TO2 PWS Attch 2 Central South - Base Specific Req Eaker Dft 20 SEP 19 v3.0.docx

DOCX document 52 KB Posted

Attached to
Base Realignment and Closure (BRAC) Environmental Construction and Optimization Services (BECOS)
Solicitation number
FA8903
Issued by

View the file

Other files

File Type Posted
Northeast Region BECOS IDIQ PWS_Draft_18 SEP 19 v4.0.docx DOCX document
Northeast Region BECOS TO 2 PWS Attch 2 - Base Specific Req Dft Griffiss 24 SEP 19 v2.0.docx DOCX document
Southwest Region BECOS TO 1 PWS_Draft_17 OCT 19 v3.0.docx DOCX document
Northeast Region BECOS IDIQ_PWS Attachment 1 - Base Site_List_Draft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
Northeast Region BECOS IDIQ PWS Attachment 2 - Acronyms and Definitions_Draft_18 Sept 19 v1.0.docx DOCX document
Southwest Region BECOS IDIQ PWS Attachment 4 - Performance Objectives Defined_Draft_18 Sept 19 v1.0.docx DOCX document
Southwest Region BECOS TO 2 PWS Attachment 1 - Site List Dft 25 SEP 19 v1.0.xlsx XLSX spreadsheet
Southwest Region BECOS IDIQ_PWS Attachment 1 - Base Site_List_Draft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
NorCal Region BECOS TO 2 PWS Attch 2 - Base Specific Req Castle Dft 19 SEP 19 v3.0.docx DOCX document
Southwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req March Dft 20 SEP 19 v3.0.docx DOCX document
Northeast Region BECOS TO 2 PWS_Draft_25 SEP 19 v3.0.docx DOCX document
NorCal Region BECOS TO 2 PWS Attachment 1 - Site List Dft 25 SEP 19 v1.0.xlsx XLSX spreadsheet
NorCal Region BECOS TO 1 PWS_Draft_17 OCT 19 v3.0.docx DOCX document
Southwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Williams Dft 20 SEP 19 v3.0.docx DOCX document
Northeast Region BECOS TO 2 PWS Attachment 1 - Site List Dft 25 SEP 19 v2.0.xlsx XLSX spreadsheet
Southwest Region BECOS IDIQ PWS Attachment 2 - Acronyms and Definitions_Draft_18 Sept 19 v1.0.docx DOCX document
Southwest Region BECOS IDIQ PWS_Draft_18 SEP 19 v4.0.docx DOCX document
Northeast Region BECOS TO 2 PWS Attch 2 - Base Specific Req Dft Loring 24 SEP 19 v2.0.docx DOCX document
Northeast Region BECOS TO 2 PWS Attch 2 - Base Specific Req Dft Pease 24 SEP 19 v2.0.docx DOCX document
Southwest Region BECOS IDIQ PWS Attachment 3 - Deliverable Review Process_Draft_18 Sept 19 v1.0.docx DOCX document
Southwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Norton Dft 20 SEP 19 v3.0.docx DOCX document
NorCal Region BECOS TO 2 PWS Attch 2 - Base Specific Req Mather Dft 19 SEP 19 v3.0.docx DOCX document
Northeast Region BECOS TO 2 PWS Attch 2 - Base Specific Req Dft Plattsburgh 24 SEP 19 v2.0.docx DOCX document
Southwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req George Dft 20 SEP 19 v3.0.docx DOCX document
Northeast Region BECOS IDIQ PWS Attachment 4 - Performance Objectives Defined_Draft_18 Sept 19 v1.0.docx DOCX document
NorCal Region BECOS TO 2 PWS_Draft_25 SEP 19 v3.0.docx DOCX document
NORCAL Region BECOS IDIQ PWS_Draft_18 SEP 19 v4.0.docx DOCX document
Midwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Gentile Dft 24 SEP 19 v3.0.docx DOCX document
Midwest Region BECOS TO 2 PWS Attachment 1 Dft Site List 25 SEP 19 v2.0.xlsx XLSX spreadsheet
DRAFT 10242019_Southwest IDIQ_TO1_TO2 CLIN Structure and Price Model.xlsx XLSX spreadsheet
IDIQ PWS Central South Dft 18 SEP 19 v4.0.docx DOCX document
TO2 PWS Attch 1 Central South - Site List Dft 25 SEP 19 v1.0.xlsx XLSX spreadsheet
Galena - Alaska Region BECOS IDIQ PWS Attachment 2 - Acronyms and Definitions_Draft_18 Sept 19 v1.0.docx DOCX document
TO2 PWS Attch 2 Central South - Base Specific Req Kelly Dft 20 SEP 19 v3.0.docx DOCX document
Galena - Alaska Region BECOS IDIQ PWS Attachment 4 - Performance Objectives Defined_Draft_18 Sept 19 v1.0.docx DOCX document
Galena AK Region BECOS TO 1 PWS_Draft_17 OCT 19 v3.0.docx DOCX document
TO1 PWS Central South Dft 17 OCT 19 v3.0.docx DOCX document
20191114_Section_M_Draft RFP.docx DOCX document
Midwest Region BECOS IDIQ_PWS Attachment 1 - Base Site_List_Draft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
TO2 PWS Attch 2 Central South - Base Specific Req Bergstrom Dft 20 SEP 19 v3.0.docx DOCX document
Midwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req KI Sawyer Dft 24 SEP 19 v3.0.docx DOCX document
IDIQ PWS Attch 1 Central South - Base Site List Dft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
Midwest Region BECOS TO 1 PWS_Draft_17 OCT 19 v3.0.docx DOCX document
NorCal Region BECOS IDIQ_PWS Attachment 1 - Base Site_List_Draft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
Draft RFP BECOS Questions and Answers Template.xlsx XLSX spreadsheet
Galena Alaska Region BECOS IDIQ_PWS Attachment 1 - Base Site_List_Draft 18 Sept 2019 v1.0.xlsx XLSX spreadsheet
Midwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Chanute Dft 24 SEP 19 v3.0.docx DOCX document
DRAFT 10242019_Galena IDIQ_TO1_TO2 CLIN Structure and Price Model_v2.xlsx XLSX spreadsheet
Midwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Wurtsmith Dft 24 SEP 19 v3.0.docx DOCX document
TO2 PWS Attch 2 Central South - Base Specific Req England Dft 20 SEP 19 v3.0.docx DOCX document
Show 40 more

Latest 50 of 93 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4890-06-R-9999

Attachment 1

APRIL XX, 2009

- final –

BECOS TO 2

ATTACHMENT 2

20 September 2019

1.1 Scope

The former Eaker Air Force Base (AFB) is located in Blytheville, Arkansas. Eaker AFB was closed on 15 December 1992. Whole-base transfer completed in September 2002. The Gosnell Regional Airport Authority now operates the airfield as the Arkansas International Airport.

At the former Eaker AFB, the 17 sites are being addressed following the RCRA process or Military Munitions Response Program (MMRP). Eaker AFB and the United States Environmental Protection Agency (USEPA) signed an administrative consent order indicating sites were subject to RCRA corrective action and would be addressed under a RCRA facility investigation. DDs have been completed for all RCRA sites and remedies are in place. At the former Eaker AFB, one RCRA site requires groundwater monitoring (Site SS003). Three other RCRA sites are anticipated to achieve closure in FY19 (Sites FT001, ST012, and ST005). If closure is not achieved, these sites will be included in this PBR contract. All 17 Sites require Visual Site Inspections (VSIs) and Five-Year Reviews.

In addition to the requirements presented in this PWS, this scope includes the following:

· No additional requirements.

Contractors are not responsible for the following:

· No additional base-specific exclusions.

1.3 Applicable Documents

Key Documents

Entry No.
Document Title
Location
Date Issued
1.
Final Remedial Action Decision Document (RADD) for Corrective Action
AR#331
October 1999
2.
Consent Administrative Order and Agreement, Eaker AFB, Blytheville, Arkansas
AR#Pending
August 1993

1.4 Work Ramp-Up and Transition

Transition of Work

Contract No.
Project Name
Field Support

Complete Reporting Complete

FA8903-09-D-8565-0007
Performance-Based Remediation at Former Bergstrom AFB, TX, Former Carswell AFB, TX, Former Eaker AFB, AR, Former Homestead AFB, FL, Former Richards-Gebaur AFB, MO
9/24/2020
9/24/2020
W9128F-14-D-0036
Air Force Military Munitions Response Program Site Inspections, Former Bergstrom AFB, TX, and Former Eaker AFB, AR
9/30/2020
9/30/2020

1.5 Remedial System Components

· See Attachment 1 regarding remedial system components.

2.6.1 Meeting/Teleconference Support

· The Contractor participate in Quarterly Teleconferences with the United States Air Force (USAF) representatives to discuss the progress toward accomplishing project objectives.

2.6.2 Public Meetings and Hearings

· There are no base-specific meetings or hearing requirements.

2.6.5 Site Access: Permits, Easements, and Work Site Access

· There are no base-specific permit/easement requirements.

2.9 Contractor Documentation

· No base-specific requirements.

3.4 Computer Aided Design Drawing (CADD) and Geographic Information Systems (GIS) Updates

· No base-specific requirements.

6.14 Land Use Controls (LUC)

· The Contractor shall conduct annual Visual Site Inspections at all sites and prepare a report. The next VSI event is due in 2020.

6.15 Five-Year Reviews

· The Contractor shall prepare a Five-Year Review Report for sites managed under the RCRA/MMRP MMRP as a policy review. The signature date for the Fourth Five-Year Review Report is due March 2021.