Contract Att13 - CDRL B006 - Closeout Report_08.11.2025.xlsx

XLSX spreadsheet 94 KB Posted

Attached to
Screening Equipment Deployment Services (SEDS) - Checkpoint (CP)
Solicitation number
70T04026R7672N005
Issued by

About this file

This is a Checkpoint Deployment Closeout Report template (CDRL B006) designed for the Transportation Security Administration (TSA) to document the completion and handover of screening equipment deployment projects at airport checkpoints. The form is contractor-filled and serves as the final project closure documentation for the Screening Equipment Deployment Services (SEDS) contract (Solicitation 70T04026R7672N005).

The closeout report comprises four primary sections with standardized checklists: Design Layout Description validates that all computed tomography/X-ray machines, advanced imaging technology, explosive trace detection/baggage level screening/advanced video systems, checkpoint advanced technology/bulk physical screening, and walk-through metal detector placements conform to approved TSA drawings and specifications, including electrical and data infrastructure; FF&E (Furniture, Fixtures, and Equipment) and TSE (Tunnel Screening Equipment) Description verifies the correct quantities of roller tables, removal of dunnage, proper installation per structural drawings, and status of metal detector retrieval systems; Site Restoration Description confirms the checkpoint is restored to pre-construction condition or better, including floor repairs, camera angle verification, damage assessment to ceilings, doors, walls and other structures, and proper dunnage disposal; and Shipping Description documents that removed equipment is crated per original equipment manufacturer requirements with DD-1149 forms completed and submitted to the TSA Logistics Center. A supplementary Specific Punch-List section allows tracking of remaining items requiring completion, including verification that walk-through metal detectors do not produce false alarms during normal screening operations. The form requires sign-off from the contractor site lead, TSA representative, and airport authority representative, with photographic documentation of the checkpoint front, rear, and computed tomography exit areas.

View the file

Other files

File Type Posted
SEDS CP RFP Questions and Answers.4.pdf PDF
RFP Att2 - CP SEDS Pricing Sheet_Amendment 3.xlsx XLSX spreadsheet
RFP Att2 - CP SEDS Pricing Sheet_Amendment 3.xlsx XLSX spreadsheet
SEDS CP RFP Questions and Answers.3.pdf PDF
SEDS CP RFP - Amendment 3 SF30.pdf PDF
SEDS CP RFP 70T04026R7672N005 Amendment 3 clean.docx DOCX document
SEDS CP RFP 70T04026R7672N005 Amendment 3 track changes.docx DOCX document
SEDS CP RFP Questions and Answers.2.pdf PDF
SEDS CP RFP - Amendment 2 SF30.pdf PDF
RFP Att2 - CP SEDS Pricing Sheet_amendment 2.xlsx XLSX spreadsheet
RFP Att2 - CP SEDS Pricing Sheet_amendment 1.xlsx XLSX spreadsheet
SEDS CP RFP 70T04026R7672N005 Amendment 1 clean.docx DOCX document
SEDS CP RFP - Amendment 1 SF30.pdf PDF
SEDS CP RFP 70T04026R7672N005 Amendment 1 track changes.docx DOCX document
RFP Att3 - CP SEDS II Program Management Amendment 1.docx DOCX document
SEDS CP RFP Questions and Answers.pdf PDF
RFP Att3 - CP SEDS II Program Management.docx DOCX document
RFP Att3 - CP SEDS II Program Management.docx DOCX document
SEDS CP RFP 70T04026R7672N005.pdf PDF
Contract Att15 - Checkpoint Deployment IMS_Example_01.26.2026.pdf PDF
Contract Att12 - CDRL B001- Daily Site Report_08.11.2025.xlsx XLSX spreadsheet
Contract Att06 - CDRL D001 - CT De-install Decommission Checklist_05.28.2025.xlsx XLSX spreadsheet
Contract Att01 - CDRL D001 - AIT-1 and AIT-2 - Leidos Decommission Checklist_05.21.2025.xlsx XLSX spreadsheet
Contract Att07 - CDRL D001 - ETD - 500DT Install - De-Installation Checklist_05.19.2025.xlsx XLSX spreadsheet
Contract Att17 - ITAR_Terms-ConditionsTemplate_11.17.2025.docx DOCX document
RFP Att4 -DHS Subcontracting Plan Review Checklist.pdf PDF
Contract Att11 - CDRL A004 - Weekly Status Report (WSR)_08.11.2025.xlsx XLSX spreadsheet
Contract Att08 - CDRL D001 - ETD - QSB220 De-Install - Install Checklist_05.19.2025.xlsx XLSX spreadsheet
Contract Att04 - CDRL D001 - BLS - CEIA EMA-MS Decommission Checklist_05.21.2025.xlsx XLSX spreadsheet
Questions on SEDS CP RFP.xlsx XLSX spreadsheet
RFP Att1 - SEDS CP SF-1449.pdf PDF
Contract Att09 - CDRL D001 - WTMD - CEIA Decommission Checklist_05.19.2025.xlsx XLSX spreadsheet
RFP Att2 - CP SEDS Pricing Sheet_04.06.2026.xlsx XLSX spreadsheet
Contract Att10 - CDRL B002 - PSP Site Survey_08.11.2025.xlsx XLSX spreadsheet
Contract Att03- CDRL D001 - AT Decommission Checklist_05.19.2025.xlsx XLSX spreadsheet
Contract Att05 - CDRL D001 - BLS - Smiths Responder Decomm Checklist_05.21.2025.xlsx XLSX spreadsheet
Contract Att02 - CDRLD001 - AIT - RS Decommission Checklist _08.18.2025.xlsx XLSX spreadsheet
Contract Att16 - DSD Acronym List 03-11-26.docx DOCX document
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attendees

Checkpoint Final Deployment Closeout
Contractor:
Site Lead (Name/Phone/email):
Airport Name and Code:
Location (Terminal/Checkpoint/Lane(s)):
Local TSA POC (Name/Phone/Email):
Airport Authority Representative POC (Name/Phone/Email):
Project description (short summary):
Close Out Date:
NameOrganization / TitlePhoneEmail

Version 1.0 Current as of: 3/13/25

&9&K000000Leidos Proprietary&1#

&"Times New Roman,Regular"Page &P of &N

&1#

Standard Checklist

Checkpoint Deployment Closeout Documentation (Form to be filled out by the contractor)
Standard Checklist
Contractor:
Site Lead (Name/Phone/email):
Airport Name and Code:
Location (Terminal/Checkpoint/Lane(s)):
Local TSA POC (Name/Phone/Email):
Airport Authority Representative POC (Name/Phone/Email):
Project description (short summary):
Close Out Date:
Design Layout
DescriptionYesNoVerified by site leadDateIf "No" provide short explanation
All CT/X-Ray dimensions are within acceptable specifications of the location on the drawings (all changes must be approved by TSA HQ design)
All AIT placements are within acceptable specifications of the location on the drawings (all changes must be approved by TSA HQ design team)
All ETD/BLS/AVS stations are within acceptable specifications of the location on the drawings (all changes must be approved by TSA HQ design team)
All CAT/BPS placements are within acceptable specifications of the location on the drawings (all changes must be approved by TSA HQ design team)
All WTMD placements are within acceptable specifications of the location on the drawings. (all changes must be approved by TSA HQ design team)
All TSE is within the approved TSE maintenance zone(s)
All new electrical/data poke through dimensions are within acceptable tolerances of the E-002 drawing (electrical specs)
Are all data ports in place and connected (functional) to the TSA network?
Private Screening rooms are sized approprietly and located within acceptable specifications of the location on the drawings (if applicable)
Is the existing TSE on backup or emergency power?
Is the newly installed TSE on backup or emergency power?
New & relocated FF&E have been placed per the associated architectural drawings
Red line drawings were submitted for any design layout change?
FF&E and TSE
DescriptionYesNoVerified by site leadDateIf "No" provide short explanation
The number of new roller tables matches that shown in the associated architectural drawings (all changes must be approved by TSA HQ design team)
The number of relocated roller tables matches that shown in the associated architectural drawings (all changes must be approved by TSA HQ design team)
All disposable dunnage has been removed from the checkpoint
Site Lead installed all FF&E items according to structural drawings. Please note any missing items or pending items
Local riggers staging facility (RSF) has been closed-out
Was an MDR(s) installed/present?
If MDR was installed, note: Condition, RH/LH, re-used or redeployed, and/or was it disposed of locally
Site Restoration
DescriptionYesNoVerified by site leadDateIf "No" provide short explanation
Site has been restored to pre-construction condition or better
Are there any pending or missing infrastructure (electrical/data) requirements
All floor repairs have been completed to pre-construction condition or better. Airport Authority must approve the floor restoration
All camera angles have been returned and verified by the airport authority or responsible party with the concurrence of local TSA (as applicable)
All excess dunnage has been removed and disposed off properly from the checkpoint and RSF
Equipment rigging path has been inspected for damage (pre and post). For post damage, please specify location and resolution. Please provide photos
Any damaged ceilings have been repaired
Any damaged doors have been repaired
Any damaged walls have been repaired
Any other damaged structure?
Shipping
DescriptionYesNoVerified byDateIf "No" provide short explanation
All removed TSE have been packaged/crated (as applicable) in accordance with OEM requirements. Provide photos
Crate(s)/Shipping containers return to TSALC with approval from the DSD Tech Lead.
DD-1149 has been completed and provided to TSA for all removed TSE
All TSE has been shipped to TSALC or other approved location per the corresponding DD-1149
All approved FF&E has been shipped to the TSALC with a corresponding DD-1149
Duress Alarms
DescriptionYesNoQtyDateComments
Are all required duress buttons installed and functional or relocated and tested at the checkpoint?
Is there an airport required panic alarm? Were the additional panic alarm buttons installed?
Is the TSA duress alarm system integrated with the airports duress alarm system?
Does this location have backup power for the duress alarm system. Is it working properly?
Total number of new buttons delivered
Other Items
DescriptionYesNoVerified byDateIf "No" provide short explanation
Did the contractor observe any dirty power throughout the airport?
Signatures
Deployment and Sustainment (DC) NameDeployment and Sustainment (DC) SignatureDate

Contractor Representative Name Contractor Representative Signature Date

TSA Representative Name TSA Representative Signature Date

Airport Representative Name Airport Representative Signature Date

Front of checkpointFront of checkpoint
Insert pictures hereInsert pictures here
Rear of CheckpointExit of CT
Insert pictures hereInsert pictures here

Page &P of &N

Specific Punch-list

Checkpoint Deployment Punch-list (Form to be filled out by contractor)
Airport Specific Final Punch-list
Contractor:
Site Lead (Name/Phone/email):
Airport Name and Code:
Location (Terminal/Checkpoint/Lane(s):
Local TSA POC (Name/Phone/Email):
Airport Aurhority Representative POC (Name/Phone/Email):
Project description (short summary):
Close Out Date:
<All items listed must be the responsibility of the contractor, do not record items beyond the scope of the project>Initial/ Date Following Completion of Each Item Listed
Item #DescriptionDate IdentifiedEstimated Completion DateResponsible Party (Owner)Contractor's Intials and Date When completedTSA/Airport's Initial and Date When completed
1WTMD does not produce ghost alarms during normal passanger screening hours and varying times of day (if applicable)
2
3
4
5
6
7
8
9
10

<The following signatures confirm agreement that the list of items recorded above is complete and that all are the responsibility of the SL Team>

Contractor Representative Name Contractor Representative Signature Date

TSA Representative NameTSA Representative SignatureDate
If applicable

Airport Representative Name Airport Representative Signature Date

<Provide photos that would be helpful in understanding punch list item and / or correction>
Item #Insert Punch-list Item Pictures When ApplicableAdditional Comments

image1.jpeg image11.png image14.png