This is a Contract Considerations document (Section 01 29 00) applicable to the 82 West Indian Lane FEMA Demolition project in West Norriton Township, Montgomery County, Pennsylvania. The document establishes procedural requirements for schedule of values, applications for payment, change orders, and project alternates. The Contractor must submit a preliminary Schedule of Values in duplicate within 10 days of the Effective Date of Agreement and revise it with each Application for Payment to reflect approved Change Orders. Monthly payment applications require submission of three copies in an acceptable format, including payroll certification forms, updated construction progress schedules, and waiver of liens documentation with the final payment application. The work scope includes demolition of the existing single-family home, removal of all buildings and associated impervious surfaces, erosion control, grading, soil compaction, trash and material removal, and local permitting, with all materials, equipment, tools, labor, and supervision provided by the Contractor.

Change procedures are addressed through multiple mechanisms: the Engineer may issue supplemental instructions for minor changes not affecting Contract Price or Time; Proposal Requests require the Contractor to submit estimates within 15 days for changes affecting price and/or time; Contractors may propose changes with full documentation of effects on price, time, and other contractors' work; and Change Orders may be executed as Stipulated Price, Unit Price, Work Change Directive, or Time and Material basis. For Time and Material changes, the Contractor must maintain detailed records and provide full supporting information within specified timeframes for Engineer evaluation. Accepted project add/deduct alternates and equipment add/deduct alternates will be identified in the Agreement. The document references related sections including the Agreement and Contract Price (Document 00 52 00), Measurement and Payment (Section 01 22 00), Submittals (Section 01 33 00), and Material and Equipment (Section 01 60 00).

View the file

Other files

File Type Posted
8-Doc 00 21 13 Instructions to Bidders.pdf PDF
14-Doc 00 61 13.16 Payment Bond.pdf PDF
1-00 82 W. Indian Lane FEMA Plans.pdf PDF
39-Sec 01 33 00 Submittals.pdf PDF
35-Sec 01 42 13 Organization and Reference Acronyms.pdf PDF
33-Sec 01 32 16 Construction Project Schedule.pdf PDF
42-Sec 01 70 00 Contract Closeout.pdf PDF
29-Doc 00 73 00 04 Appendix D - Hazard Mitigation Grant Conditions.pdf PDF
41-Sec 01 55 26 Traffic Regulation.pdf PDF
12-Doc 00 45 10 Bidders Acknowledgement Form.pdf PDF
9-Doc 00 45 13 Bidder Qualification Statement.pdf PDF
10-Doc 00 45 53 Agreement of Surety Company.pdf PDF
18-Doc 00 62 16 Certificate of Insurance.pdf PDF
27-Sec 01 11 13 Summary of Work.pdf PDF
7-Doc 00 21 13.1 Instructions for Electronic Bidding.pdf PDF
2-Doc 00 01 15 List of Drawing Sheets.pdf PDF
21-Doc 00 73 00 Supplementary Conditions.pdf PDF
28-Doc 00 73 00 01 Appendix A - Prevailing Wage Rates.pdf PDF
32-Sec 01 31 00 Coordination and Meetings.pdf PDF
24-Doc 00 91 13 Addenda.pdf PDF
17-Doc 00 65 19.13 Contractors Affidavit.pdf PDF
15-Doc 00 61 19 Maintenance Bond.pdf PDF
49-Sec 32 92 00 Finish Grading, Seeding and Sodding.pdf PDF
26-Doc 00 73 00 - Supplementary Conditions.pdf PDF
50-Sec 31 23 33 Excavation, Backfill and Compaction.pdf PDF
4-Doc 00 01 10 Table of Contents.pdf PDF
13-Doc 00 52 00 Agreement.pdf PDF
16-Doc 00 61 13.13 Performance Bond.pdf PDF
45-Sec 02 41 16 Demolition.pdf PDF
40-Sec 01 56 39 Landscape Protection.pdf PDF
34-Sec 01 35 16 Alteration Project Procedures.pdf PDF
22-Doc 00 72 00 General Conditions.pdf PDF
19-Doc 00 65 19.19 Consent of Surety.pdf PDF
5-Doc 00 43 13 Bid Bond.pdf PDF
6-Doc 00 11 13 Advertisement for Bids.pdf PDF
25-Sec 01 00 00 Basic Requirements.pdf PDF
37-Sec 01 50 00 Construction Facilities and Temporary Controls.pdf PDF
23-Doc 00 73 00 02 Appendix B - Public Works Employment Verification Form.pdf PDF
46-Sec 31 11 00 Clearing and Grubbing.pdf PDF
48-Sec 01 57 13 Soil Erosion and Sediment Control.pdf PDF
44-Sec 01 60 00 Material and Equipment.pdf PDF
20-Doc 00 65 19.16 Contractors Release of Liens.pdf PDF
3-Doc 00 01 01 Project Title Page.pdf PDF
38-Sec 01 40 00 Quality Control.pdf PDF
43-Sec 01 57 14 Erosion Control Blanket.pdf PDF
36-Sec 01 22 00 Measurement and Payment.pdf PDF
11-Doc 00 45 19 Non-Collusion Affidavit.pdf PDF
47-Sec 31 20 00 Earthwork.pdf PDF
30-Doc 00 73 00 03 Appendix C - Chapter 106 Permit.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT CONSIDERATIONS

01 29 00-1

SECTION 01 29 00

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Schedule of values.

2. Application for payment.

3. Change procedures.

4. Alternates.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Document 00 52 00: Agreement: Contract Price

2. Section 01 22 00: Measurement and Payment

3. Section 01 33 00: Submittals

4. Section 01 60 00: Material and Equipment

1.03 SCHEDULE OF VALUES

A. Submit a printed schedule on Contractor's standard form or electronic media printout.

B. Submit preliminary Schedule of Values in duplicate within 10 days after Effective Date of the Agreement.

C. Format: See Supplementary Conditions.

D. Include in each line item, the amount of allowance. For unit cost allowances, identify quantities taken from Contract Documents multiplied by the unit cost to achieve the total for the item.

E. Include within each line item, a direct proportional amount of Contractor's overhead and profit.

F. Revise schedule to list approved Change Orders, with each Application for Payment.

1.04 APPLICATIONS FOR PAYMENT

A. Submit three (3) copies of each application in an acceptable format.

B. Content and Format: Utilize Schedule of Values for listing items in Application for Payment.

C. Payment Period: Monthly.

01 29 00-2

D. Waiver of Liens or Contractor's Affidavit, Contractor's Release and Statement of Surety

Company (with Final Payment Application only).

E. Include Payroll Certification forms with each Payment Application.

F. Include an updated construction progress schedule.

1.05 CHANGE PROCEDURES

A. Engineer will advise of minor changes in the Work not involving an adjustment to Contract Price or Contract Time as authorized by Paragraph 9.06 of the General Conditions by issuing supplemental instructions.

B. Engineer may issue a Proposal Request which includes a detailed description of a proposed change with supplementary or revised Drawings and specifications. Contractor will prepare and submit an estimate within 15 days relative to changes in Contract Price and/or Contract Time.

C. Contractor may propose changes by submitting a request for change to Engineer, describing the proposed change and its full effect on the Work. Include a statement describing the reason for the change, and the effect on the Contract Price and Contract Time with full documentation and a statement describing effect on Work by any other contractors.

Document any requested substitutions in accordance with Section 01 60 00.

D. Stipulated Price Change Order: Based on Proposal Request and Contractor's fixed price quotation or Contractor's request for a Change Order as approved by Engineer.

E. Unit Price Change Order: For contract unit prices and quantities, the Change Order will be executed on a fixed unit price basis. For unit costs or quantities of units of work which are not predetermined, the Change Order will be executed based on Contractor's proposed unit prices and quantities of units as approved by Engineer.

F. Work Change Directive: Engineer may issue a directive, in an acceptable format, signed by

Owner, instructing Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order. Document will describe changes in the Work, and designate method of determining any change in Contract Price or Contract Time. Promptly execute the change.

G. Time and Material Change Order: Submit itemized account and supporting data after completion of change, within time limits indicated in the Conditions of the Contract. Engineer will determine the change allowable in Contract Price and Contract Time as provided in the Contract Documents.

H. Maintain detailed records of Work done on Time and Material basis. Provide full information required for evaluation of proposed changes, and to substantiate costs for changes in the Work.

I. Execution of Change Orders: Engineer will issue Change Orders for signatures of parties as provided in the Conditions of the Contract.

1.06 ALTERNATES

A. Accepted Project add/deduct alternates (and/or equipment add/deduct alternates) will be identified in the Agreement.

01 29 00-3

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION