This is Standard Form 1413 (Statement and Acknowledgment), which is a partially completed subcontracting form for the Installation of Bedrock Wells project at the Booster Neutrino Beam (BNB) facility. The prime contractor is Fermi Forward Discovery Group, LLC, located in Batavia, IL, under prime contract number 89243024CSC000002. The work involves installing three bedrock monitoring wells to approximately 67 feet below ground surface, including all labor, materials, transportation, overhead, insurance, bonding, safety oversight, quality control, supervision, and equipment.

The project is located at the Fermilab site, 3 miles east of Batavia, Illinois. The form contains acknowledgments of various labor standards clauses and includes the Contract Work Hours and Safety Standards Act provisions. The form is signed by Danielle Amico as Procurement Specialist IV, though several fields remain incomplete including subcontractor information and dates. The related opportunity shows proposals are due February 5, 2025 at 5pm CT, with the Department of Energy Fermi National Accelerator Laboratory as the contracting agency.

View the file

Other versions and copies of SF 1413

File Revision Posted Attached to
B2_DRAFT_08.3_Sec_J_SF1413_exp_05-2027.pdf May 2027 SLAC Job Order Contract
Exhibit F - Statement of Acknowledgment (SF-1413).pdf Revision not stated KAUTZ ROAD SUBSTATION CONSTRUCION, UIP SUBPROJECT 2- KRS
S02_Attachment - SF 1413 updated.pdf Revision not stated Fort Bliss National Cemetery, Gravesite Expansion and FCA Deficiencies
SF-1413_Statement_and_Acknowledgement_Form_(Subcontracting).pdf Revision not stated IE181 - WHS Greenhouse Construction
SF 1413-23A - Statement and Acknowledgment.pdf Revision not stated 70Z03026QCLEV0106 - USCG STA/ANT BUFFALO GENERATOR MAINTENANCE
B08_Attachment_9_Subcontractor_Ack_SF1413-23a_upon_award.pdf Revision not stated EROS Removal and replacement of chilled and conden
Exhibit I - Statement of Acknowledgment (SF-1413).pdf Revision not stated Central Utility Building Addition and Renovation Construction, UIP Subproject 1-CUB
S02_Attachment - Standard Form 1413.pdf Revision not stated Fort Bliss National Cemetery, Gravesite Expansion and FCA Deficiencies
S02_Attachment - Standard Form 1413.pdf Revision not stated CAMP NELSON NATIONAL CEMETERY, KY 833CM3030 – CORRECT FCA DEFICIENCIES
Exhibit K - SF1413.pdf Revision not stated Fire Sprinkler Repair_XGal_IB2A_Lab1_MI50
SF 1413-23A - Statement and Acknowledgment (2).pdf Revision not stated 70Z03026QCLEV0100 - GROUND MAINTENANCE AND SNOW REMOVAL FOR USCG STATION ST. IGNACE
SF 1413-23A - Statement and Acknowledgment (2).pdf Revision not stated 70Z03026QCLEV0101 - GROUND MAINTENANCE AND SNOW REMOVAL FOR SECTOR NORTHERN GRREAT LAKES
SF 1413 - Statement and Acknowledgment.pdf Revision not stated 70Z03026QCLEV0071 - USCG STA LORAIN SECURITY SYSTEM WITH CCTV PROJECT
Exhibit I SF1413_fill-ins.pdf Revision not stated MINOS High Bay Roof Replacement & Masonry Wall Repair
SF 1413 - Statement and Acknowledgment.pdf Revision not stated 70Z03026QCLEV0099 Replacement HVAC Station Building at STA Sodus Point
S02_Attachment - Standard Form 1413.pdf Revision not stated Leavenworth National Cemetery, Gravesite Expansion
SF 1413 - Statement and Acknowledgment.pdf Revision not stated 70Z03026QCLEV0097 - U. S. Coast Guard Station Lorain Gate Replacement
B08_Attachment_7_Subcontractor_Statement_and_Acknowledgment_SF1413-23a.pdf Revision not stated DREDGING OF SEDIMENT POND & CONTACT POOL
SF 1413-23A - Statement and Acknowledgment (1) (1).pdf Revision not stated 70Z03026QCLEV0053- USCG STATION ST. IGNACE REPLACEMENT SHOWER STALL
Exhibit K SF1413_printed.pdf Revision not stated Roof Maintenance and Repair Services IDIQ
Show all 20

Who attaches SF 1413

State Files
Florida 3
Colorado 1

Other files

File Type Posted
Rev Exhibit H Performance Bond FL-40_FFDG.pdf PDF
Amendment 01 to RFP 351002.pdf PDF
Rev Exhibit E Construction Insurance Requirements (01-2025)_FFDG.pdf PDF
Rev Exhibit F Bond Bid FL-41_FFDG.pdf PDF
Rev Exhibit L SARC_Subcontractor Annual RepsCerts Rev 4_FFDG.pdf PDF
Rev Exhibit B Section 010010_General_Requirements_BNB Bedrock Wells_rev3_FFDG.pdf PDF
Rev Exhibit K Proposal Certifications Form PUR-466_FFDG.pdf PDF
QandA_RFP 351002.pdf PDF
Rev Exhibit G Payment Bond FL-42_FFDG.pdf PDF
Rev Exhibit D General Terms and Conditions for Construction (01-2025)_FFDG.pdf PDF
Rev Exhibit C Section 013100_11-21-2024 FermiForward.pdf PDF
Exhibit D FRA General Terms and Conditions for Construction (03.2024).pdf PDF
Exhibit E Construction Insurance Requirements 2024.pdf PDF
Exhibit C Section 013100_ESH_Requirements_BNB_Bedrock_Wells.pdf PDF
Exhibit S Director Safety Letter.pdf PDF
Summary of Required Solicitation Documents.pdf PDF
2.0 Price Proposal Form.pdf PDF
Exhibit P Figure_2-BNB_Work_Area.pdf PDF
Exhibit O Figure 1-Map-Location_BNB-MI12.pdf PDF
1.0 Request for Proposal_ESH_351002_DA.pdf PDF
Exhibit G Payment Bond FL-42 (Rev 12.22).pdf PDF
Exhibit K Proposal Certifications Form PUR-466 Rev 1 (10142021).pdf PDF
Exhibit R Well Completion Report.pdf PDF
Exhibit B Section 010010_General_Requirements_BNB Bedrock Wells_rev3.pdf PDF
Exhibit L Subcontractor Annual Representations and Certifications (SARC) (Rev. 3).pdf PDF
Exhibit A SOW-Bedrock_MWs_for_BNB_R2.pdf PDF
Exhibit N Sample Subcontract.pdf PDF
Exhibit M Davis Bacon Wage Rates IL20240011 Modification 17 11-15-2024.pdf PDF
Exhibit H Performance Bond FL-40 (Rev 12.22).pdf PDF
Exhibit F Bid Bond FL-41 (Rev 12.22).pdf PDF
Exhibit Q S-1248 Final Soil Boring Log.pdf PDF
Business Visitor Registration Instructions and Directions.pdf PDF
Exhibit I Fermilab Subcontractor Safety Information Questionnaire.pdf PDF
Exhibit J Statement and Acknowledgment (Standard Form 1413) (Rev 42013).pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT AND ACKNOWLEDGMENT OMB Control Number: 9000-0066 Expiration Date: 5/31/2025

PART I - STATEMENT OF PRIME CONTRACTOR

1. PRIME CONTRACT NUMBER 2. DATE SUBCONTRACT

AWARDED

3. SUBCONTRACT NUMBER

15b. TITLE OF PERSON SIGNING

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1413 (REV. 4/2013)

Prescribed by GSA/FAR (48 CFR) 53.222(e)

4. PRIME CONTRACTOR 5. SUBCONTRACTOR

a. NAME a. NAME

b. STREET ADDRESS b. STREET ADDRESS

c. CITY d. STATE e. ZIP CODE c. CITY d. STATE e. ZIP CODE

6. The prime contract does, does not contain the clause entitled "Contract Work Hours and Safety Standards Act -- Overtime Compensation."

7. The prime contractor states that under the contract shown in Item 1, a subcontract was awarded on the date shown in Item 2 to the subcontractor identified in item 5 by the following firm:

a. NAME OF AWARDING FIRM

b. DESCRIPTION OF WORK BY SUBCONTRACTOR

8. PROJECT 9. LOCATION

10a. NAME OF PERSON SIGNING 11. BY (Signature) 12. DATE SIGNED

10b. TITLE OF PERSON SIGNING

PART II - ACKNOWLEDGMENT OF SUBCONTRACTOR

13. The subcontractor acknowledges that the following clauses of the contract shown in Item 1 are included in this subcontract:

Contract Work Hours and Safety Standards Act - Overtime Compensation (If included in prime contract see Block 6) Payrolls and Basic Records Withholding of Funds Disputes Concerning Labor Standards Compliance with Construction Wage Rate Requirements and Related Regulations

Construction Wage Rate Requirements Apprentices and Trainees Compliance with Copeland Act Requirements Subcontracts (Labor Standards) Contract Termination - Debarment Certification of Eligibility

14. NAME(S) OF ANY INTERMEDIATE SUBCONTRACTORS, IF ANY

A C

B D

15a. NAME OF PERSON SIGNING 16. BY (Signature) 17. DATE SIGNED

Paperwork Reduction Act Statement - This information collection meets the requirements of 44 U.S.C. § 3507, as amended by section 2 of the Paperwork Reduction Act of 1995. You do not need to answer these questions unless we display a valid Office of Management and Budget (OMB) control number.

The OMB control number for this collection is 9000-0066. We estimate that it will take .05 hours to read the instructions, gather the facts, and answer the questions. Send only comments relating to our time estimate, including suggestions for reducing this burden, or any other aspects of this collection of information to: U.S. General Services Administration, Regulatory Secretariat Division (M1V1CB), 1800 F Street, NW, Washington, DC 20405.

1.6 Presentation Agent PDFlib 3.02 (C++/Win32) D:20050617125503-04'00' D:20080212101247-05'00' Presentation Agent Standard Form 1413 - Statement and Acknowledgment

STATEMENT AND ACKNOWLEDGMENT

OMB Control Number: 9000-0066 Expiration Date: 5/31/2025

PART I - STATEMENT OF PRIME CONTRACTOR

1. PRIME CONTRACT NUMBER

2. DATE SUBCONTRACT AWARDED

3. SUBCONTRACT NUMBER

15b. TITLE OF PERSON SIGNING

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1413 (REV. 4/2013)

Prescribed by GSA/FAR (48 CFR) 53.222(e)

4. PRIME CONTRACTOR

5. SUBCONTRACTOR

a. NAME

a. NAME

b. STREET ADDRESS

b. STREET ADDRESS

c. CITY

d. STATE

e. ZIP CODE

c. CITY

d. STATE

e. ZIP CODE

6. The prime contract does, does not contain the clause entitled "Contract Work Hours and Safety Standards Act -- Overtime Compensation."

7. The prime contractor states that under the contract shown in Item 1, a subcontract was awarded on the date shown in Item 2 to the subcontractor identified in item 5 by the following firm:

a. NAME OF AWARDING FIRM

b. DESCRIPTION OF WORK BY SUBCONTRACTOR

8. PROJECT

9. LOCATION

10a. NAME OF PERSON SIGNING

11. BY (Signature)

12. DATE SIGNED

10b. TITLE OF PERSON SIGNING

PART II - ACKNOWLEDGMENT OF SUBCONTRACTOR

13. The subcontractor acknowledges that the following clauses of the contract shown in Item 1 are included in this subcontract:

