22-Sec 02 41 16 - DEMOLITION.pdf

PDF 135 KB Posted

Attached to
2500999 - Canterbury Storm Sewer Replacement State and local contract opportunity
Solicitation number
Not on record
Issued by
Montgomery County, Mount Aetna CDP, Pennsylvania

About this file

This is a Demolition specification document (Section 02 41 16) for Montgomery Township's Canterbury Storm Sewer Replacement project in Pennsylvania. The work scope includes the removal of all designated structures and associated facilities in accordance with the project's construction sequence, with specific requirements for minimizing interference with adjacent building areas, maintaining protected egress and access, and managing dust control. The project involves the demolition and removal of approximately 1,800 feet of corrugated metal pipe (CMP) ranging from 12 inches to 57 inches by 38 inches, along with other storm sewer infrastructure on Canterbury Lane and Devonshire Drive. The contractor is responsible for locating and protecting existing active utilities, with requirements to contact the Pennsylvania One Call System at least three days prior to excavation work per Pennsylvania Act 172. No pre-bid meeting will be held for this project, and sealed bids must be submitted electronically via the PennBid Program by 10:00 A.M. on September 1, 2026, with public opening at Montgomery Township offices at 1001 Stump Road, Montgomeryville, PA 18936.

All demolished materials must be promptly removed from the site and disposed of in a legal manner at state-approved disposal areas, with the contractor bearing responsibility for debris removal costs. The contractor is required to restore any disturbances to existing facilities and improvements resulting from demolition work at no extra cost to the owner, including restoration of concrete curb, sidewalk, driveway apron, and asphalt roadway. Bid security must be submitted in an amount not less than ten percent (10%) of the bid amount, with a PennBid fee of 0.33% of the bid amount (minimum $150, maximum $6,000) assessed only to awarded bidders. The project is subject to Pennsylvania Act 422 (Prevailing Wage Act) and Act 127 (Public Works Employment Verification), and the contractor must provide Performance and Payment Bonds as required by the Agreement of Surety.

View the file

Other files for this state and local contract opportunity

Other files attached to 2500999 - Canterbury Storm Sewer Replacement, newest first.
File Type Posted
3-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
49-Sec 32 13 13 - PORTLAND CEMENT CONCRETE PAVING.pdf PDF
9-Doc 00 43 13 - Bid Bond (penal sum form).pdf PDF
20-Sec 01 56 39 - LANDSCAPE PROTECTION.pdf PDF
30-Sec 32 92 00 - Finish Grading, Seeding and Sodding.pdf PDF
56-X1 - Site Map 2026-07-15.pdf PDF
4-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
24-Sec 31 20 00 - Earthwork.pdf PDF
5-Doc 00 41 00 - BID FORM - EBID.pdf PDF
6-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
15-Sec 01 33 00 - Submittals.pdf PDF
25-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID - 2025.pdf PDF
42-Sec 32 12 00 - ASPHALT CONCRETE PAVING.pdf PDF
17-Doc 00 73 00 5 - Appendix B - Public Works Employment Verification Form.pdf PDF
39-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
45-Doc 00 73 00 2 - Appendix A - Cover.pdf PDF
13-Doc 00 73 00 4 - Appendix B - Cover.pdf PDF
40-Doc 00 72 00 - GENERAL CONDITIONS - 2024.pdf PDF
41-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT - 2024.pdf PDF
55-X3 - Canterbury Details 2026-07-16.pdf PDF
33-Sec 01 40 00 - QUALITY CONTROL.pdf PDF
31-Doc 00 01 15 - TABLE OF CONTENTS - LIST OF DRAWINGS.pdf PDF
52-Sec 31 11 00 - CLEARING AND GRUBBING.pdf PDF
11-Doc 00 01 10 - TABLE OF CONTENTS.pdf PDF
18-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
44-Sec 32 01 16.71 - MILLING OF ASPHALT PAVEMENT SURFACE.pdf PDF
21-Doc 00 61 19 - Maintenance Bond.pdf PDF
32-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
16-Sec 31 22 10 - Topsoiling and Finish Grading.pdf PDF
14-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
36-Sec 33 41 00 - STORM DRAIN PIPE.pdf PDF
48-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
47-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
50-Sec 31 23 33 - EXCAVATION BACKFILL AND COMPACTION.pdf PDF
26-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
43-Sec 01 55 26 - TRAFFIC REGULATION - 2024.pdf PDF
10-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
23-Sec 03 20 00 - CONCRETE REINFORCEMENT.pdf PDF
8-Doc 00 52 00 - AGREEMENT.pdf PDF
54-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
58-Sec 01 22 00-MEASUREMENT AND PAYMENT 2026-07-13.pdf PDF
37-Sec 33 44 14 - STORM INLETS CATCH BASINS ENWALLS AND END SECTIONS.pdf PDF
35-Doc 00 62 76 - Application for Payment.pdf PDF
7-Doc 00 73 00 1 - SUPPLEMENTARY CONDITIONS - 2024.pdf PDF
1-Doc 00 63 63 - Change Order.pdf PDF
27-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
51-Sec 32 17 23.13 - Painted Traffic Lines and Markings.pdf PDF
29-Sec 31 37 16 - ENIGERY DISSIPATOR.pdf PDF
28-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
57-X2 - 12-14 18-19 of 24 Marked up As-Built Plans 2026-07-15.pdf PDF
Show all 50

2500999 - Canterbury Storm Sewer Replacement has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEMOLITION

02 41 16-1

SECTION 02 41 16

PART 1 - GENERAL

1.01 WORK INCLUDED

A. Remove all items shown on the Drawings in accordance with the Sequence of Construction in Section 01 11 13 including the following:

1. Remove designated structures and associated facilities.

1.02 RELATED WORK

A. Section 01 11 13: Summary of Work B. Section 01 70 00: Contract Closeout: Project record documents.

C. Section 31 23 33: Excavation, Backfill and Compaction

1.03 SUBMITTALS

A. Submit demolition and removal procedures and schedule under provisions of Section 01 33 00 if Contractor proposes to use procedures and schedule which are not in accordance with those procedures and schedule presented in the Work Sequence portion of Section

01 11 13.

1.04 EXISTING CONDITIONS

A. Conduct demolition to minimize interference with adjacent building areas. Maintain protected egress and access at all times.

B. Provide, erect, and maintain temporary barriers and security devices.

B. Satisfactorily prevent of control dust resulting from demolition.

C. Comply with the National Emission Standard for Asbestos, as contained in the Federal

Register, Volume 38, No. 66.

D. Traffic

1. Conduct site preparation, removals and salvaging operations to ensure minimum interference with roads, streets, walks and other adjacent occupied or used facilities. Do not close or obstruct streets, walks or other occupied or used facilities without permission from authorities having jurisdiction.

E. Protection

1. Contractor shall be responsible for the protection of existing facilities and improvements, indicated to remain in place, within the area of the site where his work is being done.

2. Contractor shall be responsible for the protection of existing facilities on adjoining properties.

3. Any disturbances to the work and improvements or any impairments of facilities resulting from work of this Section, shall be promptly restored, repaired or replaced at no extra

02 41 16-2 cost to the owner.

F. Protection of Existing Utilities

1. Pursuant to the requirements of Pennsylvania Act 172, the Contractor shall contact the Pennsylvania One Call System at 1-800-242-1776 at least three days prior to any excavation work.

2. Utility companies owning services that will be affected by alteration and removal of demolition work shall be notified in advance according to the requirements of the utility.

3. The existence and location of underground utilities are not guaranteed and shall be investigated and verified in the field by the Contractor before starting work. Excavation in the vicinity of the existing utilities shall be carried on with extreme caution. Utilities encountered on the Owner's property are to be maintained in existing condition unless otherwise indicated on the drawings. All existing underground utilities, storm piping and associated structures designated for removal shall be completely removed in accordance with the utility company or agency having jurisdiction. Underground utilities designated to be abandoned in place shall be properly plugged and abandoned in accordance with the regulations of the utility company or agency having jurisdiction. Material removed shall be disposed of off-site in a lawful manner.

PART 2 - PRODUCTS

2.01 GENERAL

A. Products and materials utilized in this item of work shall be subject to the approval of the Owner’s representative.

2.02 RESTORATION

A. Products and materials used in restoration and repair of private and public property shall be of a quality equal to or better than the original project or material.

PART 3 - EXECUTION

3.01 PREPARATION

A. Locate existing active utilities and verify whether each utility will remain in service and therefore requires protection of is part of the demolition and removal activity.

B. Protect existing items which are not indicated to be altered.

C. Prior to starting work make arrangements with the proper authorities for turning off and disconnecting utilities in conjunction with demolition activities. Disconnect, remove, and cap designated utility services within demolition areas. Mark location of disconnected utilities.

Identify and indicate capping locations on Project Record Documents.

D. Visit the premises and verify all conditions covering the work of this Section and verify all dimensions. Examine all drawings covering the work of this Section and refer to all other drawings that may affect the work of this Section or require coordination with other trades.

Before starting the work of this Section, make a thorough examination of all portions of the premises in which the work of this Section is to be performed. Check all of the work adjoining, adjacent to, and underlying the locations where the work of this Section is to be performed. Report to the Engineer any and all conditions that may interfere with or otherwise affect or prevent the proper execution and/or completion of the work of this Section. Do not

02 41 16-3 commence work until any and all such conditions have been corrected by the trade or trades responsible.

E. Demolish in an orderly and careful manner. Protect any existing structures to remain from damage.

F. Do not disturb existing paving unless it becomes necessary to do so in order to complete other work.

G. Except where noted otherwise, immediately remove demolished materials from site.

H. Remove materials to be re installed or retained in manner to prevent damage.

I. Remove and promptly dispose of contaminated, vermin infested, or dangerous materials encountered.

J. Remove demolished materials from site as work progresses. Upon completion of work, leave areas of work in clean condition.

K. In the event of discrepancy, immediately notify the Engineer. Do not proceed with work of this Section in areas of discrepancy until all such discrepancies have been fully resolved.

Should any work performed under this Section expose previously unknown major conditions, all work shall be stopped and the matter reported immediately to the Engineer for instructions. However, the Contractor shall use any measures necessary to insure adequate safety conditions.

L. Appropriate erosion and sediment control measures (as shown on the Contract Drawings) should be installed prior to commencement of work of this Section.

3.03 CLEAN-UP

A. Execute work in such a manner as to avoid interference with, use of, or passage to and from adjoining spaces and facilities. Do not burn materials or debris on premises. Remove from the site all rubbish and debris resulting from work of this Section.

B. Do not allow the accumulation of scraps and debris arising from the work of this Section.

Maintain the premises in a neat and orderly condition at all times. Daily clean-up of construction areas is required.

3.04 DISPOSAL OF DEBRIS

A. All items of demolition within the contract limits, including stones, rubbish, utility lines and fixtures, plant material, and similar items shall be, unless otherwise directed, the Contractor's property and shall promptly be removed from the site and disposed of in a legal manner, in a state approved disposal area.

END OF SECTION

File details come from the government source that posted it. Updated .