This is a Contract Closeout specification document (Section 01 70 00) applicable to the FEMA-funded demolition project at 82 West Indian Lane in West Norriton Township, Montgomery County, Pennsylvania. The specification outlines mandatory closeout procedures that the contractor must complete prior to final payment and project acceptance. Key requirements include submission of written certification that the work is complete and ready for engineer review, completion of all punchlist items within contract time, final cleaning of all equipment and fixtures, site cleanup including removal of debris and construction facilities, adjustment of operating equipment, and maintenance of comprehensive project record documents including marked-up drawings, specifications, addenda, change orders, and shop drawings that accurately reflect all actual work performed and product installations. The contractor must also submit final applications for payment identifying total adjusted contract price and remaining amounts due, with final payment contingent upon engineer inspection and acceptance.
Additional documentation required prior to final payment includes payroll certification forms (if work exceeds $25,000), waivers of liens from all subcontractors and suppliers, maintenance bonds, any outstanding change orders with supporting documentation, test and sample results, and equipment warranties. Project record documents must be maintained on-site throughout construction, with entries completed concurrent with work progress, and must include measured locations of utilities, field changes, product substitutions, and manufacturer information for all installed items. These closeout requirements ensure comprehensive documentation of the demolition work and associated site restoration for owner reference and future property use.
View the file
Other files
Show all 49
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT CLOSEOUT
01 70 00-1
SECTION 01 70 00
PART 1 GENERAL
1.01 SECTION DESCRIPTION
A. The Work of This Section Includes:
1. Closeout procedures.
2. Final cleaning.
3. Adjusting.
4. Project record documents.
5. Other documentation.
1.02 RELATED SECTIONS
A. Related Work Specified Elsewhere:
1. Section 01 50 00: Construction Facilities and Temporary Controls: Progress cleaning
1.03 CONTRACT CLOSEOUT PROCEDURES
A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Engineer's review.
B. Engineer shall make a final inspection and prepare a punchlist of items remaining to be completed or corrected prior to final acceptance in accordance with Article 14, paragraph
14.06 of the General Conditions.
C. Complete all items on the punchlist, plus any new items that may be subsequently added, as soon as possible and within the Contract Time.
D. Provide submittals to Engineer that are required by governing or other authorities.
E. Submit final Application for Payment identifying total adjusted Contract Price, previous payments, and remaining amount due.
F. Final Payment will not be made until final completion and acceptance of the Work.
1.04 FINAL CLEANING
A. Execute final cleaning prior to final Project inspection.
B. Clean equipment and fixtures to a sanitary condition with cleaning materials appropriate to the surface and material being cleaned.
C. Clean or replace filters of operating equipment.
D. Clean accumulated debris and sediment from gutters and drainage systems.
01 70 00-2
E. Clean site, sweep paved areas, rake clean landscaped surfaces.
F. Remove waste and surplus materials, rubbish, and construction facilities from the site.
1.05 ADJUSTING
A. Adjust operating Products and equipment to ensure smooth and unhindered operation.
1.06 PROJECT RECORD DOCUMENTS
A. Maintain on-site one set of the following record documents; record actual revisions to the Work:
1. Drawings.
2. Specifications.
3. Addenda.
4. Change Orders and other modifications to the Contract.
5. Reviewed Shop Drawings, Product data, and samples.
6. Manufacturer’s instructions for assembly, installation and adjusting.
B. Ensure entries are complete and accurate, enabling future reference by Owner.
C. Store record documents separate from documents used for construction.
D. Record information concurrent with construction progress.
E. Specifications: Legibly mark and record at each Product section description of actual Products installed, including the following:
1. Manufacturer's name and product model and number.
2. Product substitutions or alternates utilized.
3. Changes made by Addenda and modifications.
F. Record Drawings and Shop Drawings: Legibly mark each item to record actual construction including:
1. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.
2. Measured locations of internal utilities and appurtenances concealed in construction, referenced to visible and accessible features of the Work.
3. Field changes of dimension and detail.
4. Details not on original Contract Drawings.
G. Delete Engineer's title block and seal from all documents.
01 70 00-3
H. Submit documents to Engineer with claim for final Application for Payment.
1.07 OTHER DOCUMENTATION
A. Provide data and documentation properly completed and executed prior to final Application for Payment as Engineer may reasonably require including:
1. Payroll Certification forms by Contractor and all Subcontractors (if price exceeds
$25,000).
2. Waiver of Liens by all Subcontractors and Suppliers or Contractor's Affidavit, Contractor's Release of Liens and Consent of Surety to Final Payment.
3. Maintenance Bond.
4. Any Change Orders with supporting documentation which remain to be submitted.
5. Test and/or sample results.
6. Equipment warranties.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION