This is a Construction Project Schedule specification document (Section 01 32 16) for a FEMA-funded demolition project located at 82 West Indian Lane in West Norriton Township, Montgomery County, Pennsylvania. The contractor must submit a detailed construction schedule within 15 calendar days after receiving the Notice to Proceed. The schedule submission is a critical requirement, as the Owner may withhold progress payments until the schedule is accepted. The Engineer will review and respond to the schedule and supporting documentation within 10 calendar days of receipt. If the schedule is not submitted within 30 calendar days after Notice to Proceed, the contractor will be required to attend a scheduling meeting, and the Owner may continue to withhold progress payments until scheduling is completed.
The required schedule must include minimum specifications: activity descriptions and locations, duration in working days, and start and finish calendar dates. The contractor must also submit a workday calendar detailing work days and non-work days, number of shifts per day, and hours per shift. The schedule must contain sufficient activities to demonstrate necessary interdependencies and must include a narrative description of the construction schedule. The project scope includes demolition of an existing single-family home, removal of all buildings and associated impervious surfaces, replacement with grass, erosion control, grading, soil compaction, debris removal, and local permitting. The contractor is responsible for providing all materials, equipment, tools, labor, and supervision necessary for complete project performance in accordance with contract documents.
View the file
Other files
Show all 49
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCTION PROJECT SCHEDULE
01 32 16-1
SECTION 01 32 16
CONSTRUCTION PROJECT SCHEDULE
PART 1 - GENERAL
1.01 SECTION DESCRIPTION
A. The Work of This Section Includes:
1. The preparation, maintenance, and revision of the construction project schedule to monitor progress of project operations and duration.
1.02 RELATED SECTIONS
A. Related Work Specified Elsewhere:
1. Section 01 31 00 - Coordination and Meetings
PART 2 – PRODUCTS
2.01 Not Used
PART 3 - EXECUTION
3.01 CONSTRUCTION SCHEDULE
A. Submit the schedule within 15 calendar days after the Notice to Proceed date. Owner, after consultation with Contractor, may elect not to release progress payments until the schedule is submitted and accepted.
B. Engineer will review and respond to the detailed schedule and supporting documentation within
10 calendar days of receipt. Include, as a minimum, the following in the initial schedule and in all schedule revisions:
1. Activity description & location;
2. Duration of activity, in working days; and
3. Start and finish calendar dates of activities.
C. In addition, submit a workday calendar showing work days and non-work days, number of shifts per day, and number of hours per shift.
D. Provide enough activities to demonstrate the necessary interdependencies. Use the above information to complete a narrative description of the construction schedule.
E. If the schedule is not received within 30 calendar days after the Notice to Proceed date, Contractor will be required to attend a scheduling meeting in order to prepare an acceptable schedule. Owner may elect not to release progress payments until the scheduling has been completed.
END OF SECTION