Contract Att12 - CDRL B001- Daily Site Report_08.11.2025.xlsx
XLSX spreadsheet 98 KB Posted
- Solicitation number
- 70T04026R7672N005
About this file
This file is a Contractor Delivery Requirement List (CDRL) template for daily site progress reporting on the Screening Equipment Deployment Services (SEDS) - Checkpoint contract. The template establishes requirements for contractors to submit daily site reports no later than 7:00 AM local time for all regions, beginning once Integrated Product Team (IPT) calls commence unless otherwise directed by the Regional Deployment Manager. These reports are critical to the Program Office's ability to accurately track and update program status.
The daily site report template captures essential project information including site identification (airport code, name, task order, date), site points of contact, TSA HQ/DC points of contact, and ReMAG numbers with associated dates (ordered, received, started, completed). Reports must detail accomplishments and activities performed by contractor personnel with start and end times, planned activities for the following day, identified risks with descriptions and recommendations, and issues or variances to the Site Installation Plan (SIP) with contributing factors. The template also tracks cumulative system installation locations, technology serial numbers, TSA barcodes, and supporting ancillary equipment dates (SAT and RAD). Additionally, the form requires documentation of key milestones including Notice to Proceed, Concept Drawing Approval, Construction Drawings, Permit Application Submission, ReMAG Submittal, Sub-Contractor SOW, Pre-Construction Meeting, Permit Approval, Start Site Work, and Close Out activities with their respective scheduled and actual completion dates.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
00000000
| CDRL B001- DAILY SITE REPORT | ||||||
| CDRL Purpose: | The Contractor shall deliver daily site progress and status reports for each site detailing accomplishments, risks and issues. These reports are critical to the Program Office’s ability to update program status reports accurately. Reports are due No Later Than 7AM Local time for all Regions. Daily reports are to begin once the IPT calls have commenced unless otherwise directed by the Regional Deployment Manager. | |||||
| System Integrator: | System Integrator POC: | |||||
| Airport Information | Technology Information | |||||
| System | OEM | Allocated | Install/Remove/Relocation | Site Prep | ||
| Airport Code: | ||||||
| Airport Name: | ||||||
| Task Order: |
Date: 00/00/0000
| Site Points of Contact | ||||
| Company/Position | Name | E-mail Address | Office | Cell No. |
TSA HQ/DC Points of Contact
Name E-mail Address Cell No.
ReMAG Number Need Date Ordered Date Received Date Status Date Started Date Completed
| Days Activities/Accomplishments | ||||
| Company | No. of Personnel | Start Time | End Time | Activities Performed |
Activities Planned for Tomorrow
| Specific Deployment Site Risks | ||||
| Date Identified | Risk Item | Description | Recommendation | Status |
| Issues and Variances to SIP | |||
| Date Identified | Task Owner | Description | Contributing Factors |
| Cumulative System Installation | |||||||
| Location (Ckpt/Ln) | Technology | Serial Number | TSA Barcode | Supporting Ancillary | SAT Date | RAD Date | Comments |
| Key Milestones | |||
| Key Milestone | Scheduled Completion Date | Completion Date | Comments |
| Notice to Proceed | |||
| Concept Drawing Approval | |||
| 100% Construction Drawings | |||
| Permit Application Submission | |||
| ReMAG Submittal | |||
| Sub-Contractor SOW | |||
| Sub-Contract Award | |||
| SIP Submittal | |||
| Pre-Construction Meeting | |||
| Permit Approval | |||
| Start Site Work | |||
| Close out | |||
| Warehouse Close Out | |||
| Sign off on CAS As-Built |