33-Sec 01 32 16 Construction Project Schedule.pdf

PDF 84 KB Posted

Attached to
82 W. Indian Lane - FEMA Demolition
Solicitation number
US.230082
Issued by
Montgomery County, Pennsylvania

About this file

This is a Construction Project Schedule specification document (Section 01 32 16) for a FEMA-funded demolition project located at 82 West Indian Lane in West Norriton Township, Montgomery County, Pennsylvania. The contractor must submit a detailed construction schedule within 15 calendar days after receiving the Notice to Proceed. The schedule submission is a critical requirement, as the Owner may withhold progress payments until the schedule is accepted. The Engineer will review and respond to the schedule and supporting documentation within 10 calendar days of receipt. If the schedule is not submitted within 30 calendar days after Notice to Proceed, the contractor will be required to attend a scheduling meeting, and the Owner may continue to withhold progress payments until scheduling is completed.

The required schedule must include minimum specifications: activity descriptions and locations, duration in working days, and start and finish calendar dates. The contractor must also submit a workday calendar detailing work days and non-work days, number of shifts per day, and hours per shift. The schedule must contain sufficient activities to demonstrate necessary interdependencies and must include a narrative description of the construction schedule. The project scope includes demolition of an existing single-family home, removal of all buildings and associated impervious surfaces, replacement with grass, erosion control, grading, soil compaction, debris removal, and local permitting. The contractor is responsible for providing all materials, equipment, tools, labor, and supervision necessary for complete project performance in accordance with contract documents.

View the file

Other files

File Type Posted
8-Doc 00 21 13 Instructions to Bidders.pdf PDF
14-Doc 00 61 13.16 Payment Bond.pdf PDF
1-00 82 W. Indian Lane FEMA Plans.pdf PDF
39-Sec 01 33 00 Submittals.pdf PDF
35-Sec 01 42 13 Organization and Reference Acronyms.pdf PDF
42-Sec 01 70 00 Contract Closeout.pdf PDF
29-Doc 00 73 00 04 Appendix D - Hazard Mitigation Grant Conditions.pdf PDF
41-Sec 01 55 26 Traffic Regulation.pdf PDF
12-Doc 00 45 10 Bidders Acknowledgement Form.pdf PDF
9-Doc 00 45 13 Bidder Qualification Statement.pdf PDF
10-Doc 00 45 53 Agreement of Surety Company.pdf PDF
18-Doc 00 62 16 Certificate of Insurance.pdf PDF
27-Sec 01 11 13 Summary of Work.pdf PDF
7-Doc 00 21 13.1 Instructions for Electronic Bidding.pdf PDF
2-Doc 00 01 15 List of Drawing Sheets.pdf PDF
21-Doc 00 73 00 Supplementary Conditions.pdf PDF
28-Doc 00 73 00 01 Appendix A - Prevailing Wage Rates.pdf PDF
32-Sec 01 31 00 Coordination and Meetings.pdf PDF
31-Sec 01 29 00 Contract Considerations.pdf PDF
24-Doc 00 91 13 Addenda.pdf PDF
17-Doc 00 65 19.13 Contractors Affidavit.pdf PDF
15-Doc 00 61 19 Maintenance Bond.pdf PDF
49-Sec 32 92 00 Finish Grading, Seeding and Sodding.pdf PDF
26-Doc 00 73 00 - Supplementary Conditions.pdf PDF
50-Sec 31 23 33 Excavation, Backfill and Compaction.pdf PDF
4-Doc 00 01 10 Table of Contents.pdf PDF
13-Doc 00 52 00 Agreement.pdf PDF
16-Doc 00 61 13.13 Performance Bond.pdf PDF
45-Sec 02 41 16 Demolition.pdf PDF
40-Sec 01 56 39 Landscape Protection.pdf PDF
34-Sec 01 35 16 Alteration Project Procedures.pdf PDF
22-Doc 00 72 00 General Conditions.pdf PDF
19-Doc 00 65 19.19 Consent of Surety.pdf PDF
5-Doc 00 43 13 Bid Bond.pdf PDF
6-Doc 00 11 13 Advertisement for Bids.pdf PDF
25-Sec 01 00 00 Basic Requirements.pdf PDF
37-Sec 01 50 00 Construction Facilities and Temporary Controls.pdf PDF
23-Doc 00 73 00 02 Appendix B - Public Works Employment Verification Form.pdf PDF
46-Sec 31 11 00 Clearing and Grubbing.pdf PDF
48-Sec 01 57 13 Soil Erosion and Sediment Control.pdf PDF
44-Sec 01 60 00 Material and Equipment.pdf PDF
20-Doc 00 65 19.16 Contractors Release of Liens.pdf PDF
3-Doc 00 01 01 Project Title Page.pdf PDF
38-Sec 01 40 00 Quality Control.pdf PDF
43-Sec 01 57 14 Erosion Control Blanket.pdf PDF
36-Sec 01 22 00 Measurement and Payment.pdf PDF
11-Doc 00 45 19 Non-Collusion Affidavit.pdf PDF
47-Sec 31 20 00 Earthwork.pdf PDF
30-Doc 00 73 00 03 Appendix C - Chapter 106 Permit.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION PROJECT SCHEDULE

01 32 16-1

SECTION 01 32 16

CONSTRUCTION PROJECT SCHEDULE

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. The preparation, maintenance, and revision of the construction project schedule to monitor progress of project operations and duration.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Section 01 31 00 - Coordination and Meetings

PART 2 – PRODUCTS

2.01 Not Used

PART 3 - EXECUTION

3.01 CONSTRUCTION SCHEDULE

A. Submit the schedule within 15 calendar days after the Notice to Proceed date. Owner, after consultation with Contractor, may elect not to release progress payments until the schedule is submitted and accepted.

B. Engineer will review and respond to the detailed schedule and supporting documentation within

10 calendar days of receipt. Include, as a minimum, the following in the initial schedule and in all schedule revisions:

1. Activity description & location;

2. Duration of activity, in working days; and

3. Start and finish calendar dates of activities.

C. In addition, submit a workday calendar showing work days and non-work days, number of shifts per day, and number of hours per shift.

D. Provide enough activities to demonstrate the necessary interdependencies. Use the above information to complete a narrative description of the construction schedule.

E. If the schedule is not received within 30 calendar days after the Notice to Proceed date, Contractor will be required to attend a scheduling meeting in order to prepare an acceptable schedule. Owner may elect not to release progress payments until the scheduling has been completed.

END OF SECTION