This is a Contract Considerations document for Montgomery Township, Pennsylvania, related to Contract 2025-00999 for Canterbury Storm Sewer Replacement. The project involves removal and replacement of approximately 1,800 feet of storm sewer on Canterbury Lane and Devonshire Drive, including removal of corrugated metal pipe (CMP) ranging from 12 inches through 57 inches x 38 inches, installation of new circular HDPE pipe and elliptical RCP storm sewer, replacement of three precast concrete storm sewer structures, and restoration of concrete curb, sidewalk, driveway apron, and asphalt roadway. Sealed bids will be received online through the PennBid Program until 10:00 A.M. on September 1, 2026, at which time bids will be publicly opened and read aloud at the Township offices located at 1001 Stump Road, Montgomeryville, PA 18936. No pre-bid meeting will be held for this project. All solicitation documents and details are available at no cost on PennBid at https://pennbid.bonfirehub.com/.
Each bid must include bid security in an amount not less than ten percent (10%) of the bid amount payable to Montgomery Township, along with an Agreement of Surety certifying that required Performance and Payment Bonds will be provided. A nominal fee of 0.33% of the bid amount (minimum $150 and maximum $6,000) is assessed by PennBid only to awarded bidders. The project is subject to Pennsylvania Act 422 (Prevailing Wage Act) and Act 127 (Public Works Employment Verification). Bids may be withdrawn within two (2) business days after the opening of bids.
View the file
Other files for this state and local contract opportunity
Show all 50
2500999 - Canterbury Storm Sewer Replacement has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT CONSIDERATIONS
01 29 00-1
SECTION 01 29 00
PART 1 GENERAL
1.01 SECTION DESCRIPTION
A. The Work of This Section Includes:
1. Schedule of values.
2. Application for payment.
3. Change procedures.
4. Alternates.
1.02 RELATED SECTIONS
A. Related Work Specified Elsewhere:
1. Document 00 52 00: Agreement: Contract Price
2. Section 01 22 00: Measurement and Payment
3. Section 01 60 00: Material and Equipment: Product substitutions and options.
1.03 SCHEDULE OF VALUES
A. Submit a printed schedule on Contractor's standard form or electronic media printout.
B. Submit preliminary Schedule of Values in duplicate within 10 days after Effective Date of the Agreement.
C. Format: See Supplementary Conditions
D. Include in each line item, the amount of allowance. For unit cost allowances, identify quantities taken from Contract Documents multiplied by the unit cost to achieve the total for the item.
E. Include within each line item, a direct proportional amount of Contractor's overhead and profit.
F. Revise schedule to list approved Change Orders, with each Application for Payment.
1.04 APPLICATIONS FOR PAYMENT
A. Submit three (3) copies of each application on EJCDC Form C-620 (Document 00 62 76).
B. Content and Format: Utilize Schedule of Values for listing items in Application for Payment.
C. Payment Period: Monthly
D. Waiver of Liens or Contractor's Affidavit, Contractor's Release and Statement of Surety Company (with Final Payment Application only)
E. Include Payroll Certification forms with each Payment Application.
F. Include PennDOT Form CS4171 Certificate of Compliance for all asphalt materials
F. Include an updated construction progress schedule.
1.05 CHANGE PROCEDURES
A. Engineer will advise of minor changes in the Work not involving an adjustment to Contract
Price or Contract Time as authorized by Paragraph 9.5 of the General Conditions by issuing
01 29 00-2 supplemental instructions.
B. Engineer may issue a Proposal Request which includes a detailed description of a proposed change with supplementary or revised Drawings and specifications. Contractor will prepare and submit an estimate within 15 days relative to changes in Contract Price and/or Contract Time.
C. Contractor may propose changes by submitting a request for change to Engineer, describing the proposed change and its full effect on the Work. Include a statement describing the reason for the change, and the effect on the Contract Price and Contract Time with full documentation and a statement describing effect on Work by any other contractors. Document any requested substitutions in accordance with Section 01 60 00.
D. Stipulated Price Change Order: Based on Proposal Request and Contractor's fixed price quotation or Contractor's request for a Change Order as approved by Engineer.
E. Unit Price Change Order: For contract unit prices and quantities, the Change Order will be executed on a fixed unit price basis. For unit costs or quantities of units of work which are not predetermined, the Change Order will be executed based on Contractor's proposed unit prices and quantities of units as approved by Engineer.
F. Work Change Directive: Engineer may issue a directive, on EJCDC Form C-940 Work Change
Directive signed by Owner, instructing Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order. Document will describe changes in the Work, and designate method of determining any change in Contract Price or Contract Time. Promptly execute the change.
G. Time and Material Change Order: Submit itemized account and supporting data after completion of change, within time limits indicated in the Conditions of the Contract. Engineer will determine the change allowable in Contract Price and Contract Time as provided in the Contract Documents.
H. Maintain detailed records of Work done on Time and Material basis. Provide full information required for evaluation of proposed changes, and to substantiate costs for changes in the Work.
I. Change Order Form: EJCDC Form C-941 (Document 00 63 63).
J. Execution of Change Orders: Engineer will issue Change Orders for signatures of parties as provided in the Conditions of the Contract.
1.06 ALTERNATES
A. Accepted Project alternates will be identified in the Agreement.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION