RFP - 80GSFC26R0028 SMBA - Question and Answer 13-14.pdf

PDF 65 KB Posted

Attached to
Near Earth Orbit Network Program's Sounder for Microwave-Based Applications
Solicitation number
80GSFC26R0028
Issued by

About this file

This document is a Questions and Answers clarification for RFP 80GSFC26R0028 regarding NASA's Sounder for Microwave-Based Applications (SMBA) contract. The file does not address specific products or services required, but rather clarifies contractual payment terms and cost allocation between two Contract Line Item Numbers (CLINs).

Question 13 addresses payment milestone timing, specifically whether the final 7% Performance-Based Payment (PBP) for each instrument is due upon successful completion of on-orbit commissioning and demonstration (satisfying 2009 and 2017 Milestone events in Attachment O), or deferred until the end of the five-year mission life. The Government confirmed that payment milestones 2009 and 2017 must be completed during the on-orbit commissioning timeframe, with the associated 7% payment becoming due at that time rather than at mission end.

Question 14 clarifies cost responsibility between CLIN 0001 (parts procurement for Flight Models 1-3) and CLIN 0002 (production through Bench Acceptance Test for Flight Models 2-3 at the contractor's facility). The Government established that all parts procurement costs, including rework and replacements for defective parts discovered during assembly or testing, will be charged to CLIN 0001. Conversely, all non-parts-related costs arising from contractor mishandling, production errors, assembly defects, or integration issues associated with Flight Models 2 and 3 will be charged to CLIN 0002.

View the file

Other files

File Type Posted
Amnt 3 - RFP - 80GSFC26R0028 SMBA.pdf PDF
RFP - 80GSFC26R0028 SMBA - Question and Answer 12.pdf PDF
RFP - 80GSFC26R0028 SMBA - Question and Answer 10.pdf PDF
RFP - 80GSFC26R0028 SMBA - Question and Answer 11.pdf PDF
Amnt 2 - Enclosure 2 - Cost Exhibits 1- 8.xlsx XLSX spreadsheet
RFP - 80GSFC26R0028 SMBA - Questions and Answers 1-9.pdf PDF
Amnt 2 - RFP - 80GSFC26R0028 SMBA.pdf PDF
Amnt 1 - RFP - 80GSFC26R0028 SMBA.pdf PDF
Amnt 1 - Attachment O - Milestone Payment Schedule_20260408.pdf PDF
Amnt 1 - Attachment C - Non-Technical Contract Data Requirements List_20260408.pdf PDF
Amnt 1 - DRD 6 - SCV Reporting.pdf PDF
Attachment O - Milestone Payment Schedule.pdf PDF
NS1-SMBA-SOW-0002D_NS1 SOW_03162026.pdf PDF
Enclosure 2 - Cost Exhibits 1- 8.xlsx XLSX spreadsheet
NS1-SMBA-CDRL-0001C_01152026.pdf PDF
DRD 2 - NASA C-SCRM Plan Questionnaire.xlsx XLSX spreadsheet
DRD 3 - CPIC DRD Template for IT Portfolio PPM Data Collection.xlsx XLSX spreadsheet
Attachment E - CSCRM Plan.pdf PDF
Attachment H - Requirements Statements List.pdf PDF
RFP Cover Letter - 80GSFC26R0028 SMBA.pdf PDF
Enclosure 5 - CWBS.pdf PDF
Attachment G - Small Business Subcontracting Plan.pdf PDF
Attachment B - Financial Management Reporting Requirements.pdf PDF
Attachment C - Non-Technical Contract Data Requirements List.pdf PDF
DRD 2 - Security Requirements for Unclassified IT Resources DRD w C-SCRM requirements.pdf PDF
NS1-SMBA-REQ-0001E_NS1 SMBA PRD_03112026.pdf PDF
Attachment N - Applicable Documents List.pdf PDF
Enclosure 4 - Financial Capability Disclosure.pdf PDF
DRD 4 - CITAR DRD.pdf PDF
DRD 4 - CITAR Report Template.xlsx XLSX spreadsheet
Attachment K - TM Rate Matrices.pdf PDF
DRD 3 - CPIC DRD.pdf PDF
Enclosure 3 - Past Performance Questionnaire.pdf PDF
Attachment D - OCI Plan.pdf PDF
Attachment L - Contractor Proposed Enhancements.pdf PDF
DRD 1 - OCI Plan.pdf PDF
Attachment F - Safety and Health Plan.pdf PDF
DRD 5 - CAIRIA DRD.pdf PDF
Attachment I - Government Furnished Property.pdf PDF
RFP - 80GSFC26R0028 SMBA.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Near Earth Orbit Network’s

Sounder for Microwave-Based Applications

Request for Proposal 80GSFC26R0028

Questions and Answers 13 and 14

Below are questions and answers related to the Sounder for Microwave-Based Applications (SMBA) Request for Proposal (RFP) 80GSFC26R0028. In the event of any discrepancy, the RFP provisions and contract terms (including all amendments) will take precedence.

13. Our understanding is that successful completion of on-orbit commissioning and demonstration meets the on-orbit performance requirements satisfying the 2009 and 2017 Milestone events in Attachment O, and that the associated 7% payment for each instrument becomes due at that time.

a. Could you please confirm that this understanding is correct, and that NASA does not intend to defer the final 7% PBP until the end of the five-year mission life?

Government Response: The Government expects the contractor to complete payment milestones 2009 and 2017 along with the associated completion criteria during the timeframe of on-orbit commissioning, not the end of the five-year mission life.

14. CLIN 0001 encompasses the procurement of parts for Flight Models 1-3, while CLIN 0002 covers the Production through Bench Acceptance Test (BAT) for Flight Models 2 and 3 at the Contractor’s facility. Regarding the delineation of cost responsibility between these CLINs, the Government’s clarification is requested on the following scenarios:

a. Should any parts procured under CLIN 0001 later be found to be defective (e.g., latent defects not discoverable upon receipt/inspection) during assembly or testing under CLIN 0002 would the issues be addressed under CLIN 0001 cost-reimbursable effort (including any replacement parts, rework, or recovery actions directly related to the defective part itself)?

Government Response: All parts procurement costs, including re-work or replacements, will occur under CLIN 0001.

b. Conversely, should any costs arising from contractor mishandling, production errors, assembly defects, or integration issues under CLIN 0002 be the contractor’s responsibility under CLIN 0002?

Government Response: All non-parts-related costs associated with Flight Models 2 and 3 will occur under CLIN 0002.

File details come from the government source that posted it. Updated .