This is a specification section for construction submittals applicable to the Canterbury Storm Sewer Replacement project in Montgomery Township, Pennsylvania. The specification establishes comprehensive procedures for contractor submissions throughout the project lifecycle, including construction progress schedules, product data, shop drawings, samples, design data, test reports, certificates, manufacturer's instructions, field reports, and erection drawings. Contractors must submit a preliminary progress schedule within 10 days after the effective date of the agreement, with a final schedule required within 10 days of the preconstruction conference. All submittals must be sequentially numbered, transmitted to the engineer for review with 15 days allowed for examination (excluding delivery time), and identified with project information, contractor certification, and any variations from contract documents. The specification requires contractors to submit the number of copies needed plus three additional copies for the engineer's retention, with revised submittals clearly identifying all changes from previous submissions.

The submittal procedures outlined in this specification section establish quality control and documentation standards but do not specify pricing terms, set-asides, or funding information. Product data, shop drawings, and samples submitted for review are limited to checking conformance with contract documents and design concepts, while samples for selection address aesthetic, color, or finish choices at the engineer's discretion. Manufacturer's field reports must be submitted in duplicate within 30 days of observation, and certificates of conformance are required when specified in individual specification sections. This specification functions as a standard administrative and quality assurance mechanism for the storm sewer replacement project rather than addressing financial, procurement, or contractual award terms.

View the file

Other files for this state and local contract opportunity

Other files attached to 2500999 - Canterbury Storm Sewer Replacement, newest first.
File Type Posted
3-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
49-Sec 32 13 13 - PORTLAND CEMENT CONCRETE PAVING.pdf PDF
9-Doc 00 43 13 - Bid Bond (penal sum form).pdf PDF
20-Sec 01 56 39 - LANDSCAPE PROTECTION.pdf PDF
30-Sec 32 92 00 - Finish Grading, Seeding and Sodding.pdf PDF
56-X1 - Site Map 2026-07-15.pdf PDF
4-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
24-Sec 31 20 00 - Earthwork.pdf PDF
5-Doc 00 41 00 - BID FORM - EBID.pdf PDF
6-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
25-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID - 2025.pdf PDF
42-Sec 32 12 00 - ASPHALT CONCRETE PAVING.pdf PDF
17-Doc 00 73 00 5 - Appendix B - Public Works Employment Verification Form.pdf PDF
39-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
45-Doc 00 73 00 2 - Appendix A - Cover.pdf PDF
13-Doc 00 73 00 4 - Appendix B - Cover.pdf PDF
43-Sec 01 55 26 - TRAFFIC REGULATION - 2024.pdf PDF
10-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
23-Sec 03 20 00 - CONCRETE REINFORCEMENT.pdf PDF
8-Doc 00 52 00 - AGREEMENT.pdf PDF
54-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
58-Sec 01 22 00-MEASUREMENT AND PAYMENT 2026-07-13.pdf PDF
37-Sec 33 44 14 - STORM INLETS CATCH BASINS ENWALLS AND END SECTIONS.pdf PDF
35-Doc 00 62 76 - Application for Payment.pdf PDF
7-Doc 00 73 00 1 - SUPPLEMENTARY CONDITIONS - 2024.pdf PDF
1-Doc 00 63 63 - Change Order.pdf PDF
40-Doc 00 72 00 - GENERAL CONDITIONS - 2024.pdf PDF
41-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT - 2024.pdf PDF
55-X3 - Canterbury Details 2026-07-16.pdf PDF
33-Sec 01 40 00 - QUALITY CONTROL.pdf PDF
31-Doc 00 01 15 - TABLE OF CONTENTS - LIST OF DRAWINGS.pdf PDF
52-Sec 31 11 00 - CLEARING AND GRUBBING.pdf PDF
11-Doc 00 01 10 - TABLE OF CONTENTS.pdf PDF
18-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
44-Sec 32 01 16.71 - MILLING OF ASPHALT PAVEMENT SURFACE.pdf PDF
21-Doc 00 61 19 - Maintenance Bond.pdf PDF
32-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
16-Sec 31 22 10 - Topsoiling and Finish Grading.pdf PDF
14-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
36-Sec 33 41 00 - STORM DRAIN PIPE.pdf PDF
48-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
47-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
50-Sec 31 23 33 - EXCAVATION BACKFILL AND COMPACTION.pdf PDF
26-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
27-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
51-Sec 32 17 23.13 - Painted Traffic Lines and Markings.pdf PDF
29-Sec 31 37 16 - ENIGERY DISSIPATOR.pdf PDF
28-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
57-X2 - 12-14 18-19 of 24 Marked up As-Built Plans 2026-07-15.pdf PDF
2-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
Show all 50

2500999 - Canterbury Storm Sewer Replacement has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUBMITTALS

01 33 00-1

SECTION 01 33 00

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Submittal procedures.

2. Construction progress schedules.

3. Product data.

4. Shop Drawings.

5. Samples.

6. Design data.

7. Test reports.

8. Certificates.

9. Manufacturer’s instructions.

10. Manufacturer’s field reports.

11. Erection drawings.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Section 01 40 00: Quality Control: Manufacturers' field services.

2. Section 01 70 00: Contract Closeout: Contract closeout submittals including maintenance bond, manufacturers’ warranties, and record drawings.

1.03 REFERENCES

A. AGC (Associated General Contractors of America) publication “The Use of CPM in

Construction - A Manual for General Contractors and the Construction Industry”.

1.04 SUBMITTAL PROCEDURES

A. Transmit each submittal to Engineer.

B. Sequentially number the transmittal forms. Revise submittals with original number and a sequential alphabetic suffix.

C. Identify Project, Contractor, Subcontractor or supplier; pertinent drawing and detail number, and specification section number, as appropriate.

01 33 00-2

D. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of

Products required, field dimensions, adjacent construction Work, and coordination of information, is in accordance with the requirements of the Work and Contract Documents.

E. Schedule submittals to expedite the Project and to coordinate submission of related items.

F. For each submittal for review, allow 15 days excluding delivery time to and from Contractor.

G. Identify variations from Contract Documents and Product or system limitations which may be detrimental to successful performance of the completed Work.

H. Provide space for Contractor and Engineer review stamps.

I. When revised for resubmission, identify all changes made since previous submission.

J. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report any inability to comply with requirements.

K. Submittals not requested will not be recognized or processed.

1.05 CONSTRUCTION PROGRESS SCHEDULES

A. Submit preliminary progress schedule in duplicate within 10 days after Effective Date of Agreement for review by Engineer.

B. Revise and resubmit as required.

C. Submit final progress schedule within 10 days of preconstruction conference or within 10 days upon request of Engineer if no preconstruction conference is to be held.

D. Submit revised progress schedule in duplicate with each Application for Payment, identifying changes since previous version.

E. Submit a horizontal bar chart with separate line for each section of Work, identifying first work day of each week.

F. Show complete sequence of construction by activity, identifying Work of separate stages and other logically grouped activities. Indicate the early and late start, early and late finish, float dates, and duration.

G. Indicate estimated percentage of completion for each item of Work at each submission.

H. Indicate submittal dates required for shop drawings, product data, samples, and product delivery dates, including those furnished by Owner.

1.06 PRODUCT DATA

A. Product Data for Review:

1. Submitted to Engineer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents.

2. After review, provide copies and distribute in accordance with Submittal Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.

01 33 00-3

B. Product Data for Information:

1. Submitted for the Engineer’s knowledge as contract administrator or for Owner.

C. Product Data for Project Closeout:

1. Submitted for Owner’s benefit during and after project completion.

D. Submit the number of copies which Contractor requires, plus three copies which will be retained by Engineer.

E. Mark each copy to identify applicable Products, models, options, and other data. Supplement manufacturers’ standard data to provide information specific to this Project.

F. Indicate Product utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

1.07 SHOP DRAWINGS

A. Shop Drawings for Review:

with information given and the design concept expressed in the Contract Documents.

2. After review, produce copies and distribute in accordance with Submittal Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.

B. Shop Drawings for Information:

1. Submitted for Engineer’s knowledge as contract administrator or for Owner.

C. Shop Drawings for Project Closeout:

1. Submitted for Owner’s benefit during and after project completion.

D. Indicate special utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

E. Submit the number of opaque reproductions which Contractor requires, plus three copies which will be retained by Engineer.

1.08 SAMPLES

A. Samples for Review:

with information given and the design concept expressed in the Contract Documents.

2. After review, produce duplicates and distribute in accordance with Submittal

Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.

B. Samples for Information:

1. Submitted for Engineer’s knowledge as contract administrator or for Owner.

01 33 00-4

C. Samples for Selection:

1. Submitted to Engineer for aesthetic, color, or finish selection.

2. Submit samples of finishes [from the full range of manufacturers’ standard colors,] [in custom colors selected,] textures, and patterns for Engineer’s selection.

3. After review, produce duplicates and distribute in accordance with Submittal

Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.

D. Submit samples to illustrate functional and aesthetic characteristics of the Product, with integral parts and attachment devices. Coordinate sample submittals for interfacing work.

E. Include identification on each sample, with full Project information.

F. Submit the number of samples specified in individual specification sections; one of which will be retained by Engineer.

G. Reviewed samples which may be used in the Work are indicated in individual specification sections.

H. Samples will not be used for testing purposes unless specifically stated in the specification section.

1.09 DESIGN DATA

A. Submit for Engineer’s knowledge as contract administrator or for Owner.

B. Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the Contract Documents.

1.10 TEST REPORTS

A. Submit for Engineer’s knowledge as contract administrator or for Owner.

B. Submit test reports for information for the limited purpose of assessing conformance with information given and the design concept expressed in the Contract Documents.

1.11 CERTIFICATES

A. When specified in individual specification sections, submit certification by the manufacturer, installation/application subcontractor, or Contractor to Engineer, in quantities specified for Product Data.

B. Indicate material or Product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.

C. Certificates may be recent or previous test results on material or Product, but must be acceptable to Engineer.

1.12 MANUFACTURER’S INSTRUCTIONS

A. When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, to Engineer for delivery to Owner in quantities specified for Product Data.

01 33 00-5

B. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.

C. Refer to Section 01 40 00 - Quality Control, Manufacturers’ Field Services article.

1.13 MANUFACTURER’S FIELD REPORTS

A. Submit reports for Engineer’s benefit as contract administrator or for Owner.

B. Submit report in duplicate within 30 days of observation to Engineer for information.

C. Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the Contract Documents.

1.14 ERECTION DRAWINGS

A. Submit drawings for Engineer’s benefit as contract administrator or for Owner.

B. Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the Contract Documents.

C. Data indicating inappropriate or unacceptable Work may be subject to action by Engineer or

Owner.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION