36-Sec 01 22 00 Measurement and Payment.pdf
PDF 118 KB Posted
- Attached to
- 82 W. Indian Lane - FEMA Demolition
- Solicitation number
- US.230082
- Issued by
- Montgomery County, Pennsylvania
About this file
This is a Measurement and Payment specification document for a FEMA demolition project in West Norriton Township, Montgomery County, Pennsylvania, involving the removal of a single-family residence at 82 West Indian Lane. The scope of work includes seven distinct line items compensated on a lump sum basis: installation and maintenance of erosion and sediment controls; building and garage demolition with removal of foundations and concrete slabs to a depth of at least 24 inches below grade; bituminous pavement removal including all wearing, base, and stone subbase layers; concrete pavement, retaining wall, and steps removal with associated stone subbase; grading of the entire limit of disturbance; import and placement of six inches of topsoil to achieve proposed grades; and seeding of disturbed areas with Formula B permanent seed mix. All measurements for payment are based on completed work performed in accordance with the project drawings and manual, with the Resident Project Representative responsible for taking measurements and computing quantities.
The contractor is responsible for providing all labor, materials, equipment, and supervision necessary to complete each line item, with lump sum unit prices covering full compensation for work performed. Payment procedures require that work be completed in strict accordance with contract specifications and drawings, and payment clauses ensure that work or materials essential to each item are not duplicated or paid under multiple line items. The contractor must assist with measurements by providing necessary equipment and personnel as required by the Resident Project Representative.
View the file
Other files
Show all 49
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MEASUREMENT AND PAYMENT
01 22 00-1
SECTION 01 22 00
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Measurement and payment criteria applicable to the Work performed under a unit price payment method.
1.02 PROCEDURE
A. All measurements for payment will be based on completed work, performed in strict accordance with the Drawings and Project Manual, and with the Agreement’s “Schedule of Bid Items”.
B. The Resident Project Representative shall take all measurements and compute quantities relative to all work completed under the Agreement in accordance with the methods included in this section. Contractor shall assist by providing necessary equipment and personnel as required.
C. In cases where the payment clause for an item in this section relating to any unit or lump sum price requires that the said unit or lump sum price cover and be considered compensation for certain work or material essential to the item, this same work or material shall not be measured or paid for under any other item which may appear elsewhere in this section.
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
3.01 INSTALL AND MAINTAIN E&S CONTROLS
A. Measurement
Measurement of this item will be based on the LUMP SUM of the installation and maintenance if all E&S controls in accordance construction entrances installed with the Project Manual and Drawings.
B. Payment
Payment for E&S Controls will be made at the applicable unit price listed in the Bid Schedule.
This price shall constitute full compensation for the furnishing of all labor, materials, equipment, install and maintain all erosion and sediment controls in accordance with the plans, including but not limited to Rock Construction Entrance, Silt Sock and Inlet Protections.
01 22 00-2
3.02 BUILDING & GARAGE DEMOLITION AND DISPOSAL (INCLUDES BACKFILL)
Measurement of this item will be on a lump sum basis, covering the demolition and disposal of the existing house in accordance with the Project Manual and Drawings. Building walls, foundations, and concrete slab shall be fully removed to a depth of at least 24-inches below existing grade.
Payment for building demolition and disposal (includes backfill) will be made at the applicable unit price listed in the Bid Schedule. This price shall constitute full compensation for the furnishing of all labor, materials, and equipment necessary to fully demolish and dispose of the existing house. Building walls, foundations, and concrete foundation slab shall be fully removed to a depth of at least 24-inches below existing grade. This shall include any/all required testing, demolition, excavation, disposal, backfill and compaction of required material, and all other related work necessary to complete the building demolition and disposal.
3.03 BITUMINOUS PAVEMENT REMOVAL AND DISPOSAL (FULL PAVEMENT SECTION,
INCLUDING STONE SUBBASE)
Measurement of this item will be based on a Lump Sum basis of existing bituminous pavement and existing stone subbase removed and disposed of in accordance with the
Payment for bituminous pavement removal and disposal (full pavement section, including stone subbase) will be made at the applicable unit price listed in the Bid Schedule. This price shall constitute full compensation for the furnishing of all labor, materials, and equipment necessary to remove and dispose of the full bituminous pavement section, including any/all wearing, base, and stone subbase layers.
3.04 CONCRETE PAVEMENT, RETAINING WALL & STEPS REMOVAL AND DISPOSAL (FULL
CONCRETE SECTION, INCLUDING STONE SUBBASE)
Measurement of this item will be based on a Lump Sum basis of existing concrete pavement and/or steps and existing stone subbase removed and disposed of in accordance with the
Payment for concrete pavement / steps removal and disposal (full concrete section, including stone subbase) will be made at the applicable unit price listed in the Bid Schedule. This price shall constitute full compensation for the furnishing of all labor, materials, and equipment necessary to remove and dispose of the full concrete pavement/steps section, including any/all concrete and stone subbase layers.
01 22 00-3
3.05 GRADE ENTIRE LIMIT OF DISTURBANCE
Measurement of this item will be based on a Lump Sum basis, of area to be disturbed and graded by Contractor relative to the site improvement work in accordance with the Project Manual and Drawings. The disturbed areas shall be graded prior to the placement of topsoil.
Payment to rough grade will be made at the applicable unit price listed in the Bid Schedule.
This price shall constitute full compensation for the furnishing of all labor, materials and equipment necessary to rough grade the project site, specifically the area fill area adjecnt to the retaining wall.
3.06 IMPORT AND SPREAD 6” DEPTH OF TOPSOIL
Measurement of this item will be based on the LUMP SUM of topsoil placed, and spread in accordance with the Project Manual and Drawings. Topsoil shall be imported and spread as necessary to achieve the proposed grades depicted on the plans.
Payment to import and spread 6-inch depth of topsoil will made be at the applicable unit price listed in the Bid Schedule. This price shall constitute full compensation for the furnishing of all labor, materials, and equipment necessary to import, place, and spread the topsoil as necessary to achieve the grades depicted on the plans.
3.07 SEED DISTURBED AREAS WITH FORMULA B PERMANENT SEED MIX
Measurement of this item will be based on a Lump Sum basis, of all disturbed areas adequately covered with seed in accordance with the Project Manual and Drawings.
Payment to seed disturbed areas with Formula B permanent seed mix will be made at the applicable unit price listed in the Bid Schedule. This price shall constitute full compensation for the furnishing of all labor, materials, and equipment necessary to install and maintain the seed to ensure that it survives as more fully defined in the Project Manual and shown on the Drawings.
END OF SECTION