21-Doc 00 61 19 - Maintenance Bond.pdf

PDF 119 KB Posted

Attached to
2500999 - Canterbury Storm Sewer Replacement State and local contract opportunity
Solicitation number
Not on record
Issued by
Montgomery County, Mount Aetna CDP, Pennsylvania

About this file

This is a Maintenance Bond document related to CONTRACT 2025-00999 for Canterbury Storm Sewer Replacement, a capital infrastructure project managed by Montgomery Township in Pennsylvania. The project involves the removal and replacement of approximately 1,800 feet of storm sewer on Canterbury Lane and Devonshire Drive, including removal of corrugated metal pipe ranging from 12 inches to 57 inches by 38 inches in diameter, installation of new circular HDPE pipe and elliptical RCP storm sewer, replacement of three precast concrete storm sewer structures, and restoration of concrete curb, sidewalk, driveway apron, and asphalt roadway. Sealed bids will be accepted online through the PennBid Program until 10:00 A.M. on September 1, 2026, with public opening and reading at Montgomery Township offices located at 1001 Stump Road, Montgomeryville, PA 18936. No pre-bid meeting will be held for this project.

Bid security in the amount of not less than ten percent (10%) of the bid amount is required, payable to Montgomery Township, along with an Agreement of Surety certifying that Performance and Payment Bonds will be provided. A nominal PennBid administrative fee of 0.33% of the bid amount (minimum $150, maximum $6,000) applies only to awarded bidders. The project is subject to Pennsylvania's Act 422 Prevailing Wage Act and Act 127 Public Works Employment Verification requirements. Bids may be withdrawn within two business days after bid opening. All solicitation documents and details are available at no cost through PennBid at https://pennbid.bonfirehub.com/.

View the file

Other files for this state and local contract opportunity

Other files attached to 2500999 - Canterbury Storm Sewer Replacement, newest first.
File Type Posted
27-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
51-Sec 32 17 23.13 - Painted Traffic Lines and Markings.pdf PDF
29-Sec 31 37 16 - ENIGERY DISSIPATOR.pdf PDF
28-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
57-X2 - 12-14 18-19 of 24 Marked up As-Built Plans 2026-07-15.pdf PDF
2-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
53-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
46-Sec 32 17 23.43 - ADA DETECTABLE WARNING TILES.pdf PDF
34-Sec 33 44 15 - BOXES AND ENDWALLS.pdf PDF
38-Doc 00 45 10 - BIDDERS ACKNOWLEDGEMENT FORM.pdf PDF
19-Sec 01 11 13-SUMMARY OF WORK.pdf PDF
22-Sec 02 41 16 - DEMOLITION.pdf PDF
12-Doc 00 11 13 - ADVERTISEMENT FOR BIDS - Canterbury Storm Sewer Replacement.pdf PDF
3-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
49-Sec 32 13 13 - PORTLAND CEMENT CONCRETE PAVING.pdf PDF
9-Doc 00 43 13 - Bid Bond (penal sum form).pdf PDF
20-Sec 01 56 39 - LANDSCAPE PROTECTION.pdf PDF
30-Sec 32 92 00 - Finish Grading, Seeding and Sodding.pdf PDF
56-X1 - Site Map 2026-07-15.pdf PDF
4-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
24-Sec 31 20 00 - Earthwork.pdf PDF
5-Doc 00 41 00 - BID FORM - EBID.pdf PDF
6-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
15-Sec 01 33 00 - Submittals.pdf PDF
25-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID - 2025.pdf PDF
42-Sec 32 12 00 - ASPHALT CONCRETE PAVING.pdf PDF
17-Doc 00 73 00 5 - Appendix B - Public Works Employment Verification Form.pdf PDF
39-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
45-Doc 00 73 00 2 - Appendix A - Cover.pdf PDF
13-Doc 00 73 00 4 - Appendix B - Cover.pdf PDF
40-Doc 00 72 00 - GENERAL CONDITIONS - 2024.pdf PDF
41-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT - 2024.pdf PDF
55-X3 - Canterbury Details 2026-07-16.pdf PDF
33-Sec 01 40 00 - QUALITY CONTROL.pdf PDF
31-Doc 00 01 15 - TABLE OF CONTENTS - LIST OF DRAWINGS.pdf PDF
52-Sec 31 11 00 - CLEARING AND GRUBBING.pdf PDF
11-Doc 00 01 10 - TABLE OF CONTENTS.pdf PDF
18-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
44-Sec 32 01 16.71 - MILLING OF ASPHALT PAVEMENT SURFACE.pdf PDF
32-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
16-Sec 31 22 10 - Topsoiling and Finish Grading.pdf PDF
14-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
36-Sec 33 41 00 - STORM DRAIN PIPE.pdf PDF
48-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
47-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
50-Sec 31 23 33 - EXCAVATION BACKFILL AND COMPACTION.pdf PDF
26-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
43-Sec 01 55 26 - TRAFFIC REGULATION - 2024.pdf PDF
10-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
23-Sec 03 20 00 - CONCRETE REINFORCEMENT.pdf PDF
Show all 50

2500999 - Canterbury Storm Sewer Replacement has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MAINTENANCE BOND

00 61 19-1

DOCUMENT 00 61 19

KNOW ALL MEN BY THESE PRESENTS, that We, hereinafter called the "Principal" and hereinafter called the "Surety" are held and firmly bound unto hereinafter called the “Obligee” in the sum of Dollars ($ ), the payment of which sum, well and truly to be made, we, the said Principal and the said Surety, bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.

WHEREAS, the said Principal has heretofore entered into an

Agreement with said Obligee dated________________________, 20___ for Contract 2025-00999:

Montgomery Township – Canterbury Storm Sewer Replacement, and;

WHEREAS, the said Agreement provides that the said Principal is required to furnish the said Obligee with a Maintenance Bond for 15% of the Agreement price, indemnifying the said Obligee against defects in materials or workmanship for a period of eighteen (18) month(s) after final completion and acceptance of the Work.

NOW, THEREFORE, the condition of this obligation is such, that if the said Principal shall faithfully carry out and perform the said guarantee, and shall, on due notice, repair and make good at its own expense any and all defects in materials or workmanship in the said work which may develop during the said maintenance period or shall pay over, make good and reimburse to the said Obligee all loss and damage which said Obligee may sustain by reason of failure or default of said Principal so to do, then this obligation shall be null and void; otherwise shall remain in full force and effect.

00 61 19-2

Any action filed under the bond must be commenced in the Montgomery County Court of Common Pleas or the United States District Court for the Eastern District of Pennsylvania. This is a legal requirement and not subject to negotiation or change.

Signed and sealed this___________ day of__________________, 20___.

CONTRACTOR AS PRINCIPAL SURETY

Company: Company:

Signature: Signature:

Name and Title: Name and Title:

(Corp. Seal) (Corp. Seal)

NOTE: This statement, if executed by any person other than the President or Vice President of the

Surety Company, must be accompanied by a current and effective certificate showing authority conferred upon the person so signing to execute such instruments on behalf of the Surety Company represented.

END OF DOCUMENT

File details come from the government source that posted it. Updated .