DRD 1 - OCI Plan.pdf

PDF 141 KB Posted

Attached to
Near Earth Orbit Network Program's Sounder for Microwave-Based Applications
Solicitation number
80GSFC26R0028
Issued by

About this file

This is a Data Requirements Document (DRD) for an Organizational Conflicts of Interest (OCI) Plan required under NASA solicitation 80GSFC26R0028. The document is classified as an administrative requirement with an OPR of OP and was issued on March 13, 2026.

The OCI Plan must be submitted with the initial proposal and updated as needed throughout contract performance. The contractor is required to develop a comprehensive approach to identify, avoid, mitigate, neutralize, and report potential OCI issues in accordance with FAR Subpart 9.5 and NASA's NFS 1809.5. The plan must include: a designated point of contact for OCI issues; demonstration of understanding of OCI principles and the three primary types of conflicts (biased ground rules, unequal access to information, and impaired objectivity); defined company roles and responsibilities for screening and monitoring conflicts; employee training requirements with documentation for entrance, refresher, and exit training; breach reporting procedures to the contracting officer; identification of affiliated companies and OCI coordination procedures; a process for reporting actual and potential OCIs discovered during performance; flowdown requirements to subcontractors; organizational and employee sanctions for violations; and an assertion that no OCIs currently exist. The plan must also include listings of all NASA contracts and non-NASA Federal contracts performed by the prime and proposed subcontractors within the preceding five years, with detailed scope descriptions and conflict analyses. Additionally, the contractor must address financial or other interests beyond Federal contracts, explain mitigation strategies for each identified OCI, maintain an appendix identifying resolution strategies, perform periodic self-audits, and maintain records available to the Government. The contractor shall review and update the OCI Plan annually or as directed by the contracting officer, with all revisions subject to contracting officer approval.

View the file

Other files

File Type Posted
RFP - 80GSFC26R0028 SMBA - Question and Answer 13-14.pdf PDF
Amnt 3 - RFP - 80GSFC26R0028 SMBA.pdf PDF
RFP - 80GSFC26R0028 SMBA - Question and Answer 12.pdf PDF
RFP - 80GSFC26R0028 SMBA - Question and Answer 11.pdf PDF
RFP - 80GSFC26R0028 SMBA - Question and Answer 10.pdf PDF
Amnt 2 - Enclosure 2 - Cost Exhibits 1- 8.xlsx XLSX spreadsheet
Amnt 2 - RFP - 80GSFC26R0028 SMBA.pdf PDF
RFP - 80GSFC26R0028 SMBA - Questions and Answers 1-9.pdf PDF
Amnt 1 - Attachment C - Non-Technical Contract Data Requirements List_20260408.pdf PDF
Amnt 1 - RFP - 80GSFC26R0028 SMBA.pdf PDF
Amnt 1 - Attachment O - Milestone Payment Schedule_20260408.pdf PDF
Amnt 1 - DRD 6 - SCV Reporting.pdf PDF
DRD 2 - NASA C-SCRM Plan Questionnaire.xlsx XLSX spreadsheet
DRD 3 - CPIC DRD Template for IT Portfolio PPM Data Collection.xlsx XLSX spreadsheet
DRD 4 - CITAR Report Template.xlsx XLSX spreadsheet
Attachment N - Applicable Documents List.pdf PDF
Attachment O - Milestone Payment Schedule.pdf PDF
Enclosure 3 - Past Performance Questionnaire.pdf PDF
Enclosure 4 - Financial Capability Disclosure.pdf PDF
RFP Cover Letter - 80GSFC26R0028 SMBA.pdf PDF
NS1-SMBA-SOW-0002D_NS1 SOW_03162026.pdf PDF
DRD 4 - CITAR DRD.pdf PDF
Attachment D - OCI Plan.pdf PDF
NS1-SMBA-REQ-0001E_NS1 SMBA PRD_03112026.pdf PDF
Enclosure 5 - CWBS.pdf PDF
RFP - 80GSFC26R0028 SMBA.pdf PDF
DRD 5 - CAIRIA DRD.pdf PDF
Attachment F - Safety and Health Plan.pdf PDF
Attachment I - Government Furnished Property.pdf PDF
Attachment L - Contractor Proposed Enhancements.pdf PDF
Enclosure 2 - Cost Exhibits 1- 8.xlsx XLSX spreadsheet
Attachment B - Financial Management Reporting Requirements.pdf PDF
Attachment C - Non-Technical Contract Data Requirements List.pdf PDF
DRD 2 - Security Requirements for Unclassified IT Resources DRD w C-SCRM requirements.pdf PDF
DRD 3 - CPIC DRD.pdf PDF
Attachment E - CSCRM Plan.pdf PDF
Attachment G - Small Business Subcontracting Plan.pdf PDF
Attachment H - Requirements Statements List.pdf PDF
Attachment K - TM Rate Matrices.pdf PDF
NS1-SMBA-CDRL-0001C_01152026.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. DRD Title: Organizational Conflicts of Interest (OCI) Plan

2. DRD No.: 1 3. Data Type: 1 4.OPR: OP

5. Solicitation No.: 80GSFC26R0028

6. Contract No.: TBD

7. Date Issued: March 13, 2026 8. Date Revised: N/A

9. DRD Category:

Technical ☐ Administrative ☒

S&MA ☐

10. Description/Use: The Plan will communicate the contractor’s approach to identify and resolve OCIs. The contractor will be held accountable for identifying, dispositioning, and reporting OCIs during contract performance.

11. Distribution: Distribution shall be as instructed by the contracting officer.

Initial Submission: Plan shall be submitted with the initial proposal.

Submission Frequency: As needed.

Format: As specified in Contract Attachment C, Non-Technical Data Requirements List.

Interrelationship: NASA Federal Acquisition Regulation (FAR) Supplement (NFS) 1852.237-72, Access to Sensitive Information, NFS 1852.237-73, Release of Sensitive Information.

Applicable Documents: FAR Subpart 9.5, Organizational and Consultant Conflicts of Interest, NFS 1809.5, Organizational and Consultant Conflicts of Interest, NASA Guide on Organizational Conflicts of Interest.

Scope: The OCI Plan describes the contractor’s comprehensive approach to identify, avoid, mitigate, neutralize, and report potential OCI issues, including conflicts described in the solicitation and those discovered during contract performance.

Contents: The OCI Plan shall meet the requirements of FAR 9.5 and include the following:

1. Point of contact for OCI issues and reports.

2. Demonstrate an understanding of (1) OCI principles and (2) the full breadth of OCI issues and the types of harm that can result. The Plan at a minimum addresses the three primary types of OCIs (i.e., biased ground rules, unequal access to information, and impaired objectivity).

3. Define company roles, responsibilities, and procedures for (1) screening (i.e., identifying/recognizing, analyzing/evaluating, resolving, and reporting) existing and new business opportunities for actual/potential OCIs and (2) monitoring and reporting all potential/actual OCIs that arise, resolving conflicts, and reporting previously unidentified OCIs or potential OCIs to the Government.

4. Describe how employees are notified of the Plan’s requirements and how this notification will be documented.

Establish and require entrance training for new employees, refresher training for existing employees, and exit training for departing employees. Describe how completion of this training will be documented, including a copy of any training certification template that the contractor will use to document that its employees have completed training.

5. Describe how the contractor will report breaches of the protective measures in the Plan to the contracting officer. Describe what processes the contractor will implement following any breach and indicate that final resolution of the corrective action must be approved by the contracting officer.

6. Identify any affiliated companies/entities (e.g., a parent company or a wholly owned subsidiary) and procedures for coordinating OCIs with such affiliated companies/entities.

7. Address the process for reporting all potential/actual OCIs that arise during performance of the contract. An OCI report shall include (1) a description of the conflict, (2) the plan for resolving the conflict, and (3) the benefits/risks to contract performance associated with plan approval/acceptance. Specific resolution strategies shall be appended to the Plan upon approval by the Government.

8. Explain how the contractor will flow down the provisions of this Plan to any subcontractor that may have a conflict with regard to performing the requirements of this contract. Discuss affected subcontractors’ OCI program as it relates to this contract and specifically explain how affected subcontractors will identify, resolve, and report actual/potential OCIs associated with this contract.

9. Define organizational and employee sanctions for violations of established OCI procedures/requirements/guidelines.

10. Include an assertion from the Offeror that to the best of its knowledge no OCIs exist currently, if applicable.

Provide a list of all the prime’s and proposed subcontractor(s)’s NASA contracts and subcontracts currently being performed and contracts performed within the last five years of the release of this solicitation, in order to provide the CO a better understanding of other NASA work performed by the Offeror that may give rise to an actual or potential conflict. For each prime contract and subcontract listed, the Offeror shall: (1) identify the contract number; (2) describe the scope of work in sufficient detail to ascertain the likelihood of a conflict with performance of this contract; and (3) discuss any conflicts that may arise from performance of the listed contracts and award of this contract.

11. The Offeror shall also list any non-NASA Federal contracts and subcontracts that it or its proposed subcontractors are currently performing or have performed in the five years preceding the release of the solicitation that may give rise to an OCI. For each and subcontract listed, the Offeror shall: (1) identify the contract by number and name; (2) identify the name, address and contact information of the customer(s); (3) describe the scope of work in sufficient detail to ascertain the likelihood of a conflict with performance of this contract; and (4) discuss any conflicts that may arise from performance of the listed contracts and award of this contract.

12. For financial or other interests or relationships beyond Federal contracts or subcontracts that may give rise to an OCI, the Offeror shall (1) address the nature and extent of the interest(s) or relationship(s); (2) list any entity or entities involved in the interest(s) or relationship(s) and award of this contract.

13. The Offeror shall address how it will avoid, neutralize, or mitigate each potential OCI listed above. Sufficient information must be provided to allow a meaningful evaluation of the potential effect of the interest on the performance of the statement of work.

14. Include a requirement to update this plan as necessary to address specific OCIs. All updates to the plan must be approved by the contracting officer and the updates/changes must be incorporated in the contract to be effective.

15. Require periodic self-audits to ensure compliance with established OCI procedures/requirements/guidelines.

16. Define records related to the OCI Plan (e.g., training and audit records) that will be made available to the

Government upon request. Note: The OCI Plan as outlined in paragraphs 1 through 12 above is not for the purpose of addressing other very important contractual obligations such as (1) the contractor’s obligation to protect sensitive information in accordance with NFS 1852.237-72, Access to Sensitive Information, (2) the contractor’s obligation to conduct business in an ethical manner in accordance with FAR 52.203-13, contractor’s Code of Business Ethics and Conduct, and (3) the contractor’s obligation to prevent personal conflicts of interest in accordance with FAR 52.203-16, Preventing Personal Conflicts of Interest.

17. In an appendix to the OCI Plan identify the strategy (e.g., mitigation, limitation on future contracting, etc.) for resolving each OCI that is either identified in the solicitation or created by the requirements of the solicitation/contract and explain the effect of such strategy on performance of the contract. If using a firewall, explain how these actions will operate to successfully address the conflict without adversely affecting performance of the contract. (Note: Specific plans to limit future competition are reflected in the clause at NFS 1852.209-71, Limitation of Future Contracting.)

Remarks: The OCI Plan shall explicitly address mitigation including, but not limited to, the implementation of firewalls, from other Near Earth Orbit Network procurement activities.

Maintenance: The contractor shall review the OCI Plan on an annual basis or as directed by the contracting officer to revise the OCI Plan if necessary. Revisions are subject to Contracting Officer approval and shall be incorporated by change page or complete reissue.