This is a Quality Control specification document for Montgomery Township's Canterbury Storm Sewer Replacement project in Pennsylvania. The project involves the removal and replacement of approximately 1,800 feet of corrugated metal pipe (CMP) ranging from 12 inches to 57 inches by 38 inches, installation of new circular HDPE pipe and elliptical RCP storm sewer on Canterbury Lane and Devonshire Drive, replacement of three precast concrete storm sewer structures, and restoration of concrete curb, sidewalk, driveway aprons, and asphalt roadway. Sealed bids are due online via the PennBid Program by 10:00 A.M. on September 1, 2026, with public opening and reading of bids at the Township offices located at 1001 Stump Road, Montgomeryville, PA 18936. No pre-bid meeting will be held for this project. Bids may be withdrawn within two business days after the opening of bids.

Bid security in an amount not less than ten percent of the bid amount, payable to Montgomery Township, must accompany each bid along with an Agreement of Surety certifying that required Performance and Payment Bonds will be provided. PennBid assesses a nominal fee of 0.33 percent of the bid amount (minimum $150 and maximum $6,000) only to awarded bidders. The project is subject to Pennsylvania's Act 422 Prevailing Wage Act and Act 127 Public Works Employment Verification requirements, necessitating compliance with prevailing minimum wage rates issued by the Pennsylvania Department of Labor and Industry. All solicitation documents are available at no cost through the PennBid platform.

View the file

Other files for this state and local contract opportunity

Other files attached to 2500999 - Canterbury Storm Sewer Replacement, newest first.
File Type Posted
3-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
49-Sec 32 13 13 - PORTLAND CEMENT CONCRETE PAVING.pdf PDF
9-Doc 00 43 13 - Bid Bond (penal sum form).pdf PDF
20-Sec 01 56 39 - LANDSCAPE PROTECTION.pdf PDF
30-Sec 32 92 00 - Finish Grading, Seeding and Sodding.pdf PDF
56-X1 - Site Map 2026-07-15.pdf PDF
4-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
24-Sec 31 20 00 - Earthwork.pdf PDF
5-Doc 00 41 00 - BID FORM - EBID.pdf PDF
6-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
15-Sec 01 33 00 - Submittals.pdf PDF
25-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID - 2025.pdf PDF
42-Sec 32 12 00 - ASPHALT CONCRETE PAVING.pdf PDF
17-Doc 00 73 00 5 - Appendix B - Public Works Employment Verification Form.pdf PDF
39-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
45-Doc 00 73 00 2 - Appendix A - Cover.pdf PDF
13-Doc 00 73 00 4 - Appendix B - Cover.pdf PDF
43-Sec 01 55 26 - TRAFFIC REGULATION - 2024.pdf PDF
10-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
23-Sec 03 20 00 - CONCRETE REINFORCEMENT.pdf PDF
8-Doc 00 52 00 - AGREEMENT.pdf PDF
54-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
58-Sec 01 22 00-MEASUREMENT AND PAYMENT 2026-07-13.pdf PDF
37-Sec 33 44 14 - STORM INLETS CATCH BASINS ENWALLS AND END SECTIONS.pdf PDF
35-Doc 00 62 76 - Application for Payment.pdf PDF
7-Doc 00 73 00 1 - SUPPLEMENTARY CONDITIONS - 2024.pdf PDF
1-Doc 00 63 63 - Change Order.pdf PDF
40-Doc 00 72 00 - GENERAL CONDITIONS - 2024.pdf PDF
41-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT - 2024.pdf PDF
55-X3 - Canterbury Details 2026-07-16.pdf PDF
31-Doc 00 01 15 - TABLE OF CONTENTS - LIST OF DRAWINGS.pdf PDF
52-Sec 31 11 00 - CLEARING AND GRUBBING.pdf PDF
11-Doc 00 01 10 - TABLE OF CONTENTS.pdf PDF
18-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
44-Sec 32 01 16.71 - MILLING OF ASPHALT PAVEMENT SURFACE.pdf PDF
21-Doc 00 61 19 - Maintenance Bond.pdf PDF
32-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
16-Sec 31 22 10 - Topsoiling and Finish Grading.pdf PDF
14-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
36-Sec 33 41 00 - STORM DRAIN PIPE.pdf PDF
48-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
47-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
50-Sec 31 23 33 - EXCAVATION BACKFILL AND COMPACTION.pdf PDF
26-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
27-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
51-Sec 32 17 23.13 - Painted Traffic Lines and Markings.pdf PDF
29-Sec 31 37 16 - ENIGERY DISSIPATOR.pdf PDF
28-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
57-X2 - 12-14 18-19 of 24 Marked up As-Built Plans 2026-07-15.pdf PDF
2-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
Show all 50

2500999 - Canterbury Storm Sewer Replacement has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUALITY CONTROL

01 40 00-1

SECTION 01 40 00

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Quality assurance - Control of installation.

2. Tolerances.

3. References and standards.

4. Mock-up.

5. Testing laboratory services.

6. Observation services.

7. Manufacturers' field services.

8. Examination.

9. Preparation.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Document 00 72 00: General Conditions: References to Standards and Specifications of Technical Societies; Reporting and Resolving Discrepancies.

2. Document 00 73 00: Supplementary Conditions: Duties, Responsibilities and Limitation of Authority of the Resident Project Representative.

3. Section 01 42 13: Organization and Reference Acronyms

4. Section 01 60 00: Material and Equipment: Requirements for material and product quality.

1.03 QUALITY ASSURANCE-CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, Products, services, site conditions, and workmanship, to produce Work of specified quality.

B. Comply fully with manufacturers' instructions, including each step in sequence.

C. Should manufacturers' instructions conflict with Contract Documents, request clarification from Engineer before proceeding.

D. Comply with specified standards as minimum quality for the Work except when more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

E. Perform Work by persons qualified to produce required and specified quality.

F. Verify that field measurements are as indicated on shop drawings or as instructed by the manufacturer.

G. Secure Products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion or disfigurement.

1.04 TOLERANCES

A. Monitor fabrication and installation tolerance control of Products to produce acceptable Work. Do not permit tolerances to accumulate.

B. Comply with manufacturers’ tolerances. Should manufacturers’ tolerances conflict with Contract Documents, request clarification from Engineer before proceeding.

01 40 00-2

C. Adjust Products to appropriate dimensions; position before securing Products in place.

1.05 REFERENCES AND STANDARDS

A. For Products or workmanship specified by association, trade or other consensus standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.

B. Conform to reference standard by date of issue current on date for receiving bids, except where a specific date is established by code.

C. Obtain copies of standards where required by Product specification sections.

D. Should specified reference standard conflict with Contract Documents, request clarification from Engineer before proceeding.

E. Neither the contractual relationships, duties, or responsibilities of the parties in Contract nor those of Engineer shall be altered from the Contract Documents by mention or inference otherwise in any reference document.

1.06 MOCK-UP

A. Tests will be performed under provisions identified in this section and identified in the respective Product specification sections.

B. Assemble and erect specified items with specified attachment and anchorage devices, flashings, seals, and finishes.

C. Accepted mock-ups shall be a comparison standard for the remaining Work.

D. Where mock-up has been accepted by Engineer and is specified in Product specification sections to be removed; remove mock-up and clear area when directed to do so.

1.07 TESTING LABORATORY SERVICES

A. Contractor shall furnish to Engineer duplicate certified copies of all routine tests made by the mill, shop or factory at which material or equipment is fabricated or manufactured for the Work when so specified in individual specification sections.

B. An independent firm will perform tests and other services when so specified in individual specification sections and as required by Engineer.

C. Testing and source quality control may occur on or off the Project site. Perform off-site testing as required by Engineer.

D. Reports will be submitted by the independent firm to Engineer, in duplicate, indicating observations and results of tests and indicating compliance or non-compliance with Contract Documents.

E. Cooperate with independent firm; furnish samples of materials, design mix, equipment, tools, storage, safe access and assistance by incidental labor as requested.

F. Notify Engineer and independent firm 24 hours prior to expected time for operations requiring services.

G. Make arrangements with independent firm and pay for additional samples and tests required for Contractor's use.

H. Testing does not relieve Contractor to perform Work to contract requirements.

I. Retesting required because of non-conformance to specified requirements shall be performed by the same independent firm on instructions by Engineer.

01 40 00-3

J. Contractor shall pay for all testing and laboratory services and/or test reports as are required in individual specification sections.

1.08 OBSERVATION SERVICES

A. Owner will employ and pay for observation services during construction of the Project.

B. Cooperate with construction observer; furnish safe access and assistance by incidental labor as requested.

1. Notify construction observer 24 hours prior to expected time for operations requiring services.

C. Observation does not relieve Contractor to perform Work to contract requirements.

1.09 MANUFACTURERS' FIELD SERVICES

A. When specified in individual specification sections, require material or Product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, workmanship, start-up of equipment, test, adjust and balance of equipment, and to initiate instructions when necessary.

B. Report observations and site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturers’ written instructions.

C. Refer to Section 01 33 00 - Submittals, Manufacturers’ field reports article.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 EXAMINATION

A. Verify that existing site conditions and substrate surfaces are acceptable for subsequent Work.

Beginning new Work means acceptance of existing conditions.

B. Verify that existing substrate is capable of structural support or attachment of new Work being applied or attached.

C. Examine and verify specific conditions described in individual specification sections.

D. Verify that utility services are available, of the correct characteristics, and in the correct locations.

3.02 PREPARATION

A. Clean substrate surfaces prior to applying next material or substance.

B. Seal cracks or openings of substrate prior to applying next material or substance.

C. Apply manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying any new material or substance in contact or bond.