Attachment_F__Price_Sheet.xlsx
XLSX spreadsheet 25 KB Posted
- Attached to
- Sykes Creek Phase II Muck Removal
- Solicitation number
- B-8-26-36
- Issued by
- Brevard County, Florida
About this file
This is a bid price sheet for the Sykes Creek Phase II Muck Removal Project, a dredging and muck removal initiative in Florida. The project encompasses a base bid for dredging operations in Zones 3A-North and 3B-South involving 223,600 cubic yards of muck removal, along with four optional dredging zones that can be awarded at the Owner's discretion based on budget availability and project priorities. The base bid includes comprehensive work elements such as engineering design and permitting, dredged material management area (DMMA) construction and restoration, pre-construction surveys, muck removal dredging, dewatered material transport and disposal, water quality testing, environmental protection and monitoring, and post-dredge surveys and documentation. Optional Zone 1 (3A-South) includes 17,200 cubic yards, Option 2 (3B-North) includes 34,700 cubic yards, Option 3 (1B.2) includes 38,100 cubic yards, and Option 4 (Zone 2) includes 38,800 cubic yards. Bidders must provide all labor, materials, equipment, supplies, permits, fees, supervision, testing, mobilization, overhead, and incidentals necessary for project completion and must bid on all items to be considered for award.
The bid form requires that all unit costs and total costs be completed by contractors, with the contract to be awarded to the lowest responsive and responsible bidder based on the total bid amount including all optional dredging zones. All quantities are estimated and subject to variation, with actual quantities verified by the contractor prior to material and equipment ordering. Bidders must provide the number of days required to complete each optional dredge zone. The Owner reserves the right to waive informalities, reject bids, delete portions of work items, and award any combination of optional dredge zones at its sole discretion. Contract price and time changes require prior written authorization through Change Orders. The bid form must be completed and returned as specified, with late bids rejected.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Form
SYKES CREEK PHASE II MUCK REMOVAL PROJECT
B-8-26-36
PRICE SHEET
All bid items shall include full compensation for furnishing all labor, materials, equipment, supplies, permits, fees, supervision, testing, mobilization, overhead, profit, and incidentals necessary to complete the Work in accordance with the Contract Documents, including all Work shown on the Construction Drawings and specified in the Contract Specifications.
ITEM ITEM DESCRIPTION ESTIMATED QUANTITY UNITS UNIT COST TOTAL COST
GENERAL ITEMS
1 Base Bid Bonds and Insurance 1 LS $ - 0
DREDGED MATERIAL MANAGEMENT AREA (DMMA), DEWATERING AND TREATMENT SITE CONSTRUCTION, DISPOSAL AND RESTORATION
| 2 | Engineering Design and Permitting | 1 | LS | $ - 0 |
| 3 | Temporary Utilities Construction and Permitting | 1 | LS | $ - 0 |
| 4 | DMMA Surveys (Pre-Construction and Staking) | 1 | LS | $ - 0 |
| 5 | DMMA Mobilization | 1 | LS | $ - 0 |
| 6 | DMMA Clearing and Grubbing | 1 | LS | $ - 0 |
| 7 | Construction Quality Control Testing | 1 | LS | $ - 0 |
| 8 | DMMA Facility Construction | 1 | LS | $ - 0 |
| 9 | DMMA Facility Fencing and Gates | 1 | LS | $ - 0 |
| 10 | Erosion and Sediment Control | 1 | LS | $ - 0 |
| 11 | DMMA Demobilization | 1 | LS | $ - 0 |
| 12 | DMMA Stabilization, Restoration and Cleanup | 1 | LS | $ - 0 |
| 13 | DMMA As-Built Survey | 1 | LS | $ - 0 |
| 14 | Permanent Upland Disposal Fixed Costs | 1 | LS | $ - 0 |
SUB-TOTAL (ITEMS 2 TO 15) $ - 0
DREDGING BASE BID (ZONE 3A-NORTH AND ZONE 3B-SOUTH)
| 15 | Pre-Construction Utility Surveys | 1 | LS | $ - 0 |
| 16 | Mobilization | 1 | LS | $ - 0 |
| 17 | Pre-Dredge Surveys (Including Photo Documentation) | 1 | LS | $ - 0 |
| 18 | Muck Removal Dredging | 223,600 | CY | $ - 0 |
| 19 | Dredged Material Handling and Dewatering | 223,600 | CY | $ - 0 |
| 20 | Dewatered Muck Transport and Permanent Disposal | 223,600 | CY | $ - 0 |
| 21 | Turbidity and Water Quality Testing | 1 | LS | $ - 0 |
| 22 | Post-Dredge and Progress Surveys | 1 | LS | $ - 0 |
| 23 | Post-Dredge Photo Documentaiton | 1 | LS | $ - 0 |
| 24 | Environmental Protection | 1 | LS | $ - 0 |
| 25 | Environmental Species Monitoring | 1 | LS | $ - 0 |
| 26 | Dredged Material Management | 1 | LS | $ - 0 |
| 27 | Demobilization | 1 | LS | $ - 0 |
| 28 | As-Built Hydrographic Maps | 1 | LS | $ - 0 |
SUB-TOTAL (DREDGING BASE) $ - 0
DREDGING OPTION 1 (ZONE 3A-SOUTH)
| 1.Opt1 | Options Bonds and Insurance (Option 1) | 1 | LS | $ - 0 |
| 15.1 | Pre-Construction Utility Surveys | 1 | LS | $ - 0 |
| 16.1 | Mobilization | 1 | LS | $ - 0 |
| 17.1 | Pre-Dredge Surveys (Including Photo Documentation) | 1 | LS | $ - 0 |
| 18.1 | Muck Removal Dredging | 17,200 | CY | $ - 0 |
| 19.1 | Dredged Material Handling and Dewatering | 17,200 | CY | $ - 0 |
| 20.1 | Dewatered Muck Transport and Permanent Disposal | 17,200 | CY | $ - 0 |
| 21.1 | Turbidity and Water Quality Testing | 1 | LS | $ - 0 |
| 22.1 | Post-Dredge and Progress Surveys | 1 | LS | $ - 0 |
| 23.1 | Post-Dredge Photo Documentaiton | 1 | LS | $ - 0 |
| 24.1 | Environmental Protection | 1 | LS | $ - 0 |
| 25.1 | Environmental Species Monitoring | 1 | LS | $ - 0 |
| 26.1 | Dredged Material Management | 1 | LS | $ - 0 |
| 27.1 | Demobilization | 1 | LS | $ - 0 |
| 28.1 | As-Built Hydrographic Maps | 1 | LS | $ - 0 |
| SUB-TOTAL (DREDGING OPTION 1) | $ - 0 |
| DAYS REQUIRED TO COMPLETE (DREDGING OPTION 1) |
DREDGING OPTION 2 (ZONE 3B-NORTH)
| 1.Opt2 | Options Bonds and Insurance (Option 2) | 1 | LS | $ - 0 |
| 15.2 | Pre-Construction Utility Surveys | 1 | LS | $ - 0 |
| 16.2 | Mobilization | 1 | LS | $ - 0 |
| 17.2 | Pre-Dredge Surveys (Including Photo Documentation) | 1 | LS | $ - 0 |
| 18.2 | Muck Removal Dredging | 34,700 | CY | $ - 0 |
| 19.2 | Dredged Material Handling and Dewatering | 34,700 | CY | $ - 0 |
| 20.2 | Dewatered Muck Transport and Permanent Disposal | 34,700 | CY | $ - 0 |
| 21.2 | Turbidity and Water Quality Testing | 1 | LS | $ - 0 |
| 22.2 | Post-Dredge and Progress Surveys | 1 | LS | $ - 0 |
| 23.2 | Post-Dredge Photo Documentaiton | 1 | LS | $ - 0 |
| 24.2 | Environmental Protection | 1 | LS | $ - 0 |
| 25.2 | Environmental Species Monitoring | 1 | LS | $ - 0 |
| 26.2 | Dredged Material Management | 1 | LS | $ - 0 |
| 27.2 | Demobilization | 1 | LS | $ - 0 |
| 28.2 | As-Built Hydrographic Maps | 1 | LS | $ - 0 |
| SUB-TOTAL (DREDGING OPTION 2) | $ - 0 |
| DAYS REQUIRED TO COMPLETE (DREDGING OPTION 2) |
DREDGING OPTION 3 (ZONE 1B.2)
| 1.Opt3 | Options Bonds and Insurance (Option 3) | 1 | LS | $ - 0 |
| 15.3 | Pre-Construction Utility Surveys | 1 | LS | $ - 0 |
| 16.3 | Mobilization | 1 | LS | $ - 0 |
| 17.3 | Pre-Dredge Surveys (Including Photo Documentation) | 1 | LS | $ - 0 |
| 18.3 | Muck Removal Dredging | 38,100 | CY | $ - 0 |
| 19.3 | Dredged Material Handling and Dewatering | 38,100 | CY | $ - 0 |
| 20.3 | Dewatered Muck Transport and Permanent Disposal | 38,100 | CY | $ - 0 |
| 21.3 | Turbidity and Water Quality Testing | 1 | LS | $ - 0 |
| 22.3 | Post-Dredge and Progress Surveys | 1 | LS | $ - 0 |
| 23.3 | Post-Dredge Photo Documentaiton | 1 | LS | $ - 0 |
| 24.3 | Environmental Protection | 1 | LS | $ - 0 |
| 25.3 | Environmental Species Monitoring | 1 | LS | $ - 0 |
| 26.3 | Dredged Material Management | 1 | LS | $ - 0 |
| 27.3 | Demobilization | 1 | LS | $ - 0 |
| 28.3 | As-Built Hydrographic Maps | 1 | LS | $ - 0 |
| SUB-TOTAL (DREDGING OPTION 3) | $ - 0 |
| DAYS REQUIRED TO COMPLETE (DREDGING OPTION 3) |
DREDGING OPTION 4 (ZONE 2)
| 1.Opt4 | Options Bonds and Insurance (Option 4) | 1 | LS | $ - 0 |
| 15.4 | Pre-Construction Utility Surveys | 1 | LS | $ - 0 |
| 16.4 | Mobilization | 1 | LS | $ - 0 |
| 17.4 | Pre-Dredge Surveys (Including Photo Documentation) | 1 | LS | $ - 0 |
| 18.4 | Muck Removal Dredging | 38,800 | CY | $ - 0 |
| 19.4 | Dredged Material Handling and Dewatering | 38,800 | CY | $ - 0 |
| 20.4 | Dewatered Muck Transport and Permanent Disposal | 38,800 | CY | $ - 0 |
| 21.4 | Turbidity and Water Quality Testing | 1 | LS | $ - 0 |
| 22.4 | Post-Dredge and Progress Surveys | 1 | LS | $ - 0 |
| 23.4 | Post-Dredge Photo Documentaiton | 1 | LS | $ - 0 |
| 24.4 | Environmental Protection | 1 | LS | $ - 0 |
| 25.4 | Environmental Species Monitoring | 1 | LS | $ - 0 |
| 26.4 | Dredged Material Management | 1 | LS | $ - 0 |
| 27.4 | Demobilization | 1 | LS | $ - 0 |
| 28.4 | As-Built Hydrographic Maps | 1 | LS | $ - 0 |
| SUB-TOTAL (DREDGING OPTION 4) | $ - 0 |
| DAYS REQUIRED TO COMPLETE (DREDGING OPTION 4) |
TOTAL BID (LINE ITEMS 01 TO 28.4) $ - 0
Company Name Name of Authorized Representative (Print)
Street Address Name of Authorized Representative (Signature)
City, State, Zip Code E-Mail Address
Telephone
NOTICE TO ALL BIDDERS:
1. All quantities are estimated. Actual quantities may vary.
2. The Owner reserves the right to waive any informality in any bid, to reject any and all bids, and to delete any portion of any of the above items.
3. Changes in the Contract Price and Contract Time require prior authorization, in writing from the Owner, in the form of a Change Order. The Contractor is responsible for verification of all bid quantities and to report to the Engineer any discrepancies found prior to ordering materials and/or equipment for construction.
4. Bid prices for the various work items are intended to establish a total price for completing the project in its entirety. The Contractor shall include in the Bid, any item for which a separate pay item has not been established in the Bid Form (under any related pay item), to reflect the total price for completing the project in its entirety.
5. The Contractor shall meet requirements of all applicable authorizations, permits, and codes (in their current edition).
6. Bids must be received no later than the date and time stated in the Advertisement. Bids received after that date and time will not be considered.
7. This form must be returned with the Bid. Bids on any other form will not be accepted.
8. The Bidder must Bid on all items in the this form to be considered for award. This project will be awarded to the lowest responsive and responsible bidder based on the total bid amount, including all optional dredging zones.
9. The Owner intends to award the optional dredge zones in the order indicated on the Bid Form but reserves the right to award and/or execute any combination of the optional dredge zones at its sole discretion based on budget availability and project priorities.
10. This project includes four (4) bid options to dredge additional volumes from adjacent dredge zones as indicated on the construction drawings. The Contractor shall provide additional time required for each optional dredge zone on this Bid Form.
File details come from the government source that posted it. Updated .