618-21-700.MEHRM.FINAL.B70.20220506Part-7.pdf
PDF 17 MB Posted
- Solicitation number
- 36C77622R0045
About this file
This document describes a federal contract opportunity for construction design and build services. The solicitation is being issued by the Department of Veterans Affairs Office of Information Service Center as a Request for Proposal to upgrade infrastructure needed for the Electronic Health Record Modernization project at the Minneapolis VA Medical Center. The construction and commissioning work will be performed in accordance with design plans and specifications provided by the architect-engineer. Services include building a new server room on the hospital roof and upgrading systems throughout multiple departments. As a total Service-Disabled Veteran-Owned Small Business set-aside, offers will only be accepted from SDVOSB concerns. The period of performance is approximately 450 calendar days from notice to proceed, and the magnitude of construction is estimated between $20-50 million. Questions must be submitted in writing by email to the issuing office contact by the specified due date.
View the file
Other files
Show 40 more
Latest 50 of 80 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
on e-ei gh th in ch o ne fo ot on e-qu ar te r ne fo ot th re e-ei gh th s ne fo ot on e-ha lf ne fo ot th re e-qu ar te r ne fo ot in ch on e ne fo ot on e an d on e-ha lf ne fo ot th re e in es ne fo ot
REVISIONS DATE
General Notes:
GENERAL CONTRACTOR AND/OR ALL SUBCONTRACTORS SHALL FIELD VERIFY ALL DIMENSIONS SHOWN ON THESE PLANS AND SHALL BE RESPONSIBLE FOR VARIATIONS BETWEEN PLAN DIMENSIONS AND ACTUAL FIELD DIMENSIONS. WHERE VARIATIONS ARE FOUND TO OCCUR, THE CONTRACTOR SHALL NOTIFY THE PROJECT ENGINEER IN WRITING PRIOR TO PROCEEDING WITH CONSTRUCTION; NO ADJUSTMENT TO
THE WORK WILL BE MADE WITHOUT THE PRIOR APPROVAL OF THE PROJECT ENGINEER.
GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR GENERAL DEMOLITION INCLUDING REMOVAL OF WALLS, PARTITIONS, DOORS & CEILING & FLOORS. ANY AND ALL CUTTING OF CONCRETE FLOORS, WALLS OR STRUCTURE SHALL BE THE GENERAL CONTRACTOR'S RESPONSIBILITY. CORE DRILLING THROUGH CONCRETE WALLS, FLOORS OR STRUCTURE FOR PIPING OR CONDUIT SHALL BE THE RESPONSIBILITY OF THE SUBCONTRACTOR BY TRADE; FIRESTOPPING OF THESE OPENINGS SHALL BE DONE BY THE RESPECTIVE SUBCONTRACTOR. REMOVAL OF DEBRIS RESULTING FROM DEMOLITION, CUTTING, AND/OR DRILLING IS THE RESPONSIBILITY OF THE GENERAL CONTRACTOR. PATCHING AND REPAIR OF CONCRETE WALLS, FLOOR, OR STRUCTURE SHALL BE THE RESPONSIBILITY OF THE GENERAL CONTRACTOR; THIS WILL BE ACCOMPLISHED UPON COMPLETION OF THE INSTALLATION OF ANY AND ALL UTILITIES INSTALLED
BY THE VARIOUS SUBCONTRACTORS.
Approved: Division Chief
Issue Date Checked Drawn
DrawingNumber
Building Number
Project NumberDrawing Title Project Title
Location Drawing Scale
Approved: Service DirectorPlot Scale U.S. Department of Veterans Affairs
Office of Construction and Facilities Management
FULLY SPRINKLERED
Phase
A
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
321 4 5 6 7 8 9 10
B70
A/E:
TRIPLE C - The A/E Group
2508 29th Avenue NE
Minneapolis, MN 55418
(612) 355-1251
Mat Perkins
B
IM
/6
-2
-7
E
H R
M I n fr a s tr u c tu re U p g ra d e s M
P L S
V A
M C
/6 -2
-7
.M
E H
R M
.M E
P .G e n e ra l.
S h e e ts
.r v t
/5
/2
:1
:3
P
M
05/06/2022 M. Perkins G. Weaver
618-21-700
1383 -
70FX901
FIRE PROTECTION CUTSHEETS & BASIS OF
DESIGN
1 Veterans Drive, Minneapolis, MN 55417
EHRM INFRASTRUCTURE
UPGRADESFINAL BID DOCUMENTS
05/06/2022
A
B
M
HS
S
HWS
M
M
P
PS PS
F
PS
TS
V
D
TWS
TWR
TWB
MPS
HPS
LPS
CHR
RS
RL
HWR
R
T
H
CO
CHS
XX-##
SDSD
ELBOW - DOWN
ELBOW - UP
PIPE RISE-DROP
TEE - DROP FROM TEE
END CAP
FLEX CONNECTION
PIPE REDUCER - CONCENTRIC
PIPE STRAINER
CHECK VALVE
GATE VALVE
PLUG VALVE
GLOBE VALVE
UNION - SCREWED
CHILLED WATER SUPPLY
CHILLED WATER RETURN
REFRIGERATION
STEAM - MEDIUM PRESSURE SUPPLY
STEAM - LOW PRESSURE SUPPLY
STEAM - HIGH PRESSURE SUPPLY
HEATING WATER RETURN
HEATING WATER SUPPLY
DEMO
EXISTING
TOWER WATER BYPASS
TOWER WATER RETURN
TOWER WATER RETURN
REFRIGERATION LIQUID
REFRIGERATION SUCTION
MECHANICAL PIPING
DIRECTION OF FLOW
MAKE-UP WATER
VENT
DRAIN
GEOTHERMAL SUPPLY
GEOTHERMAL RETURN
MU
CONDENSATE DRAINCD
STEAM - MEDIUM PRESSURE RETURN
STEAM - LOW PRESSURE RETURN
STEAM - HIGH PRESSURE RETURNHPR
HPR
LPR
CONDENSER WATERCND
GWS
GWR
DIRECTION PITCHDOWN
VERIFY WITH
ARCHITECTURAL
DRAWINGS
PUMPED CONDENSATEPC
PRESSURE REDUCING VALVE
3-WAY
MODULATING
CONTROL VALVE
2-WAY CONTROL VALVE
SAFETY VALVE OR
PRESSURE RELIEF
VALVE
SOLENOID VALVE
3/4" BALL VALVE WITH ADAPTER
TO 3/4" HOSE THREAD
DIAPHRAGM VALVE
BUTTERFLY VALVE
BALL VALVE
VALVE IN RISE
WATER FLOW MEASURING DEVICE
CIRCUIT SETTER
ELBOW - DROP TO TEE
PIPE REDUCER - ECCENTRIC
AIR VENT - AUTOMATIC
AIR VENT - MANUAL
GAUGE - DIFFERENTIAL
GAUGE - PRESSURE
GAUGE - PRESSURE WITH COCK
GAUGE - TEMPERATURE
PIPE ANCHOR
PIPE EXPANSION JOINT
PIPE GUIDE
SENSOR - FLOW
SWITCH - FLOW
SWITCH HUMIDITY
SWITCH - PRESSURE
SWITCH - TEMPERATURE
TEMPERATURE - PRESSURE TEST FITTING
THERMOMETER
THERMOMETER WELL
BASKET STRAINER
STEAM TRAP INVERTED BUCKET
METER - TOTALIZING BTU
METER - TOTALIZING FLOW
M301
A1
SCALE
DETAIL
SCALE
SECTION
A1
A1
X#/X###
MECHANICAL SYMBOL LEGEND
DUCT TRANSITION FROM RECTANGULAR TO ROUND
DUCT TRANSITION
SIDEWALL EXHAUST OR RETURN AIR GRILLE
OR REGISTER
SIDEWALL SUPPLY REGISTER
RETURN DUCT
SUPPLY DUCT
RISE IN DUCT
CEILING RETURN AIR REGISTER OR GRILLE
SMOKE DAMPER
ACOUSTICAL DUCT LINING
FLEXIBLE DUCT
FIRE DAMPER
MANUAL BALANCING DAMPER
12"Ø INDICATES A 12" ROUND DUCT
24x12Ø INDICATES A 24"x12" FLAT OVAL DUCT (WIDTH x DEPTH)
EXISTING DUCT TO BE REMOVED
ACCESS DOOR
24x12 INDICATES A 24"x12" RECTANGULAR DUCT (WIDTH x DEPTH)
POINT OF CONNECTION, NEW DUCT TO EXISTING DUCT
OR / POINT OF REMOVAL FROM EXISTING DUCT TO DEMO DUCT
PERFORATED FACE CEILING DIFFUSERS
DUCTWORK SYMBOLS
ROOM HUMIDISTAT/HUMIDITY TRANSMITTER LOCATION ONLY
SEE CONTROL DRAWINGS FOR TYPE
SEE CONTROL DRAWINGS FOR TYPE
ROOM THERMOSTAT/TEMP. TRANSMITTER LOCATION ONLY
LETTERS REFER TO THE EQUIPMENT TYPE
EQUIPMENT SYMBOLS
NUMBERS REFER TO SPECIFIC EQUIPMENT
DUCT MOUNTED STATIC PRESSURE PROBE
DRAWING NUMBER WHERE DETAILED
SECTION LOCATION
DRAWING NUMBER WHERE DETAILED
DETAIL LOCATION
SECTION LETTER LOCATION
SECTION SYMBOL
DETAIL SYMBOL
SECTION AND DETAIL TITLES
DETAIL NUMBER LOCATION
SYMBOL INDICATES EQUIPMENT IDENTIFIED
IN EQUIPMENT SCHEDULE
XX-#
CFM
SYMBOL INDICATES GRILLE OR DIFFUSER
IDENTIFIED IN EQUIPMENT SCHEDULE
S.DPR
F.DPR
CEILING EXHAUST REGISTER
VALVE SYMBOLS FITTING SYMBOLS
PIPING SYMBOLS
EXHAUST DUCT
2HR. SMOKE BARRIER
SMOKE BARRIER
2HR. FIRE BARRIER
1 HR. FIRE BARRIER
##x##
SIDEWALL GRILLE DIMENSION WHERE
SHOWN ON PLANS
COMBINATION FIRE/SMOKE DAMPER
F/S DPR
FLEXIBLE CONNECTION
STANDARD LONG RADIUS ELBOW
VANED ELBOW (PROVIDE ALL SQUARE OR
RECTANGULAR ELBOWS WITH VANES
EXCEPT TRANSFER AIR SOUND ELBOW)
SHORT RADIUS ELBOW (PROVIDE ALL
SQUARE OR RECTANGULAR ELBOWS WITH
VANES EXCEPT TRANSFER AIR SOUND
ELBOW)
ROOM CARBON DIOXIDE TRANSMITTER LOCATION ONLY
SEE CONTROL DRAWINGS FOR TYPE
24"x12"
24"/12"
12"Ø
DUCT MOUNTED SMOKE DETECTOR
STAMPED FACE CEILING DIFFUSERS
NOTE: NOT ALL ABBREVIATIONS AND
SYMBOLS APPLY TO THIS PROJECT.
A. ALL PIPING AND DUCTS IN FINISHED ROOMS OR SPACES SHALL BE CONCEALED IN
FURRED CHASES OR SUSPENDED CEILINGS, UNLESS OTHERWISE NOTED.
B. PROVIDE ACCESS PANELS OR DOORS IN INACCESSIBLE CEILINGS AND/OR
CHASES FOR ALL VALVES, TRAPS, DAMPERS, CLEANOUTS, COILS, FANS,
CONTROLS, ETC. THEY SHALL BE FURNISHED UNDER DIVISION 23 AND
INSTALLED UNDER THE ARCHITECTURAL SPECIFICATION. ACCESS DOOR RATING
SHALL MATCH CLASSIFICATION OF WALL AND CEILING FIRE RATING.
C. COORDINATE THE LOCATION OF ALL DIFFUSERS, GRILLES, REGISTERS, ACCESS
DOORS, ETC., WITH THE ARCHITECTURAL REFLECTED CEILING PLAN(S).
D. ALL ROUND RUNOUTS AND DROPS TO DIFFUSERS SHALL BE THE SAME NOMINAL
SIZE AS THE SCHEDULED DIFFUSER NECK SIZE.
E. THE FIRST FIGURE OF DUCT SIZE INDICATES DIMENSION OF FACE SHOWN OR
INDICATED. ALL DUCT SIZES SHOWN ON DRAWINGS ARE NET INSIDE DIMENSIONS.
PROVIDE ONE INCH ACOUSTICAL LINING (TYPE D3 INSULATION) IN LOW VELOCITY
RECTANGULAR DUCTWORK FOR THE FIRST 10 DIAMETERS OF DUCTWORK
CONNECTED TO DEVICE, OR AS INDICATED ON DRAWINGS, WHICHEVER IS
GREATER. FOR THE REMAINDER OF THIS DUCTWORK PROVIDE AS INDICATED IN
THE INSULATION SPECIFICATIONS.
F. PROVIDE 1/2" MANUAL AIR VENTS AT ALL HIGH POINTS OF CLOSED SYSTEM PIPING
AND 1/2" MANUAL DRAIN VALVES WITH HOSE CONNECTION AT LOW POINTS AS
REQUIRED TO PROVIDE COMPLETE SYSTEM DRAINAGE. WHERE DRAIN VALVES
OCCUR ABOVE CEILING AREAS AND IN AREAS OUTSIDE MECHANICAL RANGE
PROVIDE HOSE CONNECTION ON VALVE.
G. REFER TO THE ARCHITECTURAL DRAWINGS FOR EXACT LOCATION OF ALL FIRE
RATED AND/OR SMOKE RATED WALLS AND ASSEMBLIES. PROVIDE APPROVED
FIRE DAMPERS IN ALL REQUIRED PENETRATIONS FOR DUCTWORK, GRILLES,
REGISTERS AND DIFFUSERS. ALL PIPE AND DUCTWORK PENETRATIONS OF FIRE,
SMOKE AND FULL HEIGHT WALLS SHALL BE CAULKED AIRTIGHT TO THE ADJACENT
STRUCTURE BY MEANS OF U.L. APPROVED FIRE PROOF CAULKING MATERIAL.
H. CONTRACTOR SHALL COORDINATE ALL DUCTWORK, PIPING, PLUMBING AND
FIRE PROTECTION PIPING WITH STRUCTURAL AND ELECTRICAL SYSTEMS AND
SHALL PROVIDE NECESSARY OFFSETS TO AVOID CONFLICTS AND TO MAINTAIN
EQUIPMENT ACCESS AND SERVICEABILITY.
I. CONTRACTOR SHALL FURNISH ALL NECESSARY STRUCTURES, INSERTS,
SLEEVES, AND HANGING DEVICES FOR INSTALLATION OF MECHANICAL AND
PLUMBING EQUIPMENT, DUCTWORK AND PIPING, ETC. CONTRACTOR SHALL
COORDINATE WITH GENERAL CONTRACTOR AND ALL BUILDING TRADES TO AVOID
CONFLICTS AND TO MAINTAIN EQUIPMENT ACCESS AND SERVICEABILITY.
J. CONTRACTOR SHALL BE RESPONSIBLE FOR PROVIDING ALL NECESSARY
MISCELLANEOUS ANGLES, CHANNELS, UNISTRUT, ETC., AS MAY BE REQUIRED TO
ADEQUATELY SUPPORT THE MECHANICAL PIPING, DUCTWORK, AND EQUIPMENT
IN A MANNER APPROVED BY THE ARCHITECT, WHICH WILL NOT OVERLOAD THE
BUILDING STRUCTURAL SYSTEM.
K. CONTRACTOR SHALL PROVIDE RETURN AIR OR TRANSFER AIR OPENINGS IN
FULL HEIGHT WALLS SIZED AT 350 FPM (UNLESS OTHERWISE SPECIFICALLY
SHOWN ON THE DRAWINGS) TO CREATE AND/OR MAINTAIN A RETURN AIR PATH AS
REQUIRED. FIRE DAMPERS AND/OR SMOKE DAMPERS SHALL BE PROVIDED IN
SUCH OPENINGS WHERE REQUIRED BY NOTE "J".
L. SEAL ALL TRANSVERSE JOINTS, LONGITUDINAL SEAMS, DUCT WALL
PENETRATIONS AND FITTING CONNECTIONS ON ALL DUCT SYSTEMS.
M. MECHANICAL ITEMS SUCH AS ROOF DRAINS, FLOOR DRAINS, PLUMBING FIXTURES,
ETC. SHOWN ON THE ARCHITECTURAL DRAWINGS BUT NOT SHOWN ON THE
MECHANICAL DRAWINGS SHALL BE INCLUDED IN THE PROJECT. THESE ITEMS
SHALL BE BROUGHT TO THE ATTENTION OF THE ARCHITECT FOR INCLUSION IN
ADDENDUM.
N. IT IS CRITICAL THAT THE CONTRACTOR PERFORM A COMPLETE REVIEW OF ALL
SUBMITTALS PRIOR TO SUBMISSION TO THE AE/COR. INCOMPLETE, INCORRECT
AND UNCLEAR SUBMITTALS WILL BE REJECTS AND MARKED AS "REVISE AND
RESUBMIT". ALL SUBMITTALS MUST CLEARLY INDICATE THE EQUIPMENT
SELECTIONS FOR THE PROJECT. TECHNICAL DRAWINGS OF COMPLETE
ASSEMBLIES, REFLECTING ACCURATE PROJECT CONDITIONS, SHALL BE
SUBMITTED WITH EQUIPMENT SELECTIONS TO ENSURE SPACE ALLOWANCES ARE
REFLECTED IN THE ACTUAL SPACE AVAILABLE. WHERE SIZE DEVIATIONS DIFFER
FROM THE BASIS OF DESIGN CONTRACTOR SHALL HIGHLIGHT THE DIFFERENCES
FOR AE/COR REVIEW WITHIN THE SUBMITTAL. CONTRACTOR SHALL PROVIDE
INSTALLATION ROUTE AND VERIFICATION THAT ACCESS POINTS, PLACEMENT
ROUTE, SUPPORTS, AND REQUIRED EQUIPMENT CLEARANCES ARE IDENTIFIED ON
THE ROUTE DRAWING. SAFETY PROTOCOLS FOR SUBJECT STATION SHALL BE
REFLECTED ON EQUIPMENT CLEARANCES. PLATFORMS AND INTERFACE AREAS
(FILTER, GAUGES, MONITORS, VALVES, ETC.) SHALL HAVE PROPER CLEARANCE AS
DEFINED BY THE MANUFACTURER, VA SAFETY PERSONNEL AND SERVICE
PERSONNEL. ACCESS POINTS OF USE SHALL BE CLEARLY IDENTIFIED ON THE
DRAWINGS.
O. THIS PROJECT RECONFIGURATION OF EXISTING BUILDING MECHANICAL AND
PLUMBING SYSTEMS TO MAINTAIN EXISTING BUILDING UTILITY SERVICES. THIS
WORK INCLUDES: (1) RELOCATING AND REPLACING EXISTING DUCT, PIPE, AIR
TERMINALS, ETC.; (2) PROVIDING NEW STRUCURAL SUPPORTS AND SEISMIC
BRACING FOR EXISTING MECHANICAL AND PLUMBING SYSTEMS WHERE
RECONFIGURATIONS ARE REQUIRED; (3) PROVIDING DRIP PANS WITH DRAIN
CONNECTIONS TO EXISTING FLOOR DRAINS BELOW ALL EXISTING WATER WATER
PIPES THAT ROUTE ADJACENT TO OR ABOVE ELECTRICAL AND COMMUNICATIONS
EQUIPMENT.
P. CONTRACTOR SHALL SUBMIT COORDINATION DRAWINGS PRIOR TO COMMENCING
WORK SHOWING ALL NEW AND EXISTING SYSTEMS IN THE AREA OF WORK AND
ALL PROVISIONS FOR COORDINATING ROUTING, ACCESS AND CLEARANCES.
SUBMITTALS WILL NOT BE ACCEPTED WITHOUT APPROVED COORDINATION
DRAWINGS.
A. THE DEMOLITION DRAWINGS REFLECT INFORMATION ON EXISTING BUILDING
SERVICES GATHERED BY SITE INSPECTION, DISCUSSIONS WITH MAINTENANCE
PERSONNEL AND PREVIOUS CONSTRUCTION DRAWINGS. THE EXACT LOCATION,
ARRANGEMENT, AND SIZES OF PIPE LINES AND DUCTWORK IN THE EXISTING BUILDING
MAY BE DIFFERENT FROM THAT SHOWN ON THESE DRAWINGS.
B. THE CONTRACTOR SHALL COORDINATE THE SHUTDOWN OF EXISTING BUILDING
SERVICES FOR REMOVAL WITH OWNER AUTHORIZED REPRESENTATIVE AND SHALL
CONFORM TO THEIR REQUIREMENTS.
C. DISRUPTION OF NORMAL FACILITY ACTIVITIES ARE TO BE KEPT TO AN ABSOLUTE
MINIMUM. DUST, DEBRIS, AND FUMES SHALL BE CONTROLLED SO AS NOT TO AFFECT
THE HEALTH AND SAFETY OF OCCUPIED AREAS WITHIN THE FACILITY WHICH ARE
OUTSIDE THE AREA OF WORK. COORDINATE WITH THE ARCHITECT AND THE
OWNER'S REPRESENTATIVE WITH REGARD TO ALL ACTIVITIES TO BE CONDUCTED
OUTSIDE OF THE SUITE REMODEL AREA WHICH MAY AFFECT THE OPERATION OF THE
FACILITY.
D. THE CONTRACTOR SHALL PROVIDE TEMPORARY VENTILATION (MAINTAIN WORK ZONE
AT NEGATIVE PRESSURE), FILTRATION, AIR PURIFIERS, DUST SCREENS, ETC. FOR ALL
WORK AREAS AFFECTED BY DEMOLITION FOR NEW INSTALLATION TO MINIMIZE DUST
AND FUMES.
E. THE CONTRACTOR SHALL PRESENT AN AREA BY AREA WORK PLAN WELL IN ADVANCE
TO THE ARCHITECT AND THE OWNER'S AUTHORIZED REPRESENTATIVE FOR
APPROVAL PRIOR TO BEGINNING WORK. THE WORK PLAN SHALL INCLUDE AN
OUTLINE OF ALL ACTIVITIES OF ALL SUBCONTRACTORS. THE CONTRACTOR SHALL
COORDINATE WITH THE OWNER'S AUTHORIZED REPRESENTATIVE TO ESTABLISH
ACCEPTABLE ROUTING AND ACCESS WITHIN THE FACILITY FOR MATERIALS REQUIRED
FOR THE NEW INSTALLATION.
F. SEE SPECIFICATION SECTION 230593, TESTING, ADJUSTING, & BALANCING OR
MECHANICAL SYSTEMS FOR ADDITIONAL DESCRIPTION AND REQUIREMENTS.
G. ALL TEST AND MEASUREMENT TRAVERSE LOCATIONS SHALL BE CLEARLY NOTED ON
FLOOR PLANS WHICH SHALL BE INCLUDED WITH THE TEST AND MEASUREMENT DATA.
H. GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATION OF ALL TRADES
INCLUDING MECHANICAL, PLUMBING, ELECTRICAL, FURNITURE, AND ARCHITECTURAL.
ANY DISCREPANCIES SHALL BE REPORTED IMMEDIATELY TO THE ARCHITECT PRIOR
TO START OF WORK.
I. ALL NEW TO EXISTING DUCT CONNECTIONS SHALL BE FIELD VERIFIED PRIOR TO
ORDERING AND FABRICATING NEW DUCTWORK OR DAMPERS
GENERAL DEMO NOTES
GENERAL NOTESABBREVIATIONS
AHU AIR HANDLING UNIT
BRAKE HORSEPOWER
BTU PER HOUR
BRITISH THERMAL UNIT
BOTTOM OF DUCT
BOTTOM OF PIPE
ACOUSTIC LINING
ABOVE FINISHED FLOOR
ACCESS DOOR
COMPRESSED AIR
DRAIN
ENTERING
EXHAUST
CONTINUATION
DIRECT EXPANSION
CUBIC FEET PER MINUTE
CONDENSATE DRAIN
AL
AFF
AD
BHP
BOD
BTU
BOP
CA
CFM
D
DX
ENT
EXH
CD
EMCS
CONT.
BTUH
FLEXIBLE
FLAT BOTTOM
FILTER GAUGE
FLOOR SINK
FLOOR DRAIN
FAN COIL UNIT
DEGREES FAHRENHEIT
FEET PER MINUTE
FEET
FLAT TOP
HOSE BIBB
INCHES
GALLONS PER MINUTE
GALLONS PER HOUR
FB
°F
FD
FCU
F.G.
FS
FPM
FT.
FT
GPM
GPH
HB
HD
IN
HEPA
FLEX
KILOWATT
MAIN AIR (CONTROLS)
KILOWATT HOUR
OPPOSED BLADE DAMPER
OUTSIDE AIR
NUMBER (QUANTITY)
NOT IN CONTRACT
NOT APPLICABLE
MOTOR CONTROL CENTER
QUANTITY
QUADRANT
REVOLUTIONS PER MINUTE
RELATIVE HUMIDITY
SMOKE CONTROL DAMPER
RETURN AIR
PRESSURE REDUCING VALVE
KW
KWH
MA
MCC
NO.
NIC
OBD
OA
NA
PRV
PSIG
QTY
Rh
R.A.
RPM
SCD
QUAD
ENERGY MANAGEMENT CONTROL SYSTEM
HIGH EFFICIENCY PARTICULATE AIR (FILTER)
HAND DAMPER (VOLUME DAMPER)
POUNDS PER SQUARE INCH GAGE
TYPICAL
VOLTS
SOUND TRAP
VARIABLE AIR VOLUME
TOP OF PIPE TRAPEZE
VENT THRU ROOF
VELOCITY
ST
SP
TYP.
VAC
VAV
V
TP
VTR
VEL
SDVV
TOPT
SINGLE DUCT VARIABLE VOLUME
STATIC PRESSURE (INCHES OF WATER)
TOTAL PRESSURE (INCHES OF WATER)
VOLTS, ALTERNATING CURRENT
ACU AIR CONDITIONING UNIT
CONTRACTING OFFICER'S REPRESENTATIVECOR
RS
RL REFRIGERATION LIQUID
REFRIGERATION SUCTION
CONDENSING UNITCU
INDOOR UNITIU
DISCONNECT SWITCH, FUSED.
PROVIDE SWITCH AND FUSE AMPACITY EQUAL TO OR GREATER THAN FEEDER AMPACITY,
UON
ELECTRICAL EQUIPMENT SYMBOLS
on e-ei gh th ne fo ot on e-qu ar te r ne fo ot th re e-ei gh th s ne fo ot on e-ha lf ne fo ot th re e-qu ar te r ne fo ot in ch on e ne fo ot on e an d on e-ha lf ne fo ot th re e in es ne fo ot
REVISIONS DATE
General Notes:
GENERAL CONTRACTOR AND/OR ALL SUBCONTRACTORS SHALL FIELD VERIFY ALL DIMENSIONS SHOWN ON THESE PLANS AND SHALL BE RESPONSIBLE FOR VARIATIONS BETWEEN PLAN DIMENSIONS AND ACTUAL FIELD DIMENSIONS. WHERE VARIATIONS ARE FOUND TO OCCUR, THE CONTRACTOR SHALL NOTIFY THE PROJECT ENGINEER IN WRITING PRIOR TO PROCEEDING WITH CONSTRUCTION; NO ADJUSTMENT TO
THE WORK WILL BE MADE WITHOUT THE PRIOR APPROVAL OF THE PROJECT ENGINEER.
GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR GENERAL DEMOLITION INCLUDING REMOVAL OF WALLS, PARTITIONS, DOORS & CEILING & FLOORS. ANY AND ALL CUTTING OF CONCRETE FLOORS, WALLS OR STRUCTURE SHALL BE THE GENERAL CONTRACTOR'S RESPONSIBILITY. CORE DRILLING THROUGH CONCRETE WALLS, FLOORS OR STRUCTURE FOR PIPING OR CONDUIT SHALL BE THE RESPONSIBILITY OF THE SUBCONTRACTOR BY TRADE; FIRESTOPPING OF THESE OPENINGS SHALL BE DONE BY THE RESPECTIVE SUBCONTRACTOR. REMOVAL OF DEBRIS RESULTING FROM DEMOLITION, CUTTING, AND/OR DRILLING IS THE RESPONSIBILITY OF THE GENERAL CONTRACTOR. PATCHING AND REPAIR OF CONCRETE WALLS, FLOOR, OR STRUCTURE SHALL BE THE RESPONSIBILITY OF THE GENERAL CONTRACTOR; THIS WILL BE ACCOMPLISHED UPON COMPLETION OF THE INSTALLATION OF ANY AND ALL UTILITIES INSTALLED
BY THE VARIOUS SUBCONTRACTORS.
Approved: Division Chief
Issue Date Checked Drawn
DrawingNumber
Building Number
Project NumberDrawing Title Project Title
Location Drawing Scale
Approved: Service DirectorPlot Scale U.S. Department of Veterans Affairs
Office of Construction and Facilities Management
FULLY SPRINKLERED
Phase
A
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
321 4 5 6 7 8 9 10
B70
A/E:
TRIPLE C - The A/E Group
2508 29th Avenue NE
Minneapolis, MN 55418
(612) 355-1251
Mat Perkins
1/4" = 1'-0"
B
IM
/6
-2
-7
E
H R
M I n fr a s tr u c tu re U p g ra d e s M
P L S
V A
M C
/6 -2
-7
.M
E H
R M
.M E
P .G e n e ra l.
S h e e ts
.r v t
/5
/2
:2
:0
P
M
05/06/2022 M. Perkins G. Weaver
618-21-700
1383 - 70M-001
MECHANICAL ABBREVIATIONS AND
SYMBOLS
1 Veterans Drive, Minneapolis, MN 55417
EHRM INFRASTRUCTURE
UPGRADESFINAL BID DOCUMENTS
05/06/2022
File details come from the government source that posted it. Updated .