Contract Att12 - CDRL B001- Daily Site Report_08.11.2025.xlsx

XLSX spreadsheet 98 KB Posted

Attached to
Screening Equipment Deployment Services (SEDS) - Checkpoint (CP)
Solicitation number
70T04026R7672N005
Issued by

About this file

This file is a Contractor Delivery Requirement List (CDRL) template for daily site progress reporting on the Screening Equipment Deployment Services (SEDS) - Checkpoint contract. The template establishes requirements for contractors to submit daily site reports no later than 7:00 AM local time for all regions, beginning once Integrated Product Team (IPT) calls commence unless otherwise directed by the Regional Deployment Manager. These reports are critical to the Program Office's ability to accurately track and update program status.

The daily site report template captures essential project information including site identification (airport code, name, task order, date), site points of contact, TSA HQ/DC points of contact, and ReMAG numbers with associated dates (ordered, received, started, completed). Reports must detail accomplishments and activities performed by contractor personnel with start and end times, planned activities for the following day, identified risks with descriptions and recommendations, and issues or variances to the Site Installation Plan (SIP) with contributing factors. The template also tracks cumulative system installation locations, technology serial numbers, TSA barcodes, and supporting ancillary equipment dates (SAT and RAD). Additionally, the form requires documentation of key milestones including Notice to Proceed, Concept Drawing Approval, Construction Drawings, Permit Application Submission, ReMAG Submittal, Sub-Contractor SOW, Pre-Construction Meeting, Permit Approval, Start Site Work, and Close Out activities with their respective scheduled and actual completion dates.

View the file

Other files

File Type Posted
SEDS CP RFP Questions and Answers.4.pdf PDF
RFP Att2 - CP SEDS Pricing Sheet_Amendment 3.xlsx XLSX spreadsheet
RFP Att2 - CP SEDS Pricing Sheet_Amendment 3.xlsx XLSX spreadsheet
SEDS CP RFP - Amendment 3 SF30.pdf PDF
SEDS CP RFP 70T04026R7672N005 Amendment 3 track changes.docx DOCX document
SEDS CP RFP 70T04026R7672N005 Amendment 3 clean.docx DOCX document
SEDS CP RFP Questions and Answers.3.pdf PDF
SEDS CP RFP Questions and Answers.2.pdf PDF
SEDS CP RFP - Amendment 2 SF30.pdf PDF
RFP Att2 - CP SEDS Pricing Sheet_amendment 2.xlsx XLSX spreadsheet
SEDS CP RFP 70T04026R7672N005 Amendment 1 track changes.docx DOCX document
RFP Att2 - CP SEDS Pricing Sheet_amendment 1.xlsx XLSX spreadsheet
SEDS CP RFP 70T04026R7672N005 Amendment 1 clean.docx DOCX document
SEDS CP RFP Questions and Answers.pdf PDF
SEDS CP RFP - Amendment 1 SF30.pdf PDF
RFP Att3 - CP SEDS II Program Management Amendment 1.docx DOCX document
RFP Att3 - CP SEDS II Program Management.docx DOCX document
RFP Att3 - CP SEDS II Program Management.docx DOCX document
RFP Att4 -DHS Subcontracting Plan Review Checklist.pdf PDF
Contract Att09 - CDRL D001 - WTMD - CEIA Decommission Checklist_05.19.2025.xlsx XLSX spreadsheet
Contract Att08 - CDRL D001 - ETD - QSB220 De-Install - Install Checklist_05.19.2025.xlsx XLSX spreadsheet
Contract Att01 - CDRL D001 - AIT-1 and AIT-2 - Leidos Decommission Checklist_05.21.2025.xlsx XLSX spreadsheet
Contract Att17 - ITAR_Terms-ConditionsTemplate_11.17.2025.docx DOCX document
Contract Att06 - CDRL D001 - CT De-install Decommission Checklist_05.28.2025.xlsx XLSX spreadsheet
RFP Att2 - CP SEDS Pricing Sheet_04.06.2026.xlsx XLSX spreadsheet
Contract Att03- CDRL D001 - AT Decommission Checklist_05.19.2025.xlsx XLSX spreadsheet
Contract Att05 - CDRL D001 - BLS - Smiths Responder Decomm Checklist_05.21.2025.xlsx XLSX spreadsheet
Contract Att13 - CDRL B006 - Closeout Report_08.11.2025.xlsx XLSX spreadsheet
Contract Att11 - CDRL A004 - Weekly Status Report (WSR)_08.11.2025.xlsx XLSX spreadsheet
Contract Att10 - CDRL B002 - PSP Site Survey_08.11.2025.xlsx XLSX spreadsheet
Contract Att15 - Checkpoint Deployment IMS_Example_01.26.2026.pdf PDF
Contract Att02 - CDRLD001 - AIT - RS Decommission Checklist _08.18.2025.xlsx XLSX spreadsheet
Contract Att16 - DSD Acronym List 03-11-26.docx DOCX document
Contract Att07 - CDRL D001 - ETD - 500DT Install - De-Installation Checklist_05.19.2025.xlsx XLSX spreadsheet
Contract Att04 - CDRL D001 - BLS - CEIA EMA-MS Decommission Checklist_05.21.2025.xlsx XLSX spreadsheet
SEDS CP RFP 70T04026R7672N005.pdf PDF
RFP Att1 - SEDS CP SF-1449.pdf PDF
Questions on SEDS CP RFP.xlsx XLSX spreadsheet
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

00000000

CDRL B001- DAILY SITE REPORT
CDRL Purpose:The Contractor shall deliver daily site progress and status reports for each site detailing accomplishments, risks and issues. These reports are critical to the Program Office’s ability to update program status reports accurately. Reports are due No Later Than 7AM Local time for all Regions. Daily reports are to begin once the IPT calls have commenced unless otherwise directed by the Regional Deployment Manager.
System Integrator:System Integrator POC:
Airport InformationTechnology Information
SystemOEMAllocatedInstall/Remove/RelocationSite Prep
Airport Code:
Airport Name:
Task Order:

Date: 00/00/0000

Site Points of Contact
Company/PositionNameE-mail AddressOfficeCell No.

TSA HQ/DC Points of Contact

Name E-mail Address Cell No.

ReMAG Number Need Date Ordered Date Received Date Status Date Started Date Completed

Days Activities/Accomplishments
CompanyNo. of PersonnelStart TimeEnd TimeActivities Performed

Activities Planned for Tomorrow

Specific Deployment Site Risks
Date IdentifiedRisk ItemDescriptionRecommendationStatus
Issues and Variances to SIP
Date IdentifiedTask OwnerDescriptionContributing Factors
Cumulative System Installation
Location (Ckpt/Ln)TechnologySerial NumberTSA BarcodeSupporting AncillarySAT DateRAD DateComments
Key Milestones
Key MilestoneScheduled Completion DateCompletion DateComments
Notice to Proceed
Concept Drawing Approval
100% Construction Drawings
Permit Application Submission
ReMAG Submittal
Sub-Contractor SOW
Sub-Contract Award
SIP Submittal
Pre-Construction Meeting
Permit Approval
Start Site Work
Close out
Warehouse Close Out
Sign off on CAS As-Built

image1.jpeg

File details come from the government source that posted it. Updated .