ESBD_535245_1783451490513_ATTACHMENT G.O - Ellington Field (EF) Starting Of Systems.pdf
PDF 61 KB Posted
- Attached to
- Ellington HVAC Replacement Projects
- Solicitation number
- TMD26-ANG-WJ-25269002
- Issued by
- Harris County, Texas
About this file
This document is a specification attachment for the Ellington Air Force Base in Houston, Texas, detailing requirements for the starting of systems as part of a construction or renovation project. The scope of work encompasses the coordination and execution of equipment and system start-up procedures, including manufacturer demonstrations, testing, adjusting, and balancing services. The contractor is required to notify the Project Manager seven days prior to initiating start-up of any equipment or system and must verify proper installation, lubrication, electrical characteristics, and wiring completion before operation. Start-up activities must be conducted under the supervision of applicable contractor personnel and in accordance with manufacturers' instructions, with manufacturer representatives required to be present when specified in individual specification sections. The contractor must submit written reports confirming proper installation and correct functioning of each system.
Demonstration and instruction requirements mandate that the contractor demonstrate equipment operation and maintenance to the owner's personnel prior to final payment, utilizing operation and maintenance manuals as instructional basis. For equipment requiring seasonal operation, demonstrations must be performed for alternative seasons within six months of initial instruction. The General Contractor is responsible for hiring an independent third-party firm to perform all testing, adjusting, and balancing services, with the independent firm reporting observations and test results to the Project Manager to verify compliance with contract requirements. The specification document was issued on May 21, 2024, for Ellington Field in Houston, Texas.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT G.O - ELLINGTON AFB (EF) STARTING OF SYSTEMS
PART 1 – GENERAL
1. SUMMARY
A. This Section includes:
a. Starting systems.
b. Demonstration and instructions.
c. Testing, adjusting, and balancing.
d. Third party testing, adjusting, and balancing.
2. RELATED SECTIONS
A. Solicitation Section C Statement of Work.
B. Attachment G.G - Ellington AFB (EF) Quality Control.
C. Attachment G.P - Ellington AFB (EF) Contract Closeout.
3. STARTING OF SYSTEMS
A. Coordinate schedule for start-up of various equipment and systems.
B. Notify the Project Manager in writing seven days prior to start-up of each item.
C. Verify that each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, control sequence, or for other conditions which may cause damage.
D. Verify that tests, meter readings, and specified electrical characteristics agree with those re- quired by the equipment or system manufacturer.
E. Verify wiring and support components for equipment are complete and tested.
F. Execute start-up under supervision of applicable Contractors' personnel in accordance with manufacturers' instructions.
G. When specified in individual specification Sections, require manufacturer to provide authorized representative to be present at site to inspect, check, and approve equipment or system installation prior to start-up, and to supervise placing equipment or system in operation.
H. Submit a written report in accordance with Section 01400 that equipment or system has been properly installed and is functioning correctly.
4. DEMONSTRATION AND INSTRUCTIONS
A. Demonstrate operation and maintenance of Products to Owner's personnel prior to final payment.
B. For equipment or systems requiring seasonal operation, perform demonstration for other sea- son within six months.
C. Utilize operation and maintenance manuals as basis for instruction. Review contents of manual with Owners' personnel in detail to explain all aspects of operation and maintenance.
D. Demonstrate start-up, operation, control, adjustment, troubleshooting, servicing, maintenance, and shutdown of each item of equipment at scheduled time at designated location.
E. Prepare and insert additional data in operations and maintenance manuals when need for additional data becomes apparent during instruction.
ELLINGTON FIELD, HOUSTON, TX 21 May 2024
F. The amount of time required for instruction on each item of equipment and system is that specified in individual sections.
5. TESTING, ADJUSTING, AND BALANCING
A. General Contractor shall pay for (Hire) for services of an independent firm to perform testing, adjusting, and balancing. The independent firm shall work with the Project
Manager in conducting operations of the performance.
B. Reports will be submitted by the independent firm to the Project Manager indicating observations and results of tests and indicating compliance or non-compliance with the requirements of the Contract Documents.