Contract Work Hours and Safety Standards Act - Overtime Compensation (If included in prime contract see Block 6) Payrolls and Basic RecordsWithholding of FundsDisputes Concerning Labor StandardsCompliance with Construction Wage Rate Requirements and Related Regulations Construction Wage Rate Requirements Apprentices and Trainees Compliance with Copeland Act Requirements Subcontracts (Labor Standards) Contract Termination - Debarment Certification of Eligibility

14. NAME(S) OF ANY INTERMEDIATE SUBCONTRACTORS, IF ANY

A C B D 15a. NAME OF PERSON SIGNING

16. BY (Signature)

17. DATE SIGNED

Paperwork Reduction Act Statement - This information collection meets the requirements of 44 U.S.C. § 3507, as amended by section 2 of the Paperwork Reduction Act of 1995. You do not need to answer these questions unless we display a valid Office of Management and Budget (OMB) control number. The OMB control number for this collection is 9000-0066. We estimate that it will take .05 hours to read the instructions, gather the facts, and answer the questions. Send only comments relating to our time estimate, including suggestions for reducing this burden, or any other aspects of this collection of information to: U.S. General Services Administration, Regulatory Secretariat Division (M1V1CB), 1800 F Street, NW, Washington, DC 20405.

1. PRIME CONTRACT NUMBER: 89243024CSC000002
4A. NAME: Fermi Forward Discovery Group, LLC
4B. STREET ADDRESS: Kirk Road and Wilson Street
4C. CITY: Batavia
7A. NAME OF AWARDING FIRM: Fermi Forward Discovery Group, LLC
10A. NAME OF PERSON SIGNING: Danielle Amico
15A. NAME OF PERSON SIGNING:
15B. TITLE OF PERSON SIGNING:
10B. TITLE OF PERSON SIGNING: Procurement Specialist IV
14. NAME(S) OF ANY INTERMEDIATE SUBCONTRACTORS, IF ANY. Line A.:
14. NAME(S) OF ANY INTERMEDIATE SUBCONTRACTORS, IF ANY. Line D.:
14. NAME(S) OF ANY INTERMEDIATE SUBCONTRACTORS, IF ANY. Line C.:
14. NAME(S) OF ANY INTERMEDIATE SUBCONTRACTORS, IF ANY. Line B.:
8. PROJECT: Installation of Bedrock Wells at Booster Neutrino Beam (BNB)
9. LOCATION: Fermilab Site, 3 miles east of the City of Batavia, Illinois
7B. DESCRIPTION OF WORK BY SUBCONTRACTOR: The Subcontractor shall furnish all labor, materials, transportation, overhead, insurance, bonding costs, safety oversight, quality control oversight, supervision, and equipment necessary to perform the work described in the Statement of Work entitled, “Installation of Bedrock Wells at Booster Neutrino Beam (BNB)” dated November 1, 2024, Section 010010 - General Requirement (March 2022), Section 013100 - Environment, Safety, and Health Requirements (October 2024) mentioned therein, which the Statement of Work, amendment, and other documents are attached to and hereby made a part of this Subcontract.
5C. CITY:
4E. ZIP CODE: 60510
5E. ZIP CODE:
4D. STATE: IL
5D. STATE:
3. SUBCONTRACT NUMBER:
5A. NAME:
5B. STREET ADDRESS:
2. DATE SUBCONTRACT AWARDED. Enter 2 digit month, 2 digit day and 4 digit year.:
12. DATE SIGNED. Enter 2 digit month, 2 digit day and 4 digit year.:
17. DATE SIGNED. Enter 2 digit month, 2 digit day and 4 digit year.:
6. The prime contract does contain the clause entitled "Contract Work Hours and Safety Standards Act -- Overtime Compensation.": 1
6. The prime contract does not contain the clause entitled "Contract Work Hours and Safety Standards Act -- Overtime Compensation.": 0
Sign here if you are the Subcontractor.:

File details come from the government source that posted it. Updated .