RFP - 80GSFC26R0028 SMBA - Questions and Answers 1-9.pdf

PDF 110 KB Posted

Attached to
Near Earth Orbit Network Program's Sounder for Microwave-Based Applications
Solicitation number
80GSFC26R0028
Issued by

About this file

This is a Questions and Answers document for RFP 80GSFC26R0028 issued by NASA's Goddard Space Flight Center for the Sounder for Microwave-Based Applications (SMBA) contract. The document clarifies proposal preparation requirements and cost volume instructions through nine government-answered questions.

Key clarifications include: (1) offerors may expand the compliance matrix to map specific "shall" statements within Section L requirements; (2) all proposal volumes must be submitted as single searchable PDF files (compatible with Adobe Reader DC or 2017) with appropriate bookmarks, though Mission Suitability items and Cost/Price Volume Exhibits may be submitted in Excel when specified; (3) the government will add a two-page Common Estimating Basis Narrative section to address comparable program explanations separate from the two-page-per-WBS-Level-4 BOE requirement; (4) Enclosure 2, Exhibit 5 will be amended to remove profit/total cost breakouts for FFP pricing; (5) CLIN 003 (T&M) must be included in the Small Business Subcontracting Plan with no valid FAR Part 19 exclusion available; (6) T&M rate calculations are exempt from page count restrictions but the entire BOE section must be in PDF form; (7) non-significant subcontractors on CLIN 003 will have the prime's applicable loadings and fee applied and must be evaluated for reasonableness; (8) the "Item" numbers in Sections B and F correspond to "Delivery Item Nos." in the Section E Acceptance table; and (9) acceptance timelines for Flight Model 2 and Flight Model 3 hardware are defined in Section E clause GSFC 52.246-93 as "Post-Bench Acceptance Test at the Spacecraft/Mission Elements Contractor's Facility."

View the file

Other files

File Type Posted
RFP - 80GSFC26R0028 SMBA - Question and Answer 13-14.pdf PDF
Amnt 3 - RFP - 80GSFC26R0028 SMBA.pdf PDF
RFP - 80GSFC26R0028 SMBA - Question and Answer 12.pdf PDF
RFP - 80GSFC26R0028 SMBA - Question and Answer 10.pdf PDF
RFP - 80GSFC26R0028 SMBA - Question and Answer 11.pdf PDF
Amnt 2 - Enclosure 2 - Cost Exhibits 1- 8.xlsx XLSX spreadsheet
Amnt 2 - RFP - 80GSFC26R0028 SMBA.pdf PDF
Amnt 1 - RFP - 80GSFC26R0028 SMBA.pdf PDF
Amnt 1 - Attachment O - Milestone Payment Schedule_20260408.pdf PDF
Amnt 1 - Attachment C - Non-Technical Contract Data Requirements List_20260408.pdf PDF
Amnt 1 - DRD 6 - SCV Reporting.pdf PDF
Attachment O - Milestone Payment Schedule.pdf PDF
NS1-SMBA-SOW-0002D_NS1 SOW_03162026.pdf PDF
Enclosure 2 - Cost Exhibits 1- 8.xlsx XLSX spreadsheet
NS1-SMBA-CDRL-0001C_01152026.pdf PDF
DRD 2 - NASA C-SCRM Plan Questionnaire.xlsx XLSX spreadsheet
DRD 3 - CPIC DRD Template for IT Portfolio PPM Data Collection.xlsx XLSX spreadsheet
Attachment E - CSCRM Plan.pdf PDF
Attachment H - Requirements Statements List.pdf PDF
RFP Cover Letter - 80GSFC26R0028 SMBA.pdf PDF
Enclosure 5 - CWBS.pdf PDF
Attachment G - Small Business Subcontracting Plan.pdf PDF
Attachment B - Financial Management Reporting Requirements.pdf PDF
Attachment C - Non-Technical Contract Data Requirements List.pdf PDF
DRD 2 - Security Requirements for Unclassified IT Resources DRD w C-SCRM requirements.pdf PDF
NS1-SMBA-REQ-0001E_NS1 SMBA PRD_03112026.pdf PDF
Attachment N - Applicable Documents List.pdf PDF
Enclosure 4 - Financial Capability Disclosure.pdf PDF
DRD 4 - CITAR DRD.pdf PDF
DRD 4 - CITAR Report Template.xlsx XLSX spreadsheet
Attachment K - TM Rate Matrices.pdf PDF
DRD 3 - CPIC DRD.pdf PDF
Enclosure 3 - Past Performance Questionnaire.pdf PDF
Attachment D - OCI Plan.pdf PDF
Attachment L - Contractor Proposed Enhancements.pdf PDF
DRD 1 - OCI Plan.pdf PDF
Attachment F - Safety and Health Plan.pdf PDF
DRD 5 - CAIRIA DRD.pdf PDF
Attachment I - Government Furnished Property.pdf PDF
RFP - 80GSFC26R0028 SMBA.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Near Earth Orbit Network’s

