ESBD_535245_1783451462644_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf

PDF 63 KB Posted

Attached to
Ellington HVAC Replacement Projects
Solicitation number
TMD26-ANG-WJ-25269002
Issued by
Harris County, Texas

About this file

This is an Attachment G.M specification document for material equipment procurement at Ellington Air Force Base (EF) in Houston, Texas, dated May 21, 2024. The document establishes requirements for the transportation, handling, storage, and protection of products to be supplied under the contract. Key specifications include the mandatory transportation and inspection of products in accordance with manufacturer's instructions, with prompt verification of compliance, quantities, and damage upon receipt. Storage requirements mandate weather-tight, climate-controlled enclosures for sensitive products, sloped supports for exterior storage of fabricated products, and bonded off-site storage when on-site storage is unavailable. The document further requires periodic inspections to maintain product condition and arranges storage to permit access for inspection purposes.

The specification addresses product substitution procedures through a structured submittal process requiring three copies of substitution requests on provided forms, complete data substantiation, shop drawings, product data, and certified test results demonstrating equivalence to specified products. Contractors requesting substitutions must represent that they have investigated the proposed product, determined it meets or exceeds quality standards, will provide equivalent warranty coverage, will coordinate any required installation changes at no additional cost to the owner, and waive claims for additional costs or time extensions. The Project Manager will provide written notification of substitution acceptance or rejection, and contractors are responsible for supplying items as originally specified or an acceptable alternative substitution without additional cost to the government if substitution requests are denied. Payment for stored materials on-site is limited to actual material costs and requires submission of inventory documentation and supplier invoices.

View the file

Other files

File Type Posted
ESBD_535245_1783451200196_ATTACHMENT G.C - Ellington AFB (EF) Project Coordination.pdf PDF
ESBD_535245_1783451141821_Attachment G.4 - Mandatory Pricing Sheet.xlsx XLSX spreadsheet
ESBD_535245_1783451228039_ATTACHMENT G.E - Ellington Field (EF) Safety Policies And Procedures.pdf PDF
ESBD_535245_1783451274676_ATTACHMENT G.F.2 - Ellington AFB (EF) Contractor Hazardous Material Identification Form Close-Out Procedures.pdf PDF
ESBD_535245_1783451625900_ATTACHMENT G.V - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Unmarked Burials.pdf PDF
ESBD_535245_1783451641521_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
ESBD_535245_1783451577202_ATTACHMENT G.S - Ellington AFB (EF) Substitutions Request Form.pdf PDF
ESBD_535245_1783451132036_ATTACHMENT G.3 Texas Military Department Standard Terms and Conditions Revision 6.pdf PDF
ESBD_535245_1783451287242_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf PDF
ESBD_535245_1783451100102_TMD26-ANG-WJ-25269002 - Solicitation.pdf PDF
ESBD_535245_1783451238797_ATTACHMENT G.F - Ellington Field (EF) EMS Hazardous Material Procedures.pdf PDF
ESBD_535245_1783451344370_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
ESBD_535245_1783451325745_ATTACHMENT G.I - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Cultural Materials.pdf PDF
ESBD_535245_1783451508643_ATTACHMENT G.P - Ellington Field (EF) Contract Closeout.pdf PDF
ESBD_535245_1783451258158_ATTACHMENT G.F.1 - Ellington AFB (EF) Contractor Hazardous Material Usage Data.pdf PDF
ESBD_535245_1783451524511_ATTACHMENT G.Q - Ellington AFB (EF) Cutting And Patching.pdf PDF
ESBD_535245_1783451599549_ATTACHMENT G.T - Ellington Field (EF) Post Award Submittals.pdf PDF
ESBD_535245_1783451651616_ATTACHMENT G.X - Ellington AFB (EF) AF3000.pdf PDF
ESBD_535245_1783451121206_ATTACHMENT G.2 Application for Texas Identification Number AP-152.pdf PDF
ESBD_535245_1783451432778_ATTACHMENT G.K - Ellington AFB (EF) Construction Facilities And Temporary Controls.pdf PDF
ESBD_535245_1783451478101_ATTACHMENT G.N - Ellington Field (EF) Manufacturers’ Services.pdf PDF
ESBD_535245_1783451177632_ATTACHMENT G.A - Ellington Field (EF) General Requirements.pdf PDF
ESBD_535245_1783451111748_ATTACHMENT G.1 Direct Deposit Authorization Form 74-176 (Rev.9-2121).pdf PDF
ESBD_535245_1783451612312_ATTACHMENT G.U - Ellington Field (EF) Sustainable Design Requirements.pdf PDF
ESBD_535245_1783451216328_ATTACHMENT G.D - Ellington AFB (EF) Field Engineering.pdf PDF
ESBD_535245_1783451540073_ATTACHMENT G.R - Ellington Field (EF) EMS Construction Waste Management And Disposal Part 1 - General.pdf PDF
ESBD_535245_1783451158210_Attachment G.5 - HUB HSP.pdf PDF
ESBD_535245_1783451490513_ATTACHMENT G.O - Ellington Field (EF) Starting Of Systems.pdf PDF
ESBD_535245_1783451446516_ATTACHMENT G.L - Ellington Field JRB Final Asbestos Abatement Report Template.pdf PDF
ESBD_535245_1783451304801_ATTACHMENT G.H - Ellington Field (EF) EMS Environmental Protection.pdf PDF
ESBD_535245_1783451189009_ATTACHMENT G.B - Ellington Field (EF) Coordination And Meetings.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT G.M - ELLINGTON AFB (EF) MATERIAL EQUIPMENT

PART 1 – GENERAL

1. RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and

Supplementary Conditions, apply to this Section.

2. SUMMARY

A. This Section includes:

a. Transportation and handling

b. Storage and protection

c. Product options

d. Substitutions

3. TRANSPORTATION AND HANDLING

A. Transport and handle Products in accordance with manufacturer's instructions.

B. Promptly inspect shipments to ensure that Products comply with requirements, quantities are correct, and Products are undamaged.

C. Provide equipment and personnel to handle Products by methods to prevent soiling, disfigurement, or damage.

4. STORAGE AND PROTECTION

A. Store and protect Products in accordance with manufacturers' instructions, with seals and labels intact and legible.

B. Store sensitive Products in weather tight, climate-controlled enclosures.

C. For exterior storage of fabricated Products, place on sloped supports, above ground.

D. Provide bonded off-site storage and protection when site does not permit on-site storage or protection.

E. Cover Products subject to deterioration with impervious sheet covering. Provide ventilation to avoid condensation or potential degradation of Product.

F. Store loose granular materials on solid flat surfaces in a well-drained area. Prevent mixing with foreign matter.

G. Provide equipment and personnel to store Products by methods to prevent soiling, disfigurement, or damage.

H. Arrange storage of Products to permit access for inspection. Periodically inspect to verify Products are undamaged and are maintained in acceptable condition.

I. Payment for materials stored on site will be made only when the request is accompanied by an inventory of stored materials along with copies of the supplier invoices for the stored materials. Only actual cost of the materials stored will be compensated.

5. PRODUCT OPTIONS

A. Products Specified by Reference Standards or by Description Only: Any Product meeting those standards or description.

B. Products Specified by Naming One or More Manufacturers: Products of manufacturers named and meeting specifications, no options or substitutions allowed.

C. Products Specified by Naming One or More Manufacturers with a Provision for

ELLINGTON FIELD, HOUSTON, TX 21 May 2024

Substitutions: Submit a request for substitution for any manufacturer not named in accordance with the following article.

6. SUBSTITUTIONS

A. Project Manager will consider requests for Substitutions during the submittal phase of the project.

B. Substitutions may be considered when a Product becomes unavailable through no fault of the Contractor.

C. Document each request with complete data substantiating compliance of proposed

Substitution with Contract Documents.

D. A request constitutes a representation that the Contractor:

a. Has investigated proposed Product and determined that it meets or exceeds the quality level of the specified Product.

b. Will provide the same warranty for the Substitution as for the specified

Product.

c. Will coordinate installation and make changes to other Work which may be required for the Work to be complete with no additional cost to Owner.

d. Waives claims for additional costs or time extension which may subsequently become apparent.

E. Substitutions will not be considered when they are indicated or implied on shop drawing or product data submittals, without separate written request, or when acceptance will require revision to the Contract Documents.

F. Substitution Submittal Procedure:

a. Submit three copies of request for Substitution for consideration on

Substitution Request Form attached to this section. Limit each Substitution

Request Form to one proposed Substitution.

b. Submit shop drawings, product data, and certified test results attesting to the proposed Product equivalence.

c. The Project Manager will notify Contractor in writing of decision to accept or reject re- quest.

G. If request for substitution is not accepted by the government, Contractor is responsible for sup- plying item as originally specified or an acceptable substitution without additional cost to the Owner.

File details come from the government source that posted it. Updated .