This is a Schedule of Fire Protection System Inspections by FPQC Specialist document (Amendment 008, dated 03/10/2026) that outlines inspection and surveillance requirements for fire protection systems during construction phases and final acceptance inspections.
The document establishes three surveillance phases: Surveillance During Construction (periodic on-site visits), Pre-Final Acceptance Inspection (FPQC must be onsite), and Final Acceptance Inspection (FPQC must be onsite). Inspections consist of three types: Visual Inspections (to confirm work conforms with contract requirements and applicable codes), Observations (witnessing component and system testing in person), and Documentation (recording all inspections, observations, and deficiencies in FPQC Reports per UFGS 01 45 00). The surveillance scope covers four primary system categories: Fire Suppression Systems (underground and above-ground piping, hydrants, hydrostatic testing, fire pump operations, sprinkler piping), Special Fire Suppression Systems (gaseous systems, elevator fire protection, firestopping), Passive Fire Protection Systems (fire-rated assemblies, fireproofing, firestopping), and Fire Alarm Systems (conduit, wiring, device installation). During construction, the FPQC performs visual inspections and observes testing; during pre-final inspection, the FPQC inspects all systems, witnesses functional testing, identifies deficiencies, verifies rework, and certifies conformance; during final acceptance, the FPQC verifies proper installation and operation, documents deficiencies, confirms corrections, and certifies completion. All inspections require daily documentation and recording of deficiencies in rework lists.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCHEDULE OF FIRE PROTECTION SYSTEM
INSPECTIONS BY FPQC SPECIALIST
1. INSTRUCTIONS for FPQC Specialist:
Perform surveillance of fire protection system installation during construction and during pre-final and final acceptance inspections. Surveillance includes either visual inspections or observations performed by the FPQC as indicated in the following Schedule of Fire Protection System Inspections.
Check boxes in the schedule indicate the inspections or observations that are applicable to this project, which must be performed and documented by the FPQC.
Surveillance of fire protection system inspections is divided into three phases:
Surveillance During Construction – Includes periodic on-site visits by the FPQC during construction Pre-Final Acceptance Inspection – FPQC must be onsite during pre-final acceptance inspection Final Acceptance inspection – FPQC must be onsite during final acceptance inspection
2. INSPECTION TYPE
VISUAL INSPECTION:
Perform on-site visual inspections as indicated in the Schedule of Fire Protection System Inspections as construction progresses to confirm work conforms with the contract requirements including but not limited to verifying proper installation of equipment and materials in accordance with applicable codes. Where work will be covered up by finished walls and ceilings, inspections must be scheduled and performed when work is still visible.
OBSERVATION:
Observe component and system testing in person on-site as indicated in the Schedule of Fire Protection System Inspections. Confirm testing is completed in accordance with applicable codes and that testing was successful.
DOCUMENTATION:
Document all inspections and observations in the FPQC Report in accordance with UFGS 01 45 00.
Document any deficiencies and all work observed that has been successfully performed in accordance with the contract documents. Record deficiencies in the rework list.
llangley Typewritten Text
AMENDMENT 008, 03/10/2026
PERFORM SURVEILLANCE DURING CONSTRUCTION
~ FIRE SUPPRESSION SYSTEM ~
PERFORM
TASK IF
CHECKED
TASK INSPECTION
TYPE DESCRIPTION
☒ 1. Verify proper installation of underground service main and service; laterals, thrust blocks, tie-rods and connection to above ground piping.
VISUAL
INSPECTION
Visually inspect materials Visually inspect installation
☒ 2. Verify proper orientation of fire hydrants and fire department access
VISUAL
INSPECTION
Visually inspect installation and orientation
☐ 3. Verify proper installation of interior and exterior attachments, coatings, and vortex plate prior to filling fire protection water tank
VISUAL
INSPECTION
Visually inspect fire protection water tank installation
☒ 4. Hydrostatic/leak test for underground piping
OBSERVE Verify proper test method Confirm test was successful
☒ 5. Hydrostatic/leak test for above ground piping prior to ceiling installation
OBSERVE Verify proper test method Confirm test was successful
☒ 6. Underground system flush prior to connection to the riser
OBSERVE Verify system was properly flushed
☒ 7. Forward flow test for Backflow preventer
OBSERVE Verify proper test method Confirm test was successful
☒ 8. Suction pipe flush prior to fire pump startup
OBSERVE Verify system was properly flushed
☒ 9. Hydrostatic test fire pump suction and discharge piping
OBSERVE Verify proper test method Confirm test was successful
☒ 10. Fire pump startup OBSERVE Confirm successful startup
☒ 11. Verify proper installation of sprinkler piping prior to wall or ceiling installation
VISUAL
INSPECTION
Inspect pipe hangars, bracing, sprinkler heads
Inspect for sprinkler obstructions;
damaged, painted or covered heads
Verify proper location of control valves, drains, vents, backflow, test header
Verify proper component mounting heights
☒ 12. Document inspections and observations in FPQC Report
DOCUMENT Submit report for each day inspections or observations occur
Annotate deficiencies and satisfactory work observed
Record rework items in FPQC report
~ SPECIAL FIRE SUPPRESSION SYSTEM ~
PERFORM
TASK IF
CHECKED
TASK INSPECTION
TYPE DESCRIPTION
☐ 1. Verify proper installation of gaseous fire suppression system
VISUAL
INSPECTION
Inspect gas cylinders, initiating controls, shutdowns, aborts, and visual warning
☐ 2. Verify proper installation of IR hangar detector
VISUAL
INSPECTION
Inspect detector and nozzle layout Inspect for obstructions, abort stations Inspect riser piping
☒ 3. Verify proper installation of elevator fire protection
VISUAL
INSPECTION
Inspect elevator recall functions Inspect two-way communication
☐ 4. Verify proper installation of fire suppression in secure spaces
VISUAL
INSPECTION
Inspect location of sprinkler piping and sprinklers
☒ 5. Document inspections and observations in FPQC Report
DOCUMENT Submit report for each day inspections or observations occur
Document deficiencies and satisfactory work observed in FPQC Report
Record deficiencies in rework list
~ PASSIVE FIRE PROTECTION SYSTEMS ~
PERFORM
TASK IF
CHECKED
TASK INSPECTION
TYPE DESCRIPTION
☒ 1. Verify proper construction of fire rated assemblies
VISUAL
INSPECTION
Inspect partitions for proper fire rated construction per design
Inspect doors and door hardware for proper fire rating
Inspect glass for proper fire rating ☒ 2. Verify proper installation of fireproofing
VISUAL
INSPECTION
Inspect for use of proper fireproofing materials Inspect for cracking, spalling or delaminating Inspect for proper application thickness ☒ 3. Verify proper installation of firestopping
VISUAL
INSPECTION
Inspect to confirm firestopping system is UL tested or an engineering judgement has been obtained and submitted
Inspect for use of proper firestopping materials
Inspect penetrations through fire rated walls, partitions and ceilings
Inspect construction joints and gaps
☒ 4. Document inspections and observations in FPQC Report
DOCUMENT Submit report for each day inspections or observations occur
Document deficiencies and satisfactory work observed in FPQC Report
Record deficiencies in rework list
~ FIRE ALARM SYSTEMS ~
PERFORM
TASK IF
CHECKED
TASK INSPECTION
TYPE DESCRIPTION
☒ 1. Verify proper installation of fire alarm system after conduit is installed and wiring pulled, but before devices are installed
VISUAL
INSPECTION
Inspect conduit, wiring, conduit fill, wire type
Inspect installation heights of back boxes
☒ 2. Document inspections and observations in FPQC Report
DOCUMENT Submit report for each day inspections or observations occur
Document deficiencies and satisfactory work observed in FPQC Report
Record deficiencies in rework list
~ END OF SURVEILLANCE DURING CONSTRUCTION SECTION
PERFORM DURING PRE-FINAL ACCEPTANCE INSPECTION
PERFORM
TASK IF
CHECKED
TASK INSPECTION
TYPE DESCRIPTION
☒ 1. Inspect all fire protection systems and all life safety features
VISUAL
INSPECTION
Verify proper installation of fire protection and life safety systems
☒ 2. Witness functional testing of all fire protection and life safety systems
OBSERVE Verify proper testing is performed on fire protection and life safety systems
☒ 3. Identify deficiencies that require correction
VISUAL
INSPECTION
Document deficiencies in FPQC Report and record in rework list
☒ 4. Verify rework items have been corrected
VISUAL
INSPECTION
Record re-inspection results on FPQC Report
☒ 5. Document results of pre-final inspection and unsatisfactory conditions
DOCUMENT Document results of pre-final inspection in FPQC Report
☒ 6. Certify installation and operation of all fire protection and life safety systems conform to the contract documents
DOCUMENT Provide separate letter certifying conformance with contract requirements
~ END OF PRE-FINAL INSPECTION SECTION
PERFORM DURING FINAL ACCEPTANCE INSPECTION
PERFORM
TASK IF
CHECKED
TASK INSPECTION
TYPE DESCRIPTION
☒ 1. Verify proper installation and operation of all fire protection systems and all life safety features
VISUAL
INSPECTION
☒ 2. Note any deficiencies identified by Government FPE on deficiency list
DOCUMENT Document deficiencies identified by Government FPE on deficiency list
☒ 3. Verify all deficiencies have been corrected
VISUAL
INSPECTION
Inspect rework to confirm all deficiencies have been corrected
☒ 4. Certify that all deficiencies have been corrected
DOCUMENT Document inspection results on FPQC Report
~ END OF FINAL ACCEPTANCE INSPECTION SECTION