Sounder for Microwave-Based Applications

Request for Proposal 80GSFC26R0028

Questions and Answers

Below are questions and answers related to the Sounder for Microwave-Based Applications (SMBA) Request for Proposal (RFP) 80GSFC26R0028. In the event of any discrepancy, the RFP provisions and contract terms (including all amendments) will take precedence.

Question Number Document Page

Number Section Paragraph Question / Comment

1 RFP -

80GSFC26R0028

SMBA

L-21 GSFC 52.215-

210 MISSION

SUITABILITY

PROPOSAL

INSTRUCTIONS

(c) The RFP instructions state "The offeror shall provide, at the beginning of this volume using the table provided below, a detailed compliance matrix that cross-references the offeror's numbering structure and corresponding volume page number with all requirements associated with each subfactor delineated in paragraph (d) below. The offeror may utilize its own unique numbering structure provided the compliance matrix provides clear traceability to each of the subfactor requirements described below."

Is it acceptable for offerors to expand the cross reference table to provide mapping to the specific "shall" within the associated Section L requirement paragraph?

Government Response:

Yes, this is acceptable. The matrix should result in a clear traceability between the vendor’s proposal and the Section L requirements.

2 RFP -

80GSFC26R0028

SMBA

L-9 GSFC 52.215-

201 PROPOSAL

PREPARATION -

GENERAL

INSTRUCTIONS

(a) (3) The RFP instructions require "Each proposal volume shall be submitted in a single searchable Adobe Portable Document Format (PDF) file". The volumes will include multiple attachments and appendices (e.g. OCI Plan, Small Business Subcontracting Plan, etc).

Can attachments/appendices be submitted as separate searchable pdf files?

Government Response:

Please follow the instructions including the exceptions stated in paragraph (a)(3):

Each proposal volume shall be submitted in a single searchable Adobe Portable Document Format (PDF) file (compatible with ADOBE Reader version DC or 2017), with appropriate bookmarks except for certain Mission Suitability items as specified in Volume II and Cost/Price Volume Exhibits in Volume III. Offerors shall submit Mission Suitability items in Excel when specified. Offerors shall submit all Cost/Price Volume Exhibits in Excel and the exhibits shall contain all formulas.

3 RFP -

80GSFC26R0028

SMBA

L-10 GSFC 52.215-

201 PROPOSAL

PREPARATION -

GENERAL

INSTRUCTIONS

(b) (1) RFP instructions include page limits on the Basis of Estimate at 2 pages per WBS Level 4 BOE. Our BOE narrative includes explanation on the comparable programs used in our estimates, Cost Estimating Relationships, etc. Are these explanations included in the page limits? If so, how are they counted as they are typically in an introduction section and not repeated in each BOE.

Based on (9) BASIS OF ESTIMATES (BOE) there is substantial detail that needs to be included for the BOE section of the cost volume including travel matrices, non-labor BOM details discussion of similar programs, etc. How can we meet the 2 pages per level 4 WBS requirement?

Government Response:

The Government will add a Common Estimating Basis Narrative limited to two pages. The specific instructions added will be, “Offerors may include a section in the Basis of Estimate titled “Common Estimating Basis Narrative” to describe common similar programs, standards, or other basis. This section shall not include any calculations which shall be included in the BOEs submitted at the lowest WBS Level (WBS Level 4).”

4 RFP -

SMBA

Enclosure 2 Cost Exhibit 1-8

L-39 Cost Volume Instructions

Cost Instruction

(c)(8) Enclosure 2 , Exhibit 5

FFP pricing does not break out Cost of Money and Profit.

The entire premise is that the contractor bears all cost risk.

Once agreed upon, the government pays that price regardless of what it actually costs to perform.

Recommend removing the Profit/Total Cost Breakouts

Government Response:

The Government will amend Enclosure 2, Exhibit 5, to remove the profit/total cost breakouts.

5 RFP -

80GSFC26R0028

SMBA

Enclosure 2 Cost Exhibit 1-8

L-32, L-42 Cost Volume Instructions

Mission Suitability

Subfactor C Cost instructions (f)(1)

Enclosure 2 , Exhibit 8

T&M CLINs are, by their nature, undefined in scope at proposal time. The exact hours are not known, the labor categories that will be required and whether all of the T&M Contract value will even be utilized. Additionally T&M CLINs tend to be more direct labor driven as opposed to material/ODC costs that can be subcontracted out to qualifying small businesses.

Recommend removing CLIN 003 from Small Business Plan.

Government Response:

There is no valid FAR Part 19 exclusion in this circumstance. Please consider the CLIN 0003 T&M ceiling value part of the overall contract value for the Small Business Subcontracting Plan.

6 RFP -

80GSFC26R0028

SMBA

L-42 Cost Volume Instructions

(e)(1) IDIQ T&M Rates

Solicitation requires that the calculation of Fully Burdened T&M rates shall be shown in the BOE section.

Please confirm that is acceptable that a separate Excel file for the T&M rate calculations can be submitted as part of the BOE section and is not part of the BOE page restriction.

Government Response:

The Government will amend the Request for Proposal to clarify that the calculation of the Fully Burdened T&M rates is exempt from the page count. The entire BOE section shall be in PDF form.

7 RFP -

80GSFC26R0028

SMBA

L-42 Cost Volume Instructions

(e)(1) IDIQ T&M Rates

Solicitation requires T&M rates only from Significant Subcontractors.

If T&M non-significant subcontractors are required during execution, please confirm that the Prime’s applicable loadings and fee would apply to their cost on CLIN 003.

Government Response:

Confirmed; however, non-significant subcontractors will still be evaluated for reasonableness before being included in the executed task order.

8 RFP -

SMBA

B-3 thru B-7, E-3 thru E-4, F-2

Section B CLIN Structure, Section E Acceptance Locations & Section F Delivery Schedule

GFSC

52.211-90, GFSC

52.246-93 &

GFSC

52.247-72

Section E, Clause GSFC 52.246-93 Acceptance includes a table which relies on the Deliverable Item No.

That numbering is based on the numbering from the table under Sections B & F, which is labelled as “Item No.”

Please confirm that these columns in Sections B & F represent the Deliverable Item nos. referenced in the Section E, Acceptance table.

Government Response:

Confirmed. The “Item” number cited in the Section B clause GSFC 52.211-90

SUPPLIES AND/OR

SERVICES TO BE

PROVIDED corresponds to the “Delivery Item No.” in the Section E clause GSFC

52.246-93 ACCEPTANCE.

9 RFP -

80GSFC26R0028

SMBA

E-1 Inspection and Acceptance

52.246-2

INSPECTION

OF

SUPPLIES –

FIXED

PRICE (AUG

1996)

52.246-2 INSPECTION OF

SUPPLIES – FIXED PRICE

(AUG 1996) applies to the CLIN 2, FFP Production CLINs. The FAR clause and the statement of work does not specify the acceptance timeline for F2 and F3 hardware deliveries.

Contractor recommends NASA acceptance of F2 and F3 hardware to be provided no later than sixty (60) calendar days after submittal of the DD250, Material Inspection Report to NASA. If the acceptance time line is not defined in the contract, it may impact Contractor's completion of milestone events and Contractors ability to receive payment for work performed.

Government Response:

No change. The Acceptance timelines for Flight Model 2 and Flight Model 3 are defined in Section E clause GSFC 52.246-93 as “Post- Bench Acceptance Test at the Spacecraft/Mission

Elements Contractor’s Facility.”