Contract Att15 - Checkpoint Deployment IMS_Example_01.26.2026.pdf

PDF 120 KB Posted

Attached to
Screening Equipment Deployment Services (SEDS) - Checkpoint (CP)
Solicitation number
70T04026R7672N005
Issued by

About this file

This is a project schedule dashboard for the AIT IMS-2 contract (241016), detailing deployment timelines and tasks across multiple airport locations.

The project encompasses deployment activities at two primary sites: Atlanta Hartsfield-Jackson International Airport (ATL) and Dallas/Fort Worth International Airport (DAL). The overall deployment period spans from September 23, 2025, through May 1, 2026. The ATL deployment is scheduled for 143 days (September 23, 2025 to April 15, 2026) and includes 17 systems installation, while the DAL deployment runs 150 days (September 30, 2025 to May 1, 2026) with 4 systems installation. Key milestones include airport kickoff calls, site surveys, concept drawing development and TSA reviews, Security Improvement Plan (SIP) and Integrated Functional Configuration (IFC) submissions, ReMag approval, permitting processes, site preparation, and the actual AIT (Advanced Imaging Technology) equipment removal and replacement activities. The ATL deployment features two installation teams: Team 1 installing 8 units over 16 days and Team 2 installing 9 units over 20 days, both beginning February 5, 2026. Each installation involves sequential removal of Leidos AIT equipment and installation of R&S equipment at individual units over one-day cycles. Critical path items include TSA concept drawing reviews (10 days for ATL, 9 days for DAL), permitting processes (53 days for ATL, 34 days for DAL), and operator differences training (20 days) occurring prior to ATL go-live on March 26, 2026. All installations are scheduled complete by March 20, 2026, with punchlist and record drawings to be finalized by April 15, 2026 for ATL and May 1, 2026 for DAL.

View the file

Other files

File Type Posted
SEDS CP RFP Questions and Answers.4.pdf PDF
RFP Att2 - CP SEDS Pricing Sheet_Amendment 3.xlsx XLSX spreadsheet
RFP Att2 - CP SEDS Pricing Sheet_Amendment 3.xlsx XLSX spreadsheet
SEDS CP RFP Questions and Answers.3.pdf PDF
SEDS CP RFP - Amendment 3 SF30.pdf PDF
SEDS CP RFP 70T04026R7672N005 Amendment 3 clean.docx DOCX document
SEDS CP RFP 70T04026R7672N005 Amendment 3 track changes.docx DOCX document
SEDS CP RFP Questions and Answers.2.pdf PDF
SEDS CP RFP - Amendment 2 SF30.pdf PDF
RFP Att2 - CP SEDS Pricing Sheet_amendment 2.xlsx XLSX spreadsheet
RFP Att2 - CP SEDS Pricing Sheet_amendment 1.xlsx XLSX spreadsheet
SEDS CP RFP 70T04026R7672N005 Amendment 1 clean.docx DOCX document
SEDS CP RFP - Amendment 1 SF30.pdf PDF
SEDS CP RFP 70T04026R7672N005 Amendment 1 track changes.docx DOCX document
RFP Att3 - CP SEDS II Program Management Amendment 1.docx DOCX document
SEDS CP RFP Questions and Answers.pdf PDF
RFP Att3 - CP SEDS II Program Management.docx DOCX document
RFP Att3 - CP SEDS II Program Management.docx DOCX document
SEDS CP RFP 70T04026R7672N005.pdf PDF
Contract Att12 - CDRL B001- Daily Site Report_08.11.2025.xlsx XLSX spreadsheet
Contract Att06 - CDRL D001 - CT De-install Decommission Checklist_05.28.2025.xlsx XLSX spreadsheet
Contract Att01 - CDRL D001 - AIT-1 and AIT-2 - Leidos Decommission Checklist_05.21.2025.xlsx XLSX spreadsheet
Contract Att07 - CDRL D001 - ETD - 500DT Install - De-Installation Checklist_05.19.2025.xlsx XLSX spreadsheet
Contract Att17 - ITAR_Terms-ConditionsTemplate_11.17.2025.docx DOCX document
RFP Att4 -DHS Subcontracting Plan Review Checklist.pdf PDF
Contract Att11 - CDRL A004 - Weekly Status Report (WSR)_08.11.2025.xlsx XLSX spreadsheet
Contract Att08 - CDRL D001 - ETD - QSB220 De-Install - Install Checklist_05.19.2025.xlsx XLSX spreadsheet
Contract Att04 - CDRL D001 - BLS - CEIA EMA-MS Decommission Checklist_05.21.2025.xlsx XLSX spreadsheet
Contract Att13 - CDRL B006 - Closeout Report_08.11.2025.xlsx XLSX spreadsheet
Questions on SEDS CP RFP.xlsx XLSX spreadsheet
RFP Att1 - SEDS CP SF-1449.pdf PDF
Contract Att09 - CDRL D001 - WTMD - CEIA Decommission Checklist_05.19.2025.xlsx XLSX spreadsheet
RFP Att2 - CP SEDS Pricing Sheet_04.06.2026.xlsx XLSX spreadsheet
Contract Att10 - CDRL B002 - PSP Site Survey_08.11.2025.xlsx XLSX spreadsheet
Contract Att03- CDRL D001 - AT Decommission Checklist_05.19.2025.xlsx XLSX spreadsheet
Contract Att05 - CDRL D001 - BLS - Smiths Responder Decomm Checklist_05.21.2025.xlsx XLSX spreadsheet
Contract Att02 - CDRLD001 - AIT - RS Decommission Checklist _08.18.2025.xlsx XLSX spreadsheet
Contract Att16 - DSD Acronym List 03-11-26.docx DOCX document
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Dashboard - Team/Project

Task Name % Complete Duration Predecessors Successors Start Finish Actual Start Actual Finish Baseline Start Baseline Finish SEDS POC Airport Checkpoint Lane Actual Quantity Planned Quantity

Asset Serial Number

Vendor Model

1 Deployment Example 0% 155 days Tue 9/23/25 Fri 5/1/26 Tue 9/23/25 NA Tue 2/21/12 Thu 8/31/17 0 0 hrs 0 0 0 0 0 2 Deployment Contract Award 0% 0 days 4,68 Tue 9/30/25 Tue 9/30/25 NA NA NA NA 0 0 hrs 0 0 0 0 0 3 Deployment ATL 0% 143 days Tue 9/23/25 Wed 4/15/26 Tue 9/23/25 NA Thu 2/14/19 Thu 4/28/22 0 0 hrs 0 0 0 0 0 4 Airport Kickoff Call Week of Dates 0% 1 day 2 5 Tue 9/23/25 Tue 9/30/25 Tue 9/23/25 NA NA NA 0 0 hrs 0 0 0 0 0 5 Site Survey Visit Week of Dates 0% 3 days 4 6 Tue 9/30/25 Fri 10/3/25 Tue 9/30/25 NA NA NA 0 0 hrs 0 0 0 0 0 6 Develop Submit Concept Drawings 0% 9 days 5 7 Mon 10/6/25 Fri 10/17/25 Mon 10/6/25 NA NA NA 0 0 hrs 0 0 0 0 0 7 TSA Reviews Concept Drawings 0% 10 days 6 8 Mon 10/20/25 Fri 10/31/25 NA NA NA NA 0 0 hrs 0 0 0 0 0 8 Concept Drawings Approved 0% 0 days 7 9 Fri 10/31/25 Fri 10/31/25 NA NA NA NA 0 0 hrs 0 0 0 0 0 9 Develop and Submit SIP 0% 5 days 8 10,12,21 Mon 11/3/25 Fri 11/7/25 NA NA NA NA 0 0 hrs 0 0 0 0 0 10 Develop and Submit IFCs 0% 5 days 9 11 Mon 11/10/25 Mon 11/17/25 NA NA NA NA 0 0 hrs 0 0 0 0 0 11 TSA Reviews SIP IFCs 0% 5 days 10 15 Tue 11/18/25 Mon 11/24/25 NA NA NA NA 0 0 hrs 0 0 0 0 0 12 Develop and Submit ReMag 0% 2 days 9 13 Mon 11/10/25 Wed 11/12/25 NA NA NA NA 0 0 hrs 0 0 0 0 0 13 TSA Reviews and Approves ReMAG 0% 5 days 12 20 Thu 11/13/25 Wed 11/19/25 NA NA NA NA 0 0 hrs 0 0 0 0 0 14 Permitting Process 0% 53 days Tue 11/25/25 Mon 2/9/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 15 Develop Submit Permit Application 0% 11 days 11 17,16 Tue 11/25/25 Wed 12/10/25 NA NA NA NA 0 0 hrs 0 0 0 0 0 16 Initial Permit Submitted 0% 0 days 15 Wed 12/10/25 Wed 12/10/25 NA NA NA NA 0 0 hrs 0 0 0 0 0 17 Atlanta Department of Aviation Reviews/Comments 0% 10 days 15 18 Thu 12/11/25 Wed 12/24/25 NA NA NA NA 0 0 hrs 0 0 0 0 0

18 TSA Reviews/Adjudicates Comments 0% 10 days 17 19 Fri 12/26/25 Thu 1/8/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 19 Atlanta Department of Aviation Reviews/Approves

Permit 0% 22 days 18 20 Fri 1/9/26 Mon 2/9/26 NA NA NA NA 0 0 hrs 0 0 0 0 0

20 All Drawings and Permits Complete 0% 0 days 13,19 Mon 2/9/26 Mon 2/9/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 21 Site Prep 0% 21 days 9 22 Wed 1/7/26 Wed 2/4/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 22 Site Prep Complete 0% 0 days 21 23 Wed 2/4/26 Wed 2/4/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 23 Pre Deployment Go/No Go 0% 0 days 22 26,43 Wed 2/4/26 Wed 2/4/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 24 ATL Deployment 17 Systems 0% 20 days Thu 2/5/26 Wed 3/4/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 25 Team 1 (Install 8 Units) 0% 16 days 65,63 Thu 2/5/26 Thu 2/26/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 26 Leidos AIT Removed 0% 1 day 23 27 Thu 2/5/26 Thu 2/5/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 27 R&S AIT Installed 0% 1 day 26 28 Fri 2/6/26 Fri 2/6/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 28 Leidos AIT Removed 0% 1 day 27 29 Mon 2/9/26 Mon 2/9/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 29 R&S AIT Installed 0% 1 day 28 30 Tue 2/10/26 Tue 2/10/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 30 Leidos AIT Removed 0% 1 day 29 31 Wed 2/11/26 Wed 2/11/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 31 R&S AIT Installed 0% 1 day 30 32 Thu 2/12/26 Thu 2/12/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 32 Leidos AIT Removed 0% 1 day 31 33 Fri 2/13/26 Fri 2/13/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 33 R&S AIT Installed 0% 1 day 32 34 Mon 2/16/26 Mon 2/16/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 34 Leidos AIT Removed 0% 1 day 33 35 Tue 2/17/26 Tue 2/17/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 35 R&S AIT Installed 0% 1 day 34 36 Wed 2/18/26 Wed 2/18/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 36 Leidos AIT Removed 0% 1 day 35 37 Thu 2/19/26 Thu 2/19/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 37 R&S AIT Installed 0% 1 day 36 38 Fri 2/20/26 Fri 2/20/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 38 Leidos AIT Removed 0% 1 day 37 39 Mon 2/23/26 Mon 2/23/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 39 R&S AIT Installed 0% 1 day 38 40 Tue 2/24/26 Tue 2/24/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 40 Leidos AIT Removed 0% 1 day 39 41 Wed 2/25/26 Wed 2/25/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 41 R&S AIT Installed 0% 1 day 40 Thu 2/26/26 Thu 2/26/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 42 Team 2 (Install 9 Units) 0% 20 days 63 Thu 2/5/26 Wed 3/4/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 43 Leidos AIT Removed 0% 1 day 23 44 Thu 2/5/26 Thu 2/5/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 44 R&S AIT Installed 0% 1 day 43 45 Fri 2/6/26 Fri 2/6/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 45 Leidos AIT Removed 0% 1 day 44 46 Mon 2/9/26 Mon 2/9/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 46 R&S AIT Installed 0% 1 day 45 47 Tue 2/10/26 Tue 2/10/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 47 Leidos AIT Removed 0% 1 day 46 48 Wed 2/11/26 Wed 2/11/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 48 R&S AIT Installed 0% 1 day 47 49 Thu 2/12/26 Thu 2/12/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 49 Leidos AIT Removed 0% 1 day 48 50 Fri 2/13/26 Fri 2/13/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 50 R&S AIT Installed 0% 1 day 49 51 Mon 2/16/26 Mon 2/16/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 51 Leidos AIT Removed 0% 1 day 50 52 Tue 2/17/26 Tue 2/17/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 52 R&S AIT Installed 0% 1 day 51 53 Wed 2/18/26 Wed 2/18/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 53 Leidos AIT Removed 0% 1 day 52 54 Thu 2/19/26 Thu 2/19/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 54 R&S AIT Installed 0% 1 day 53 55 Fri 2/20/26 Fri 2/20/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 55 Leidos AIT Removed 0% 1 day 54 56 Mon 2/23/26 Mon 2/23/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 56 R&S AIT Installed 0% 1 day 55 57 Tue 2/24/26 Tue 2/24/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 57 Leidos AIT Removed 0% 1 day 56 58 Wed 2/25/26 Wed 2/25/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 58 R&S AIT Installed 0% 1 day 57 59 Thu 2/26/26 Thu 2/26/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 59 Leidos AIT Removed 0% 1 day 58 60 Fri 2/27/26 Fri 2/27/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 60 R&S AIT Installed 0% 1 day 59 61 Mon 3/2/26 Mon 3/2/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 61 Leidos AIT Removed 0% 1 day 60 62 Tue 3/3/26 Tue 3/3/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 62 R&S AIT Installed 0% 1 day 61 Wed 3/4/26 Wed 3/4/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 63 ATL Complete 0% 0 days 25,42 64,66,97 Wed 3/4/26 Wed 3/4/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 64 Punchlist / Record Drawings Complete 0% 30 days 63 Thu 3/5/26 Wed 4/15/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 65 Operator Differences Training 0% 20 days 25 66 Fri 2/27/26 Thu 3/26/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 66 Go Live 0% 0 days 63,65 Thu 3/26/26 Thu 3/26/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 67 Deployment DAL 0% 150 days Tue 9/30/25 Fri 5/1/26 Tue 9/30/25 NA Thu 2/14/19 Thu 4/28/22 0 0 hrs 0 0 0 0 0 68 Airport Kickoff Call Week of Dates 0% 1 day 2 69 Tue 9/30/25 Tue 9/30/25 Tue 9/30/25 NA NA NA 0 0 hrs 0 0 0 0 0 69 Site Survey Visit Week of Dates 0% 3 days 68 70 Tue 10/21/25 Thu 10/23/25 Tue 10/21/25 NA NA NA 0 0 hrs 0 0 0 0 0 70 Develop Submit Concept Drawings 0% 8 days 69 71 Fri 10/24/25 Tue 11/4/25 NA NA NA NA 0 0 hrs 0 0 0 0 0 71 TSA Reviews Concept Drawings 0% 9 days 70 72 Wed 11/5/25 Tue 11/18/25 NA NA NA NA 0 0 hrs 0 0 0 0 0 72 Concept Drawings Approved 0% 0 days 71 73 Tue 11/18/25 Tue 11/18/25 NA NA NA NA 0 0 hrs 0 0 0 0 0 73 Develop and Submit SIP 0% 10 days 72 74 Wed 11/19/25 Wed 12/3/25 NA NA NA NA 0 0 hrs 0 0 0 0 0

