This is an Attachment to a specification document for a construction project at Ellington Air Force Base in Houston, Texas, establishing coordination and meeting requirements for the contractor. The document outlines mandatory coordination procedures for scheduling, submittals, and work sequencing to ensure efficient installation of interdependent construction elements. Key requirements include a pre-construction meeting to be scheduled by the Project Manager after Notice of Award, during which the contractor must distribute contract documents, submit subcontractor lists, schedule of values, and construction schedules. Progress meetings are required at maximum monthly intervals, with bi-weekly meetings preferred, and must include the job superintendent, major subcontractors, suppliers, and the Project Manager. Written meeting minutes must be provided within three working days of each meeting. Pre-installation meetings are required for specific work sections, with the contractor required to notify the Project Manager four days in advance. All meetings must address coordination of interdependent work, utility compatibility, space requirements, concealment of utilities in finished areas, and maintenance accessibility.
The execution phase of this specification requires the contractor to examine existing site conditions and substrate surfaces to verify acceptability for subsequent work, with beginning new work constituting acceptance of existing conditions. The contractor must verify structural capability for attachment of new work, examine specific conditions outlined in individual specification sections, and confirm utility services are available with correct characteristics and location. Preparation requirements include cleaning substrate surfaces, sealing cracks or openings, and applying any manufacturer-required primers, sealers, or conditioners prior to applying new materials or substances. The document does not address pricing, set-asides, incumbents, or funding sources.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT G.B - ELLINGTON AFB (EF) COORDINATION AND
MEETINGS
PART 1 – GENERAL
1. SUMMARY
A. This Section includes:
a. Coordination
b. Preconstruction meeting
c. Progress meetings
d. Pre-installation meetings
e. Examination
f. Preparation
2. COORDINATION
A. Coordinate scheduling, submittals, and Work of the various sections of the Project
Manual to assure efficient and orderly sequence of installation of interdependent construction elements, [with provisions for accommodating items installed later].
B. Verify utility requirements and characteristics of operating equipment are compatible with building utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, such equipment.
C. Coordinate space requirements and installation of mechanical and electrical work which are indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit, as closely as practicable; place runs parallel with line of building.
Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.
D. In finished areas [except as otherwise indicated], conceal pipes, ducts, and wiring within the construction. Coordinate locations of fixtures and outlets with finish elements.
E. Coordinate completion and cleanup of Work of separate sections in preparation for
Substantial Completion.
F. After Owner occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Owner's activities.
3. PRE-CONSTRUCTION MEETING
A. The Project Manager will schedule a meeting after Notice of Award.
B. Agenda:
a. Distribution of Contract Documents
b. Submission of list of Subcontractors, list of Products, schedule of values, and proposed construction schedule.
c. Designation of personnel representing the parties in Contract
d. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures
e. Scheduling
f. Safety plan submittal
ELLINGTON FIELD, HOUSTON, TX 21 May 2024
4. PROGRESS MEETINGS
A. The Contractor will in Coordination with the Project Manager:
a. Schedule and administer meetings throughout progress of the Work at maximum monthly intervals, every 2-weeks is preferred.
b. Make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings.
c. Review coordination with related work
d. Provide written documentation of the meeting minutes for review and acceptance by all present within 3 working days of each meeting.
B. Attendance Required: Job superintendent, major Subcontractors and suppliers, the
Project Manager as appropriate to agenda topics for each meeting.
C. Agenda:
a. Review minutes of previous meetings
b. Review of Work progress
c. Field observations, problems, and decisions
d. Identification of problems which impede planned progress.
e. Review of submittals schedule with emphasis on Critical Path Items and status of submittals
f. Review of off-site fabrication and delivery schedules
g. Maintenance of progress schedule
h. Corrective measures to regain projected schedules.
i. Planned progress during succeeding work period.
j. Coordination of projected progress
k. Maintenance of quality and work standards
l. Effect of proposed changes on progress schedule and coordination
m. Other business relating to Work.
5. PRE-INSTALLATION MEETING
A. When required in individual specification sections, convene a pre-installation meeting at work site prior to commencing work of the section.
B. Require attendance of parties directly affecting, or affected by, work of the
C. specific section.
D. Notify the Project Manager four days in advance of meeting date.
E. Contractor will prepare agenda and preside at meeting:
a. Review conditions of installation, preparation, and installation procedures
b. Provide written documentation of the minutes of the meeting within 3 working days of each meeting.
PART 2 – EXECUTION
1. EXAMINATION
A. Verify that existing site conditions and substrate surfaces are acceptable for subsequent Work. Beginning new Work means acceptance of existing conditions.
B. Verify that existing substrate is capable of structural attachment of new Work being applied or attached.
ELLINGTON FIELD, HOUSTON, TX 21 May 2024
C. Examine and verify specific conditions described in individual specification sections.
D. Verify that utility services are available, of the correct characteristics, and in the correct location.
2. PREPARATION
A. Clean substrate surfaces prior to applying next material or substance.
B. Seal cracks or openings of substrate prior to applying next material or substance.
C. Apply any manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying any new material or substance in contact or bond.