42-Sec 01 70 00 Contract Closeout.pdf

PDF 95 KB Posted

Attached to
82 W. Indian Lane - FEMA Demolition
Solicitation number
US.230082
Issued by
Montgomery County, Pennsylvania

About this file

This is a Contract Closeout specification document (Section 01 70 00) applicable to the FEMA-funded demolition project at 82 West Indian Lane in West Norriton Township, Montgomery County, Pennsylvania. The specification outlines mandatory closeout procedures that the contractor must complete prior to final payment and project acceptance. Key requirements include submission of written certification that the work is complete and ready for engineer review, completion of all punchlist items within contract time, final cleaning of all equipment and fixtures, site cleanup including removal of debris and construction facilities, adjustment of operating equipment, and maintenance of comprehensive project record documents including marked-up drawings, specifications, addenda, change orders, and shop drawings that accurately reflect all actual work performed and product installations. The contractor must also submit final applications for payment identifying total adjusted contract price and remaining amounts due, with final payment contingent upon engineer inspection and acceptance.

Additional documentation required prior to final payment includes payroll certification forms (if work exceeds $25,000), waivers of liens from all subcontractors and suppliers, maintenance bonds, any outstanding change orders with supporting documentation, test and sample results, and equipment warranties. Project record documents must be maintained on-site throughout construction, with entries completed concurrent with work progress, and must include measured locations of utilities, field changes, product substitutions, and manufacturer information for all installed items. These closeout requirements ensure comprehensive documentation of the demolition work and associated site restoration for owner reference and future property use.

View the file

Other files

File Type Posted
8-Doc 00 21 13 Instructions to Bidders.pdf PDF
14-Doc 00 61 13.16 Payment Bond.pdf PDF
1-00 82 W. Indian Lane FEMA Plans.pdf PDF
39-Sec 01 33 00 Submittals.pdf PDF
35-Sec 01 42 13 Organization and Reference Acronyms.pdf PDF
33-Sec 01 32 16 Construction Project Schedule.pdf PDF
29-Doc 00 73 00 04 Appendix D - Hazard Mitigation Grant Conditions.pdf PDF
41-Sec 01 55 26 Traffic Regulation.pdf PDF
12-Doc 00 45 10 Bidders Acknowledgement Form.pdf PDF
9-Doc 00 45 13 Bidder Qualification Statement.pdf PDF
10-Doc 00 45 53 Agreement of Surety Company.pdf PDF
18-Doc 00 62 16 Certificate of Insurance.pdf PDF
27-Sec 01 11 13 Summary of Work.pdf PDF
7-Doc 00 21 13.1 Instructions for Electronic Bidding.pdf PDF
2-Doc 00 01 15 List of Drawing Sheets.pdf PDF
21-Doc 00 73 00 Supplementary Conditions.pdf PDF
28-Doc 00 73 00 01 Appendix A - Prevailing Wage Rates.pdf PDF
32-Sec 01 31 00 Coordination and Meetings.pdf PDF
31-Sec 01 29 00 Contract Considerations.pdf PDF
24-Doc 00 91 13 Addenda.pdf PDF
17-Doc 00 65 19.13 Contractors Affidavit.pdf PDF
15-Doc 00 61 19 Maintenance Bond.pdf PDF
49-Sec 32 92 00 Finish Grading, Seeding and Sodding.pdf PDF
26-Doc 00 73 00 - Supplementary Conditions.pdf PDF
50-Sec 31 23 33 Excavation, Backfill and Compaction.pdf PDF
4-Doc 00 01 10 Table of Contents.pdf PDF
13-Doc 00 52 00 Agreement.pdf PDF
16-Doc 00 61 13.13 Performance Bond.pdf PDF
45-Sec 02 41 16 Demolition.pdf PDF
40-Sec 01 56 39 Landscape Protection.pdf PDF
34-Sec 01 35 16 Alteration Project Procedures.pdf PDF
22-Doc 00 72 00 General Conditions.pdf PDF
19-Doc 00 65 19.19 Consent of Surety.pdf PDF
5-Doc 00 43 13 Bid Bond.pdf PDF
6-Doc 00 11 13 Advertisement for Bids.pdf PDF
25-Sec 01 00 00 Basic Requirements.pdf PDF
37-Sec 01 50 00 Construction Facilities and Temporary Controls.pdf PDF
23-Doc 00 73 00 02 Appendix B - Public Works Employment Verification Form.pdf PDF
46-Sec 31 11 00 Clearing and Grubbing.pdf PDF
48-Sec 01 57 13 Soil Erosion and Sediment Control.pdf PDF
44-Sec 01 60 00 Material and Equipment.pdf PDF
20-Doc 00 65 19.16 Contractors Release of Liens.pdf PDF
3-Doc 00 01 01 Project Title Page.pdf PDF
38-Sec 01 40 00 Quality Control.pdf PDF
43-Sec 01 57 14 Erosion Control Blanket.pdf PDF
36-Sec 01 22 00 Measurement and Payment.pdf PDF
11-Doc 00 45 19 Non-Collusion Affidavit.pdf PDF
47-Sec 31 20 00 Earthwork.pdf PDF
30-Doc 00 73 00 03 Appendix C - Chapter 106 Permit.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT CLOSEOUT

01 70 00-1

SECTION 01 70 00

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Closeout procedures.

2. Final cleaning.

3. Adjusting.

4. Project record documents.

5. Other documentation.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Section 01 50 00: Construction Facilities and Temporary Controls: Progress cleaning

1.03 CONTRACT CLOSEOUT PROCEDURES

A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Engineer's review.

B. Engineer shall make a final inspection and prepare a punchlist of items remaining to be completed or corrected prior to final acceptance in accordance with Article 14, paragraph

14.06 of the General Conditions.

C. Complete all items on the punchlist, plus any new items that may be subsequently added, as soon as possible and within the Contract Time.

D. Provide submittals to Engineer that are required by governing or other authorities.

E. Submit final Application for Payment identifying total adjusted Contract Price, previous payments, and remaining amount due.

F. Final Payment will not be made until final completion and acceptance of the Work.

1.04 FINAL CLEANING

A. Execute final cleaning prior to final Project inspection.

B. Clean equipment and fixtures to a sanitary condition with cleaning materials appropriate to the surface and material being cleaned.

C. Clean or replace filters of operating equipment.

D. Clean accumulated debris and sediment from gutters and drainage systems.

01 70 00-2

E. Clean site, sweep paved areas, rake clean landscaped surfaces.

F. Remove waste and surplus materials, rubbish, and construction facilities from the site.

1.05 ADJUSTING

A. Adjust operating Products and equipment to ensure smooth and unhindered operation.

1.06 PROJECT RECORD DOCUMENTS

A. Maintain on-site one set of the following record documents; record actual revisions to the Work:

1. Drawings.

2. Specifications.

3. Addenda.

4. Change Orders and other modifications to the Contract.

5. Reviewed Shop Drawings, Product data, and samples.

6. Manufacturer’s instructions for assembly, installation and adjusting.

B. Ensure entries are complete and accurate, enabling future reference by Owner.

C. Store record documents separate from documents used for construction.

D. Record information concurrent with construction progress.

E. Specifications: Legibly mark and record at each Product section description of actual Products installed, including the following:

1. Manufacturer's name and product model and number.

2. Product substitutions or alternates utilized.

3. Changes made by Addenda and modifications.

F. Record Drawings and Shop Drawings: Legibly mark each item to record actual construction including:

1. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.

2. Measured locations of internal utilities and appurtenances concealed in construction, referenced to visible and accessible features of the Work.

3. Field changes of dimension and detail.

4. Details not on original Contract Drawings.

G. Delete Engineer's title block and seal from all documents.

01 70 00-3

H. Submit documents to Engineer with claim for final Application for Payment.

1.07 OTHER DOCUMENTATION

A. Provide data and documentation properly completed and executed prior to final Application for Payment as Engineer may reasonably require including:

1. Payroll Certification forms by Contractor and all Subcontractors (if price exceeds

$25,000).

2. Waiver of Liens by all Subcontractors and Suppliers or Contractor's Affidavit, Contractor's Release of Liens and Consent of Surety to Final Payment.

3. Maintenance Bond.

4. Any Change Orders with supporting documentation which remain to be submitted.

5. Test and/or sample results.

6. Equipment warranties.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION