About this file
This is a close-out procedures attachment for a contractor hazardous material identification form at Ellington Air Force Base (EF). The document establishes the protocol for concluding hazardous material (HM) management activities at the installation. The contractor is required to participate in a close-out inspection alongside the Project Manager's Representative and the Environmental Manager to verify that all used and unused hazardous materials have been completely removed from the base. The procedures ensure accountability and environmental compliance by documenting the contractor's participation and obtaining signatures from all relevant parties, including the contractor, Project Manager/Representative, and CEV Environmental Manager, along with corresponding dates.
This attachment serves as Part II of a two-part form and functions as a verification mechanism for hazardous material disposition. No pricing terms, set-asides, incumbency information, funding sources, or contract award dates are specified in this document. The close-out procedures are administrative in nature and represent the final compliance step in hazardous material management operations at Ellington AFB.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT G.F.2 - ELLINGTON AFB (EF) CONTRACTOR HAZARDOUS
MATERIAL IDENTIFICATION FORM CLOSE-OUT PROCEDURES
Part II
Attach this part to Part I
Contractor shall accompany the Project Manager’s Representative and the
Environmental Manager on the close-out inspection to ensure all used and unused HM has been removed from the installation.
Close-out Approval Signatures:
Contractor
Signature Date
Project Manager
/Representative CEV
(Environmental Manager)