241016 - AIT IMS-2

ID Dashboard - Team/Project

Task Name % Complete Duration Predecessors Successors Start Finish Actual Start Actual Finish Baseline Start Baseline Finish SEDS POC Airport Checkpoint Lane Actual Quantity Planned Quantity

Asset Serial Number

Vendor Model

74 Develop and Submit IFCs 0% 10 days 73 75 Thu 12/4/25 Wed 12/17/25 NA NA NA NA 0 0 hrs 0 0 0 0 0 75 TSA Reviews SIP IFCs 0% 5 days 74 79 Thu 12/18/25 Wed 12/24/25 NA NA NA NA 0 0 hrs 0 0 0 0 0 76 Submit ReMag 0% 1 day 77,80 Mon 2/2/26 Mon 2/2/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 77 Receive Approved ReMag 0% 5 days 76 81 Tue 2/3/26 Mon 2/9/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 78 Permitting Process 0% 34 days Tue 1/6/26 Fri 2/20/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 79 Develop Submit Permit Application 0% 15 days 75 Tue 1/6/26 Mon 1/26/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 80 Receive Permit 0% 14 days 76 81 Tue 2/3/26 Fri 2/20/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 81 All Drawings and Permits Complete 0% 0 days 77,80 82 Fri 2/20/26 Fri 2/20/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 82 Site Prep 0% 11 days 81 83 Mon 2/23/26 Mon 3/9/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 83 Site Prep Complete 0% 0 days 82 84 Mon 3/9/26 Mon 3/9/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 84 Pre Deployment Go/No Go 0% 0 days 83 86 Mon 3/9/26 Mon 3/9/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 85 DAL Deployment 4 Systems 0% 9 days Tue 3/10/26 Fri 3/20/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 86 Leidos AIT Removed 0% 1 day 84 87 Tue 3/10/26 Tue 3/10/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 87 R&S AIT Installed 0% 1 day 86 88 Wed 3/11/26 Wed 3/11/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 88 Leidos AIT Removed 0% 1 day 87 89 Thu 3/12/26 Thu 3/12/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 89 R&S AIT Installed 0% 1 day 88 90 Fri 3/13/26 Fri 3/13/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 90 Leidos AIT Removed 0% 1 day 89 91 Mon 3/16/26 Mon 3/16/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 91 R&S AIT Installed 0% 1 day 90 92 Tue 3/17/26 Tue 3/17/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 92 Leidos AIT Removed 0% 1 day 91 93 Wed 3/18/26 Wed 3/18/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 93 R&S AIT Installed 0% 1 day 92 94 Thu 3/19/26 Thu 3/19/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 94 DAL Complete 0% 1 day 93 95,96,97 Fri 3/20/26 Fri 3/20/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 95 Punchlist / Record Drawings Complete 0% 30 days 94 Mon 3/23/26 Fri 5/1/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 96 Go Live 0% 0 days 94 Fri 3/20/26 Fri 3/20/26 NA NA NA NA 0 0 hrs 0 0 0 0 0 97 All installs complete 0% 0 days 94,63 Fri 3/20/26 Fri 3/20/26 NA NA NA NA 0 0 hrs 0 0 0 0 0

241016 - AIT IMS-2

File details come from the government source that posted it. Updated .