46-Sec 31 11 00 Clearing and Grubbing.pdf

PDF 135 KB Posted

Attached to
82 W. Indian Lane - FEMA Demolition
Solicitation number
US.230082
Issued by
Montgomery County, Pennsylvania

About this file

This is a technical specification document for clearing and grubbing work applicable to a FEMA-funded demolition project in West Norriton Township, Montgomery County, Pennsylvania. The specification outlines the contractor's responsibilities for removing trees, brush, vegetation, stumps, roots, and debris from the project site at 82 West Indian Lane. The work includes clearing obstructions within construction easements and limits of disturbance, grubbing to a minimum depth of eight inches to remove roots and objectionable material, stripping and stockpiling topsoil for later use in finish grading, and restoring any injuries to trees designated for preservation. The contractor must notify the engineer at least 48 hours prior to beginning clearing operations, coordinate tree removal with the Resident Project Representative, protect benchmarks and utilities with temporary fencing, and comply with Pennsylvania Act 287 regarding utility relocations. All clearing and grubbing work must be staged to limit erosion exposure, particularly for utility work limited to lengths that can be completed in a single day.

Debris resulting from clearing and grubbing operations becomes the contractor's property and must be disposed of legally at locations outside the project site, easements, and public right-of-ways, with written agreements required from property owners receiving deposited materials. Burning of debris is permitted only if local ordinances allow it and required permits are obtained. The contractor must restore or replace any trees, shrubs, and plants designated for preservation that are permanently injured or die during construction operations and must remove protective fencing upon project completion. The specification references related sections including soil erosion and sediment control (Section 01 57 13), rock removal (Section 31 23 16.26), excavation and backfill (Section 31 23 33), and finish grading and seeding (Section 32 92 00), indicating this is part of a comprehensive demolition and site restoration project funded by FEMA.

View the file

Other files

File Type Posted
8-Doc 00 21 13 Instructions to Bidders.pdf PDF
14-Doc 00 61 13.16 Payment Bond.pdf PDF
1-00 82 W. Indian Lane FEMA Plans.pdf PDF
39-Sec 01 33 00 Submittals.pdf PDF
35-Sec 01 42 13 Organization and Reference Acronyms.pdf PDF
33-Sec 01 32 16 Construction Project Schedule.pdf PDF
42-Sec 01 70 00 Contract Closeout.pdf PDF
29-Doc 00 73 00 04 Appendix D - Hazard Mitigation Grant Conditions.pdf PDF
41-Sec 01 55 26 Traffic Regulation.pdf PDF
12-Doc 00 45 10 Bidders Acknowledgement Form.pdf PDF
9-Doc 00 45 13 Bidder Qualification Statement.pdf PDF
10-Doc 00 45 53 Agreement of Surety Company.pdf PDF
18-Doc 00 62 16 Certificate of Insurance.pdf PDF
27-Sec 01 11 13 Summary of Work.pdf PDF
7-Doc 00 21 13.1 Instructions for Electronic Bidding.pdf PDF
2-Doc 00 01 15 List of Drawing Sheets.pdf PDF
21-Doc 00 73 00 Supplementary Conditions.pdf PDF
28-Doc 00 73 00 01 Appendix A - Prevailing Wage Rates.pdf PDF
32-Sec 01 31 00 Coordination and Meetings.pdf PDF
31-Sec 01 29 00 Contract Considerations.pdf PDF
24-Doc 00 91 13 Addenda.pdf PDF
17-Doc 00 65 19.13 Contractors Affidavit.pdf PDF
15-Doc 00 61 19 Maintenance Bond.pdf PDF
49-Sec 32 92 00 Finish Grading, Seeding and Sodding.pdf PDF
26-Doc 00 73 00 - Supplementary Conditions.pdf PDF
50-Sec 31 23 33 Excavation, Backfill and Compaction.pdf PDF
4-Doc 00 01 10 Table of Contents.pdf PDF
13-Doc 00 52 00 Agreement.pdf PDF
16-Doc 00 61 13.13 Performance Bond.pdf PDF
45-Sec 02 41 16 Demolition.pdf PDF
40-Sec 01 56 39 Landscape Protection.pdf PDF
34-Sec 01 35 16 Alteration Project Procedures.pdf PDF
22-Doc 00 72 00 General Conditions.pdf PDF
19-Doc 00 65 19.19 Consent of Surety.pdf PDF
5-Doc 00 43 13 Bid Bond.pdf PDF
6-Doc 00 11 13 Advertisement for Bids.pdf PDF
25-Sec 01 00 00 Basic Requirements.pdf PDF
37-Sec 01 50 00 Construction Facilities and Temporary Controls.pdf PDF
23-Doc 00 73 00 02 Appendix B - Public Works Employment Verification Form.pdf PDF
48-Sec 01 57 13 Soil Erosion and Sediment Control.pdf PDF
44-Sec 01 60 00 Material and Equipment.pdf PDF
20-Doc 00 65 19.16 Contractors Release of Liens.pdf PDF
3-Doc 00 01 01 Project Title Page.pdf PDF
38-Sec 01 40 00 Quality Control.pdf PDF
43-Sec 01 57 14 Erosion Control Blanket.pdf PDF
36-Sec 01 22 00 Measurement and Payment.pdf PDF
11-Doc 00 45 19 Non-Collusion Affidavit.pdf PDF
47-Sec 31 20 00 Earthwork.pdf PDF
30-Doc 00 73 00 03 Appendix C - Chapter 106 Permit.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CLEARING AND GRUBBING

31 11 00-1

SECTION 31 11 00

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Clearing

2. Grubbing

3. Stripping and stockpiling topsoil

4. Debris disposal

B. Definitions:

1. Clearing is defined as the removal of trees, brush, down timber, rotten wood, rubbish, any other vegetation, and objectionable material at or above original ground elevation not designated to be saved. Clearing also includes removal of fences, walls, guard posts, guard rail, signs, and other obstructions interfering with the proposed work.

2. Grubbing is defined as the removal from below the surface of the natural ground of stumps, roots and stubs, brush, organic materials and debris.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Section 01 57 13: Soil Erosion and Sediment Control

2. Section 31 23 16.26: Rock Removal

3. Section 31 23 33: Excavation, Backfill and Compaction

4. Section 32 92 00: Finish Grading, Seeding and Sodding

1.03 JOB CONDITIONS

A. Contractor may clear all obstructions within permanent and temporary construction easements and within the limit of disturbance of Owner's property as absolutely necessary to perform the construction work. Contractor shall leave as many trees as possible within the work area and shall not disturb portions of Owner's property beyond the limit of disturbance indicated on the Plans. Removal of trees shall be coordinated with the Resident Project Representative.

1.04 SUBMITTALS

A. Agreements for Disposal of Debris:

1. Arrange for disposal of debris resulting from clearing and grubbing to locations outside Owner's property, easements and public right-of-ways and obtain a written agreement with the owners of each property where the debris will be deposited.

2. Submit two (2) copies of the agreement with each property owner releasing Owner from responsibility in connection with the disposal of the debris.

31 11 00-2

PART 2 - PRODUCTS

2.01 MATERIALS

A. Temporary Fencing:

1. Undamaged picket snow fence, 4' high, formed of wooden slats, tightly woven with wire cable or orange, open mesh plastic construction fencing, 4' high, or other acceptable, highly visible, weather resistant, easily maintained fencing that provides a substantial barrier.

2. Soil-set fence posts, studded "T" type, 6' high.

B. Tree Wound Dressing:

1. Antiseptic and waterproof, asphalt base.

PART 3 - EXECUTION

3.01 PREPARATION

A. Notify Engineer at least 48 hours prior to beginning any clearing work.

B. Protect benchmarks, utilities, existing trees, shrubs and other landscape features designated for preservation with temporary fencing or barricades satisfactory to the Resident Project Representative. No material shall be stored or construction operation carried on within four

(4) feet of any tree to be saved or within the tree protection fence.

C. If a private enclosure fence encroaches on the work area, notify the property owner at least five (5) days in advance of the clearing/grubbing operations to permit the property owner to remove it, construct a supplemental fence, or make such other arrangements as may be necessary for security purposes. Upon failure of the property owner to reasonably proceed with the work required to secure his property, carefully remove the fence, in whole or in part, and neatly pile the materials on the property owner's property.

3.02 UTILITY RELOCATIONS

A. Inform all companies, individuals and others owning or controlling facilities or structures within the limits of the work which have to be relocated, adjusted or reconstructed in sufficient time for the utility to organize and perform such work in conjunction with or in advance of Contractor's operations.

B. Comply with the provisions of PA Act 287 (1974) as last amended by PA Act 121 (2008).

3.03 CLEARING

A. Confine clearing as required to within the limits of the public right-of-ways, easements and Owner's property. Attention is called to Paragraph 1.03 of this Section.

B. Fell trees in a manner that will avoid damage to trees, shrubs, and other installations which are to remain.

C. Where stumps are not required to be grubbed, they shall be flushcut with ground elevation.

31 11 00-3

3.04 GRUBBING

A. Turf clearing and grubbing shall be staged to limit exposure and potential erosion. For utility demolition, removal, and construction, stages shall be limited to that length of trench which may be demolished, removed, and/or installed and backfilled in one (1) day.

B. Grub areas within the construction limits to remove roots and other objectionable material to a minimum depth of 8".

C. Remove all stumps within the cleared areas unless otherwise authorized by the Resident

Project Representative.

3.05 STRIPPING AND STOCKPILING TOPSOIL

A. Stripping of topsoil shall be staged to limit exposure and potential erosion. For utility demolition, removal, and construction, stages shall be limited to that length of trench which may be demolished, removed, and/or installed and backfilled in one (1) day.

B. Strip topsoil to whatever depth it may occur from areas to be excavated, filled, or graded and stockpile at a location approved by the Resident Project Representative for use in finish grading.

C. Topsoil shall not be used as backfill or removed from the site.

3.06 DEBRIS DISPOSAL

A. Trees, logs, branches, brush, stumps, and other debris resulting from clearing and grubbing operations associated with the Work on the Project site and/or within off-site easements/public right-of-ways shall become the property of Contractor and shall be disposed of legally.

B. Debris resulting from the clearing and grubbing work shall not be deposited or buried on the

Project site, easements or public right-of-ways.

C. Debris may be burned on-site if local ordinances allow open air burning, if required permits are obtained, and if burning operations are conducted in compliance with local ordinances and regulations.

3.07 RESTORATION

A. Repair all injuries to bark, trunk, limbs, and roots of remaining plants by properly dressing, cutting, tracing and painting, using approved arboricultural practices and materials.

B. Replace trees, shrubs and plants designated to be saved which are permanently injured or die during the Contract or the maintenance period as a result of construction operations with like species acceptable to the property owner.

C. Remove protective fences, enclosures and guards upon the completion of the project.

D. Restore guard posts, guard rail, signs and other interferences to the condition equal to that existing before construction operations.

END OF SECTION