About this file

This is a Measurement and Payment specification document for a FEMA demolition project in West Norriton Township, Montgomery County, Pennsylvania, involving the removal of a single-family residence at 82 West Indian Lane. The scope of work includes seven distinct line items compensated on a lump sum basis: installation and maintenance of erosion and sediment controls; building and garage demolition with removal of foundations and concrete slabs to a depth of at least 24 inches below grade; bituminous pavement removal including all wearing, base, and stone subbase layers; concrete pavement, retaining wall, and steps removal with associated stone subbase; grading of the entire limit of disturbance; import and placement of six inches of topsoil to achieve proposed grades; and seeding of disturbed areas with Formula B permanent seed mix. All measurements for payment are based on completed work performed in accordance with the project drawings and manual, with the Resident Project Representative responsible for taking measurements and computing quantities.

The contractor is responsible for providing all labor, materials, equipment, and supervision necessary to complete each line item, with lump sum unit prices covering full compensation for work performed. Payment procedures require that work be completed in strict accordance with contract specifications and drawings, and payment clauses ensure that work or materials essential to each item are not duplicated or paid under multiple line items. The contractor must assist with measurements by providing necessary equipment and personnel as required by the Resident Project Representative.

View the file

Other files

File Type Posted
8-Doc 00 21 13 Instructions to Bidders.pdf PDF
14-Doc 00 61 13.16 Payment Bond.pdf PDF
1-00 82 W. Indian Lane FEMA Plans.pdf PDF
39-Sec 01 33 00 Submittals.pdf PDF
35-Sec 01 42 13 Organization and Reference Acronyms.pdf PDF
33-Sec 01 32 16 Construction Project Schedule.pdf PDF
42-Sec 01 70 00 Contract Closeout.pdf PDF
29-Doc 00 73 00 04 Appendix D - Hazard Mitigation Grant Conditions.pdf PDF
41-Sec 01 55 26 Traffic Regulation.pdf PDF
12-Doc 00 45 10 Bidders Acknowledgement Form.pdf PDF
9-Doc 00 45 13 Bidder Qualification Statement.pdf PDF
10-Doc 00 45 53 Agreement of Surety Company.pdf PDF
18-Doc 00 62 16 Certificate of Insurance.pdf PDF
27-Sec 01 11 13 Summary of Work.pdf PDF
7-Doc 00 21 13.1 Instructions for Electronic Bidding.pdf PDF
2-Doc 00 01 15 List of Drawing Sheets.pdf PDF
21-Doc 00 73 00 Supplementary Conditions.pdf PDF
28-Doc 00 73 00 01 Appendix A - Prevailing Wage Rates.pdf PDF
32-Sec 01 31 00 Coordination and Meetings.pdf PDF
31-Sec 01 29 00 Contract Considerations.pdf PDF
24-Doc 00 91 13 Addenda.pdf PDF
17-Doc 00 65 19.13 Contractors Affidavit.pdf PDF
15-Doc 00 61 19 Maintenance Bond.pdf PDF
49-Sec 32 92 00 Finish Grading, Seeding and Sodding.pdf PDF
26-Doc 00 73 00 - Supplementary Conditions.pdf PDF
50-Sec 31 23 33 Excavation, Backfill and Compaction.pdf PDF
4-Doc 00 01 10 Table of Contents.pdf PDF
13-Doc 00 52 00 Agreement.pdf PDF
16-Doc 00 61 13.13 Performance Bond.pdf PDF
45-Sec 02 41 16 Demolition.pdf PDF
40-Sec 01 56 39 Landscape Protection.pdf PDF
34-Sec 01 35 16 Alteration Project Procedures.pdf PDF
22-Doc 00 72 00 General Conditions.pdf PDF
19-Doc 00 65 19.19 Consent of Surety.pdf PDF
5-Doc 00 43 13 Bid Bond.pdf PDF
6-Doc 00 11 13 Advertisement for Bids.pdf PDF
25-Sec 01 00 00 Basic Requirements.pdf PDF
37-Sec 01 50 00 Construction Facilities and Temporary Controls.pdf PDF
23-Doc 00 73 00 02 Appendix B - Public Works Employment Verification Form.pdf PDF
46-Sec 31 11 00 Clearing and Grubbing.pdf PDF
48-Sec 01 57 13 Soil Erosion and Sediment Control.pdf PDF
44-Sec 01 60 00 Material and Equipment.pdf PDF
20-Doc 00 65 19.16 Contractors Release of Liens.pdf PDF
3-Doc 00 01 01 Project Title Page.pdf PDF
38-Sec 01 40 00 Quality Control.pdf PDF
43-Sec 01 57 14 Erosion Control Blanket.pdf PDF
11-Doc 00 45 19 Non-Collusion Affidavit.pdf PDF
47-Sec 31 20 00 Earthwork.pdf PDF
30-Doc 00 73 00 03 Appendix C - Chapter 106 Permit.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MEASUREMENT AND PAYMENT

01 22 00-1

SECTION 01 22 00

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Measurement and payment criteria applicable to the Work performed under a unit price payment method.

