39-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf
PDF 89 KB Posted
- Attached to
- 2500999 - Canterbury Storm Sewer Replacement State and local contract opportunity
- Solicitation number
- Not on record
- Issued by
- Montgomery County, Mount Aetna CDP, Pennsylvania
About this file
This is a Specification Section document for Construction Facilities and Temporary Controls prepared for Montgomery Township's Canterbury Storm Sewer Replacement project in Pennsylvania. The specification outlines the contractor's responsibilities for managing temporary utilities, controls, and facilities throughout the construction of storm sewer replacement work on Canterbury Lane and Devonshire Drive. The project scope includes removal of approximately 1,800 feet of corrugated metal pipe (CMP) in sizes ranging from 12 inches to 57 inches by 38 inches, installation of new circular HDPE pipe and elliptical RCP storm sewer, replacement of three precast concrete storm sewer structures, and restoration of concrete curb, sidewalk, driveway apron, and asphalt roadway. Sealed bids are due online via PennBid by 10:00 A.M. on September 1, 2026, with public opening at Montgomery Township offices located at 1001 Stump Road, Montgomeryville, Pennsylvania 18936. No pre-bid meeting is scheduled for this project.
The specification requires the contractor to provide and pay for temporary electricity from utility sources, temporary sanitary facilities, barriers to prevent unauthorized entry, water control and dust control measures, progress cleaning and waste removal, and project security at no additional cost to the owner. The contractor must maintain the construction site free of debris, implement dust control measures as directed by the Resident Project Representative, protect landscaped areas and existing facilities from damage, and restore all temporary facilities and permanent facilities used during construction to their original condition. Bid security of not less than ten percent of the bid amount is required, along with an Agreement of Surety certifying that Performance and Payment Bonds will be provided. The project is subject to Pennsylvania's Act 422 Prevailing Wage Act and Act 127 Public Works Employment Verification requirements. A nominal fee of 0.33 percent of the bid amount (minimum $150, maximum $6,000) applies only to awarded bidders through the PennBid platform.
View the file
Other files for this state and local contract opportunity
Show all 50
2500999 - Canterbury Storm Sewer Replacement has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
01 50 00-1
SECTION 01 50 00
PART 1 GENERAL
1.01 GENERAL
A. The Work of this Section shall be the responsibility of the contractor as noted in the Summary of Work (Section 01 11 13).
1.02 SECTION INCLUDES
A. Temporary Utilities: Electricity and sanitary facilities.
B. Temporary Controls: Barriers, protection of the Work, water control and dust control.
C. Construction Facilities: Progress cleaning and project signage.
1.03 RELATED SECTIONS
A. Section 01 55 26: Traffic Regulation.
B. Section 01 70 00: Contract Closeout: Final cleaning.
1.04 TEMPORARY ELECTRICITY
A. Cost: By Contractor; provide and pay for power service required from utility source.
1.05 TEMPORARY SANITARY FACILITIES
A. Provide and maintain required facilities and enclosures. Existing facility use is not permitted.
Provide at time of project mobilization.
B. At end of construction, return facilities to same or better condition than originally found.
1.06 BARRIERS
A. Provide barriers to prevent unauthorized entry to construction areas and to protect existing facilities and adjacent properties from damage from construction operations.
B. Provide protection for plants designated to remain. Replace damaged plants.
C. Protect non-owned vehicular traffic, stored materials, site, and structures from damage.
1.07 WATER CONTROL
A. Grade site to drain. Maintain excavations free of water. Provide, operate, and maintain pumping equipment.
B. Protect site from ponding or running water.
1.08 PROTECTION OF INSTALLED WORK
A. Protect installed Work and provide special protection where specified in individual specification sections.
B. Prohibit traffic from landscaped areas.
1.09 SECURITY
A. Provide security and facilities to protect Work, and Owner's operations from unauthorized entry, vandalism, or theft.
01 50 00-2
1.10 PROGRESS CLEANING AND WASTE REMOVAL
A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in a clean and orderly condition.
B. Collect and remove waste materials, debris, and rubbish from site daily and dispose off-site.
C. Open free-fall chutes are not permitted. Terminate closed chutes into appropriate containers with lids.
1.11 PROJECT IDENTIFICATION
A. No other signs are allowed without Owner permission except those required by law.
1.12 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS
A. Clean and repair damage caused by installation or use of temporary work.
B. Restore existing facilities used during construction to original condition. Restore permanent facilities used during construction to specified condition.
1.13 DUST CONTROL
A. Execute Work by methods to minimize raising dust from construction operations.
B. Provide positive means (i.e. use of sprinkling water or other methods approved by the Resident Project Representative) to prevent air-borne dust from dispersing into atmosphere.
C. Dust control measures shall be employed when required in the opinion of the Resident Project Representative at no additional cost to Owner.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION
File details come from the government source that posted it. Updated .