, April 2017, Site ST004 Operations and Maintenance Services, Groundwater Remediation System
AR # 574059
May 2017
8.
Final Operations, Maintenance, and Monitoring Plan, 2016 Groundwater Monitoring Program, ST004, FT007, LF008, LF010/LF011, SS017, and XE027
AR # 574120
October 2016
9.
Final First Five-Year Review, DFSP Escanaba, IRP Site OT-013
AR # 465804
November 2013
10.
Final Addendum to the Final Second Five Year Remedial Actions Review
AR # 1142
August 2012
11.
Final Second Five Year Review
AR # 421658
March 2012
12.
Technical Document to Support Decision Document and Remedial Action Plan, ST-04
AR # 997
February 2000
13.
Technical Document to Support Decision Document and Remedial Action Plan, FT-07
AR # 1038
December 1999
14.
Draft Decision Document, Bulk Fuels Storage Area, ST-04
AR # 527
April 1995
15.
Draft Decision Document, Fire Training Area 2, FT-07
AR # 526
April 1995
16.
Decision Document, Wells Terminal Annex, OT-13
AR # 235
December 1994
17.
Final Decision Document, Free Product Removal, DP-01, ST04
AR # 127
March 1990
18.
Draft Decision Document, TCE Plume and Free JP-4, DP-02, ST04
AR # 90
September 1989
19.
Draft Decision Document, Landfill 2, LF-09
AR # 79
June 1988
20.
Draft Decision Document, Landfill 3, LF-10
AR # 78
June 1988

1.4 Work Ramp-Up and Transition

Transition of Work

Contract No.
Project Name
Field Support

Complete Reporting Complete

Contract GS10F0280V, Order Number FA8903-16-F-0014
PBR, Central Region BRAC Installations
4/27/2021
6/27/2021

1.5 Remedial System Components

· See Attachment 1 regarding remedial system components.

2.6.1 Meeting/Teleconference Support

· K.I. Sawyer BCT meetings are generally held monthly via PBR contractor-hosted teleconference calls. In addition, onsite BCT meetings are held on an as-needed basis approximately 2 times per year and are typically scheduled to occur the same week as other Air Force meetings (e.g., RAB meetings, public meetings, stakeholder meetings). Onsite meetings are typically held at the former base in the Grissom Reserves offices.

2.6.2 Public Meetings and Hearings

· K.I. Sawyer RAB meetings are held annually; typically in October. The meeting is currently held at the K.I. Sawyer Heritage Museum. The PBR contractor is required to facilitate the meeting location and logistics, prepare briefing material, meeting meetings, and issue a newspaper notice.

2.6.5 Site Access: Permits, Easements, and Work Site Access

· None.

2.9 Contractor Documentation

· No additional base-specific requirements.

3.4 Computer Aided Design Drawing (CADD) and Geographic Information Systems (GIS) Updates

· No additional base-specific requirements.

6.14 Land Use Controls (LUC)

· Annual LUC inspections are required.

6.15 Five-Year Reviews

· Two separate five-year reviews are required for K.I. Sawyer and DFSP Escanaba. The Five-Year Reviews for K.I. Sawyer and Escanaba will be completed under the current PBR in 2020 and 2018 respectively. The successive five-year reviews (one each for K.I. Sawyer and Escanaba) falling within the PoP of this contract are included in this PBR.