1.02 PROCEDURE

A. All measurements for payment will be based on completed work, performed in strict accordance with the Drawings and Project Manual, and with the Agreement’s “Schedule of Bid Items”.

B. The Resident Project Representative shall take all measurements and compute quantities relative to all work completed under the Agreement in accordance with the methods included in this section. Contractor shall assist by providing necessary equipment and personnel as required.

C. In cases where the payment clause for an item in this section relating to any unit or lump sum price requires that the said unit or lump sum price cover and be considered compensation for certain work or material essential to the item, this same work or material shall not be measured or paid for under any other item which may appear elsewhere in this section.

PART 2 - PRODUCTS

Not Used

PART 3 - EXECUTION

3.01 INSTALL AND MAINTAIN E&S CONTROLS

A. Measurement

Measurement of this item will be based on the LUMP SUM of the installation and maintenance if all E&S controls in accordance construction entrances installed with the Project Manual and Drawings.

B. Payment

Payment for E&S Controls will be made at the applicable unit price listed in the Bid Schedule.

This price shall constitute full compensation for the furnishing of all labor, materials, equipment, install and maintain all erosion and sediment controls in accordance with the plans, including but not limited to Rock Construction Entrance, Silt Sock and Inlet Protections.

01 22 00-2

3.02 BUILDING & GARAGE DEMOLITION AND DISPOSAL (INCLUDES BACKFILL)

Measurement of this item will be on a lump sum basis, covering the demolition and disposal of the existing house in accordance with the Project Manual and Drawings. Building walls, foundations, and concrete slab shall be fully removed to a depth of at least 24-inches below existing grade.

Payment for building demolition and disposal (includes backfill) will be made at the applicable unit price listed in the Bid Schedule. This price shall constitute full compensation for the furnishing of all labor, materials, and equipment necessary to fully demolish and dispose of the existing house. Building walls, foundations, and concrete foundation slab shall be fully removed to a depth of at least 24-inches below existing grade. This shall include any/all required testing, demolition, excavation, disposal, backfill and compaction of required material, and all other related work necessary to complete the building demolition and disposal.

3.03 BITUMINOUS PAVEMENT REMOVAL AND DISPOSAL (FULL PAVEMENT SECTION,

INCLUDING STONE SUBBASE)

Measurement of this item will be based on a Lump Sum basis of existing bituminous pavement and existing stone subbase removed and disposed of in accordance with the

Payment for bituminous pavement removal and disposal (full pavement section, including stone subbase) will be made at the applicable unit price listed in the Bid Schedule. This price shall constitute full compensation for the furnishing of all labor, materials, and equipment necessary to remove and dispose of the full bituminous pavement section, including any/all wearing, base, and stone subbase layers.

3.04 CONCRETE PAVEMENT, RETAINING WALL & STEPS REMOVAL AND DISPOSAL (FULL

CONCRETE SECTION, INCLUDING STONE SUBBASE)

Measurement of this item will be based on a Lump Sum basis of existing concrete pavement and/or steps and existing stone subbase removed and disposed of in accordance with the

Payment for concrete pavement / steps removal and disposal (full concrete section, including stone subbase) will be made at the applicable unit price listed in the Bid Schedule. This price shall constitute full compensation for the furnishing of all labor, materials, and equipment necessary to remove and dispose of the full concrete pavement/steps section, including any/all concrete and stone subbase layers.

01 22 00-3

3.05 GRADE ENTIRE LIMIT OF DISTURBANCE

Measurement of this item will be based on a Lump Sum basis, of area to be disturbed and graded by Contractor relative to the site improvement work in accordance with the Project Manual and Drawings. The disturbed areas shall be graded prior to the placement of topsoil.

Payment to rough grade will be made at the applicable unit price listed in the Bid Schedule.

This price shall constitute full compensation for the furnishing of all labor, materials and equipment necessary to rough grade the project site, specifically the area fill area adjecnt to the retaining wall.

3.06 IMPORT AND SPREAD 6” DEPTH OF TOPSOIL

Measurement of this item will be based on the LUMP SUM of topsoil placed, and spread in accordance with the Project Manual and Drawings. Topsoil shall be imported and spread as necessary to achieve the proposed grades depicted on the plans.

Payment to import and spread 6-inch depth of topsoil will made be at the applicable unit price listed in the Bid Schedule. This price shall constitute full compensation for the furnishing of all labor, materials, and equipment necessary to import, place, and spread the topsoil as necessary to achieve the grades depicted on the plans.

3.07 SEED DISTURBED AREAS WITH FORMULA B PERMANENT SEED MIX

Measurement of this item will be based on a Lump Sum basis, of all disturbed areas adequately covered with seed in accordance with the Project Manual and Drawings.

Payment to seed disturbed areas with Formula B permanent seed mix will be made at the applicable unit price listed in the Bid Schedule. This price shall constitute full compensation for the furnishing of all labor, materials, and equipment necessary to install and maintain the seed to ensure that it survives as more fully defined in the Project Manual and shown on the Drawings.

END OF SECTION