This is a decommissioning checklist template for the Smiths Responder Bottled Liquid Scanner (BLS), a checkpoint screening device used by the Transportation Security Administration. The checklist is designated as Contract Data Requirements List (CDRL) D001 and is utilized during the decommissioning process for BLS units that are being removed from service.

The checklist is organized into multiple verification sections completed by field personnel and system integrators. The inventory section confirms the presence of required components including the BLS system, power supply, verification kit, safety enclosure, clear sticker dispenser, and test samples. The testing section documents the timeframe of last use and verifies operational functionality including power-on capability, user login, calibration, and system detection verification. The unit condition section assesses exterior and interior damage, followed by cleaning requirements for lens and viewing window areas using specified methods. The visual verification section requires photographic documentation of the unit while operational, front, sides, back, serial number, barcode, and make/model, with all images to include damage or concern notations. The packaging section documents the unit's shipping preparation and labeling accuracy. The checklist requires sign-off from three parties: the subcontractor performing the decommissioning, the system integrator conducting review, and a federal employee serving as witness to confirm on-site completion.

View the file

Other files

File Type Posted
SEDS CP RFP Questions and Answers.4.pdf PDF
RFP Att2 - CP SEDS Pricing Sheet_Amendment 3.xlsx XLSX spreadsheet
RFP Att2 - CP SEDS Pricing Sheet_Amendment 3.xlsx XLSX spreadsheet
SEDS CP RFP - Amendment 3 SF30.pdf PDF
SEDS CP RFP 70T04026R7672N005 Amendment 3 track changes.docx DOCX document
SEDS CP RFP 70T04026R7672N005 Amendment 3 clean.docx DOCX document
SEDS CP RFP Questions and Answers.3.pdf PDF
SEDS CP RFP Questions and Answers.2.pdf PDF
SEDS CP RFP - Amendment 2 SF30.pdf PDF
RFP Att2 - CP SEDS Pricing Sheet_amendment 2.xlsx XLSX spreadsheet
SEDS CP RFP 70T04026R7672N005 Amendment 1 track changes.docx DOCX document
RFP Att2 - CP SEDS Pricing Sheet_amendment 1.xlsx XLSX spreadsheet
SEDS CP RFP 70T04026R7672N005 Amendment 1 clean.docx DOCX document
SEDS CP RFP Questions and Answers.pdf PDF
SEDS CP RFP - Amendment 1 SF30.pdf PDF
RFP Att3 - CP SEDS II Program Management Amendment 1.docx DOCX document
RFP Att3 - CP SEDS II Program Management.docx DOCX document
RFP Att3 - CP SEDS II Program Management.docx DOCX document
RFP Att4 -DHS Subcontracting Plan Review Checklist.pdf PDF
Contract Att09 - CDRL D001 - WTMD - CEIA Decommission Checklist_05.19.2025.xlsx XLSX spreadsheet
Contract Att08 - CDRL D001 - ETD - QSB220 De-Install - Install Checklist_05.19.2025.xlsx XLSX spreadsheet
Contract Att01 - CDRL D001 - AIT-1 and AIT-2 - Leidos Decommission Checklist_05.21.2025.xlsx XLSX spreadsheet
Contract Att17 - ITAR_Terms-ConditionsTemplate_11.17.2025.docx DOCX document
Contract Att06 - CDRL D001 - CT De-install Decommission Checklist_05.28.2025.xlsx XLSX spreadsheet
RFP Att2 - CP SEDS Pricing Sheet_04.06.2026.xlsx XLSX spreadsheet
Contract Att03- CDRL D001 - AT Decommission Checklist_05.19.2025.xlsx XLSX spreadsheet
Contract Att13 - CDRL B006 - Closeout Report_08.11.2025.xlsx XLSX spreadsheet
Contract Att11 - CDRL A004 - Weekly Status Report (WSR)_08.11.2025.xlsx XLSX spreadsheet
Contract Att10 - CDRL B002 - PSP Site Survey_08.11.2025.xlsx XLSX spreadsheet
Contract Att15 - Checkpoint Deployment IMS_Example_01.26.2026.pdf PDF
Contract Att12 - CDRL B001- Daily Site Report_08.11.2025.xlsx XLSX spreadsheet
Contract Att02 - CDRLD001 - AIT - RS Decommission Checklist _08.18.2025.xlsx XLSX spreadsheet
Contract Att16 - DSD Acronym List 03-11-26.docx DOCX document
Contract Att07 - CDRL D001 - ETD - 500DT Install - De-Installation Checklist_05.19.2025.xlsx XLSX spreadsheet
Contract Att04 - CDRL D001 - BLS - CEIA EMA-MS Decommission Checklist_05.21.2025.xlsx XLSX spreadsheet
SEDS CP RFP 70T04026R7672N005.pdf PDF
RFP Att1 - SEDS CP SF-1449.pdf PDF
Questions on SEDS CP RFP.xlsx XLSX spreadsheet
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table 1

CDRL D001

Decommission Checklist For the Smiths RespondeR Bottled Liquid Scanner (BLS)

BLS S/N: TSA Bar Code Number:

Airport Code: Terminal/Checkpoint/Lane: Date of Test: Time:

The comments/concerns section may be used to provide further detail concerning unit quality, quantity, or general notes on unit/part condition
SectionEvaluation CriteriaYesNoComments/Concerns
InventoryRespondeR BLS System?
Power Supply with AC Adapter?
Verification Kit?
Safety Enclosure?

(Should be attached to the RespondeR BLS) Clear Sticker Dispenser?

(Should be attached to the Safety Enclosure) "Abnormal Object" Test Sample with Red Label?

(NO PASS)

TestingWhat was the time frame when the system was last used?
Please mark one (1) box.Please check one
(1) box:Past/Current
DayPast 3 DaysPast WeekPast MonthMore than a
monthUnknown
Does the system turn on?
Does the system allow users to Log On?
Does the system calibrate correctly?
Did the system pass the System Detection Verification Check Successfully?

Unit Condition Does the unit have any Exterior Damage?

(i.e. broken pieces, dents, paint chipping, locally added stickers) Does the unit have Interior Damage?

(i.e. broken pieces, dust, locally added stickers)

Cleaning Using a cotton tip applicator, gently clean the lens area to remove any dust or debris.

Using no chemicals, wipe off any dust or debris from the viewing windows.

Visual Verification Take a photo of the unit while OPERATIONAL and document any damage or concerns. (screen included) Take a photo of the FRONT of the unit and document any damage or concerns.

Take a photo of the SIDES of the unit and document any damage or concerns.

Take a photo of the BACK of the unit and document any damage or concerns.

Take a photo of the SERIAL NUMBER and BARCODE on the unit and document any damage or concerns.

Take a photo of the MAKE/MODEL of the unit and document any damage or concerns.

Unit Packaging Take photo of the unit PACKAGED for shipping and document any damage or concerns.

Is there packaging for the BLS responder? Please indicate what type of packaging in the comments (pelican case, cardboard box, etc.).
Is the labeling correct on the packaging?
Subcontractor Contact Information and Verification
Sign and date this Decommission Checklist and leave a copy with the unit.
Performed By:
Printed NameEmail AddressPhone Number
Company NameSignatureDate
System Integrator Section (This section should be filled in by the System Integrator ONLY)
Evaluation CriteriaYesNoComments/Concerns
Has all damage been documented? If NO, please specify in the comments section.
Are there any components missing? If YES, please specify in the comments section.
Is a Verification Kit being returned with this unit? If YES, please note it in the comments section.
Systems Integrator Additional Comments
Systems Integrator Contact Information and Verification
Sign and date this Decommission Checklist and leave a copy with the unit.
Reviewed By:
Printed NameEmail AddressPhone Number
Company NameSignatureDate

Federal Employee Comments/Concerns

Federal Employee Verification
As a witness, sign and date this Decommission Checklist to confirm the document was completed on-site.
Confirmed By:
Printed NameSignatureDate