54-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf

PDF 91 KB Posted

Attached to
2500999 - Canterbury Storm Sewer Replacement State and local contract opportunity
Solicitation number
Not on record
Issued by
Montgomery County, Mount Aetna CDP, Pennsylvania

About this file

This is a Contract Closeout document related to Montgomery Township's Canterbury Storm Sewer Replacement project (Contract 2025-00999) in Pennsylvania. The project scope includes the removal and replacement of approximately 1,800 feet of corrugated metal pipe (CMP) ranging from 12 inches to 57 inches by 38 inches on Canterbury Lane and Devonshire Drive, construction of new circular HDPE pipe and elliptical RCP storm sewer systems, replacement of three precast concrete storm sewer structures, and restoration of concrete curb, sidewalk, driveway apron, and asphalt roadway. Sealed bids are due online via the PennBid Program by 10:00 A.M. on September 1, 2026, at which time bids will be publicly opened and read aloud at Township offices located at 1001 Stump Road, Montgomeryville, PA 18936. No pre-bid meeting will be held for this project. Bids may be withdrawn within two business days after opening.

Bid security equal to ten percent (10%) of the bid amount must accompany each bid submission, along with an Agreement of Surety certifying that required Performance and Payment Bonds will be provided to the awarded bidder. PennBid assesses a nominal fee of 0.33% of the bid amount (minimum $150, maximum $6,000) to awarded bidders only. All solicitation documents and details are available at no cost through the PennBid portal. This project is subject to Pennsylvania Act 422 (Prevailing Wage Act) as amended and Act 127 (Public Works Employment Verification) as amended, requiring compliance with prevailing minimum wage rates issued by the Pennsylvania Department of Labor and Industry.

View the file

Other files for this state and local contract opportunity

Other files attached to 2500999 - Canterbury Storm Sewer Replacement, newest first.
File Type Posted
3-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
49-Sec 32 13 13 - PORTLAND CEMENT CONCRETE PAVING.pdf PDF
9-Doc 00 43 13 - Bid Bond (penal sum form).pdf PDF
20-Sec 01 56 39 - LANDSCAPE PROTECTION.pdf PDF
30-Sec 32 92 00 - Finish Grading, Seeding and Sodding.pdf PDF
56-X1 - Site Map 2026-07-15.pdf PDF
4-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
24-Sec 31 20 00 - Earthwork.pdf PDF
5-Doc 00 41 00 - BID FORM - EBID.pdf PDF
6-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
15-Sec 01 33 00 - Submittals.pdf PDF
25-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID - 2025.pdf PDF
42-Sec 32 12 00 - ASPHALT CONCRETE PAVING.pdf PDF
17-Doc 00 73 00 5 - Appendix B - Public Works Employment Verification Form.pdf PDF
39-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
45-Doc 00 73 00 2 - Appendix A - Cover.pdf PDF
13-Doc 00 73 00 4 - Appendix B - Cover.pdf PDF
40-Doc 00 72 00 - GENERAL CONDITIONS - 2024.pdf PDF
41-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT - 2024.pdf PDF
55-X3 - Canterbury Details 2026-07-16.pdf PDF
33-Sec 01 40 00 - QUALITY CONTROL.pdf PDF
31-Doc 00 01 15 - TABLE OF CONTENTS - LIST OF DRAWINGS.pdf PDF
52-Sec 31 11 00 - CLEARING AND GRUBBING.pdf PDF
11-Doc 00 01 10 - TABLE OF CONTENTS.pdf PDF
18-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
44-Sec 32 01 16.71 - MILLING OF ASPHALT PAVEMENT SURFACE.pdf PDF
21-Doc 00 61 19 - Maintenance Bond.pdf PDF
32-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
16-Sec 31 22 10 - Topsoiling and Finish Grading.pdf PDF
14-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
36-Sec 33 41 00 - STORM DRAIN PIPE.pdf PDF
48-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
47-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
50-Sec 31 23 33 - EXCAVATION BACKFILL AND COMPACTION.pdf PDF
26-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
43-Sec 01 55 26 - TRAFFIC REGULATION - 2024.pdf PDF
10-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
23-Sec 03 20 00 - CONCRETE REINFORCEMENT.pdf PDF
8-Doc 00 52 00 - AGREEMENT.pdf PDF
58-Sec 01 22 00-MEASUREMENT AND PAYMENT 2026-07-13.pdf PDF
37-Sec 33 44 14 - STORM INLETS CATCH BASINS ENWALLS AND END SECTIONS.pdf PDF
35-Doc 00 62 76 - Application for Payment.pdf PDF
7-Doc 00 73 00 1 - SUPPLEMENTARY CONDITIONS - 2024.pdf PDF
1-Doc 00 63 63 - Change Order.pdf PDF
27-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
51-Sec 32 17 23.13 - Painted Traffic Lines and Markings.pdf PDF
29-Sec 31 37 16 - ENIGERY DISSIPATOR.pdf PDF
28-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
57-X2 - 12-14 18-19 of 24 Marked up As-Built Plans 2026-07-15.pdf PDF
2-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
Show all 50

2500999 - Canterbury Storm Sewer Replacement has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT CLOSEOUT

01 70 00-1

SECTION 01 70 00

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Closeout procedures.

2. Final cleaning.

3. Adjusting.

4. Project record documents.

5. Operation and maintenance manual.

6. Spare parts and maintenance Products.

7. Other documentation.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Section 01 50 00: Construction Facilities and Temporary Controls: Progress cleaning.

1.03 CLOSEOUT PROCEDURES

A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Engineer's review.

B. Engineer shall make a final inspection and prepare a punch list of items remaining to be completed or corrected prior to final acceptance in accordance with Article 14, paragraph

14.06 of the General Conditions.

C. Complete all items on the punch list, plus any new items that may be subsequently added, as soon as possible and within the Contract Time.

D. Provide submittals to Engineer that are required by governing or other authorities.

E. Submit final Application for Payment identifying total adjusted Contract Price, previous payments, and remaining amount due.

F. Final Payment will not be made until final completion and acceptance of the Work.

1.04 FINAL CLEANING

A. Execute final cleaning prior to final Project inspection.

B. Clean equipment and fixtures to a sanitary condition with cleaning materials appropriate to the surface and material being cleaned.

C. Clean or replace filters of operating equipment.

D. Clean debris from gutters and drainage systems.

E. Clean site; sweep paved areas, rake clean landscaped surfaces.

F. Remove waste and surplus materials, rubbish, and construction facilities from the site.

1.05 ADJUSTING

A. Adjust operating Products and equipment to ensure smooth and unhindered operation.

01 70 00-2

1.06 PROJECT RECORD DOCUMENTS

A. Maintain on-site one set of the following record documents; record actual revisions to the Work:

1. Drawings and Specifications.

2. Addenda.

3. Change Orders and other modifications to the Contract.

4. Reviewed Shop Drawings, Product data, and samples.

5. Manufacturer’s instructions for assembly, installation and adjusting.

B. Ensure entries are complete and accurate, enabling future reference by Owner.

C. Store record documents separate from documents used for construction.

D. Record information concurrent with construction progress.

E. Specifications: Legibly mark and record at each Product section description of actual Products installed, including the following:

1. Manufacturer's name and product model and number.

2. Product substitutions or alternates utilized.

3. Changes made by Addenda and modifications.

F. Record Drawings and Shop Drawings: Legibly mark each item to record actual construction including:

1. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.

2. Field changes of dimension and detail.

3. Details not on original Contract Drawings.

G. Submit documents to Engineer with claim for final Application for Payment.

1.07 OTHER DOCUMENTATION

A. Provide data and documentation properly completed and executed prior to final Application for Payment as Engineer may reasonably require including:

1. Payroll Certification forms by Contractor and all Subcontractors (if price exceeds $25,000).

2. PennDOT Form CS4171 – Certificate of Compliance for all asphalt materials

2. Waiver of Liens by all Subcontractors and Suppliers or Contractor's Affidavit, Contractor's Release of Liens and Consent of Surety to Final Payment.

3. Maintenance Bond.

4. Any Change Orders with supporting documentation which remain to be submitted.

5. Test and/or sample results.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION