32-Sec 01 31 00 Coordination and Meetings.pdf
PDF 100 KB Posted
- Attached to
- 82 W. Indian Lane - FEMA Demolition
- Solicitation number
- US.230082
- Issued by
- Montgomery County, Pennsylvania
About this file
This is a Section 01 31 00 specification document for Coordination and Meetings procedures applicable to the 82 West Indian Lane FEMA Demolition project in West Norriton Township, Montgomery County, Pennsylvania. The specification outlines the contractor's responsibilities for coordinating all project activities, including scheduling, submittals, and sequencing of construction work to ensure efficient installation of interdependent elements. Key procedural requirements include a mandatory preconstruction meeting to be scheduled by the Engineer after the Effective Date of the Agreement and prior to work commencement, with required attendance from the Owner, Engineer, Resident Project Representative, Contractor, Contractor's Superintendent, and major Subcontractors. The agenda for this meeting covers distribution of contract documents, submission of subcontractor lists, schedules of values, progress schedules, designation of contract personnel, processing procedures for field decisions and change orders, security and housekeeping procedures, testing requirements, and equipment start-up procedures. Progress meetings shall be scheduled on an as-needed basis throughout the work with the Resident Project Representative presiding and preparing meeting minutes for distribution within five working days to all participants.
The specification requires the contractor to coordinate utility requirements and verify compatibility of operating equipment with building utilities, manage space requirements and installation routing for mechanical and electrical work, and maintain efficient utilization of installation spaces for accessibility and maintenance purposes. The contractor must employ a registered Land Surveyor in Pennsylvania if deemed necessary and acceptable to the Engineer, though survey control and stakeout are not required for demolition activities on this project. Cutting and patching work must be performed by skilled and experienced installers with advance written requests submitted for any cutting or alterations affecting structural integrity, weather-resistant elements, equipment efficiency, visual qualities, or work of separate contractors. All cutting and patching must be executed to avoid damage to other work, with materials restored in accordance with contract document requirements and surfaces refinished to match adjacent finishes.
View the file
Other files
Show all 49
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COORDINATION AND MEETINGS
01 31 00-1
SECTION 01 31 00
PART 1 GENERAL
1.01 SECTION DESCRIPTION
A. The Work of this Section Includes:
1. Coordination and Project conditions.
2. Field engineering.
3. Preconstruction meeting.
4. Site mobilization meeting.
5. Progress meetings.
6. Pre-installation meetings.
7. Equipment electrical characteristics and components.
8. Cutting and patching.
9. Alteration Project procedures.
10. Construction coordination requirements.
1.02 RELATED SECTIONS
A. Related Work Specified Elsewhere:
1. Section 01 35 16: Alteration Project Procedures.
1.03 COORDINATION AND PROJECT CONDITIONS
A. Coordinate scheduling, submittals, and Work of the various sections of the Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements with provisions for accommodating items installed later.
B. Verify utility requirements and characteristics of operating equipment are compatible with building utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, such equipment.
C. Coordinate space requirements, supports, and installation of mechanical and electrical Work which are indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit, as closely as practicable; place runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.
E. Coordinate completion and clean-up of Work of separate sections in preparation for Substantial
Completion.
F. After Owner occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Owner’s
01 31 00-2 activities.
1.04 FIELD ENGINEERING
A. If deemed necessary by the Contractor, the Contractor shall employ a Land Surveyor registered in the Commonwealth of Pennsylvania and acceptable to Engineer.
B. Survey control, reference points, and stakeout are not necessary for construction activities associated with this project.
1.05 PRECONSTRUCTION MEETING
A. Engineer will schedule a meeting at the Project site after the Effective Date of the Agreement and prior to commencement of Work and Contractor occupancy, prepare an agenda with copies for participants, and preside at the meeting.
B. Attendance Required: Owner, Engineer, Resident Project Representative, Contractor, Contractor’s Superintendent and major Subcontractors.
C. Agenda:
1. Distribution of Contract Documents.
2. Submission of list of Subcontractors, list of Products, schedule of values, and progress schedule.
3. Designation of personnel representing the parties in Contract, and the Engineer.
4. Procedures and processing of field decisions, submittals, substitutions, applications for payments, Change Orders, and Contract closeout procedures.
5. Scheduling.
6. Use of premises by Owner and Contractor.
7. Owner's requirements.
8. Construction facilities and controls provided by Owner.
9. Temporary utilities provided by Owner.
10. Survey and layout.
11. Security and housekeeping procedures.
12 Procedures for testing.
13. Procedures for maintaining record documents.
14. Requirements for start-up of equipment.
15. Inspection and acceptance of equipment put into service during construction period.
D. Engineer shall record minutes and distribute copies within five (5) working days after meeting to
Owner and all other participants.
1.06 PROGRESS MEETINGS
A. Meetings shall be scheduled throughout progress of the Work on an as-needed basis.
B. Resident Project Representative will make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings.
C. Attendance Required: Contractor's superintendent, major Subcontractors and suppliers, Owner, Engineer, as appropriate to agenda topics for each meeting.
D. Agenda:
1. Review minutes of previous meetings.
2. Review of Work progress.
3. Field observations, problems, and decisions.
01 31 00-3
4. Identification of problems which impede planned progress.
5. Review of submittals schedule and status of submittals.
6. Review of off-site fabrication and delivery schedules.
7. Maintenance of progress schedule.
8. Corrective measures to regain projected schedules.
9. Planned progress during succeeding work period.
10. Coordination of projected progress.
11. Maintenance of quality and work standards.
12. Effect of proposed changes on progress schedule and coordination.
13. Other business relating to Work.
E. Resident Project Representative shall record minutes and distribute copies within five (5) working days after meeting to Owner, Engineer and all other participants.
PART 2 - PRODUCTS
2.01 Not Used
PART 3 - EXECUTION
3.01 CUTTING AND PATCHING
A. Employ a skilled and experienced installer to perform cutting and patching.
B. Submit written request in advance of cutting or altering elements which affect:
1. Structural integrity of element.
2. Integrity of weather-exposed or moisture-resistant elements.
3. Efficiency, maintenance, or safety of element.
4. Visual qualities of sight exposed elements.
5. Work of Owner or separate contractor.
C. Execute cutting, fitting, and patching to complete Work, and to:
1. Fit the several parts together, to integrate with other Work.
2. Uncover Work to install or correct ill-timed Work.
3. Remove and replace defective and non-conforming Work.
4. Remove samples of installed Work for testing.
5. Provide openings in elements of Work for penetrations of mechanical and electrical Work.
D. Execute work by methods to avoid damage to other Work, and which will provide proper surfaces to receive patching and finishing.
E. Cut masonry and concrete materials using masonry saw or core drill.
F. Restore Work with new Products in accordance with requirements of Contract Documents.
G. Fit Work tight to pipes, sleeves, ducts, conduit, and other penetrations through surfaces.
H. Maintain integrity of wall, ceiling, or floor construction; completely seal voids.
I. Refinish surfaces to match adjacent finishes. For continuous surfaces, refinish to nearest intersection; for an assembly, refinish entire unit.
J. Identify hazardous substances or conditions exposed during the Work to Engineer for decision or remedy.
END OF SECTION